Royal Bafokeng Platinum — FY2012 Earnings Presentation
43 slides from Royal Bafokeng Platinum's earnings presentation, 2013

Slide 1: Royal Bafokeng Platinum Annual Results for the year ended 31 December 2012
Royal Bafokeng Platinum Annual Results for the year ended 31 December 2012

Slide 2: Agenda
1 > Overview 2 > Safety 3 > Market review 4 > Operational review and project update 5 > Financial review 6 > Outlook and conclusion RBPLAT ANNUAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2012 >2

Slide 3: Overview
SECTION 1 Overview >3

Slide 4: Strong performance in difficult operating environment
Strong performance in difficult operating environment… Achievements > 1.78 million fatality-free shifts • Regrettably one employee fatally injured in fall of ground incident > Tonnes milled of 2375kt (up 3%) > Immediately stopable reserve (IMS) face length of 5 710 metres (up 25%) > Working cost lab

Slide 5: Safety
SECTION 2 Safety >5

Slide 6: Safety performance – significant progress
Safety performance – significant progress Description Unit 2010 2011 2012 Var Var % LTIFR SIFR Fatal injuries No. 3 0 1 -1 100% 1.20 LTIFR /200 000 0.95 0.91 0.68 0.23 26% 0.60 SIFR /200 000 0.53 0.47 0.42 0.05 10% 0.53 0.95 1.00 0.50 0.47 0.91 0.42 > 1 FOG fatality 6th February – North shaft 0.80 0

Slide 7: Safety stoppages
Safety stoppages Safety stoppages Classification 140 Ministerial 116.7 audit, 11.48 120 kt, 10% 100 91.6 kt Milled 80 61.6 Fatal 60 accident & follow-up, 40 28.3 64.04 kt, 25.8 55% 20 Routine 1.0 visits, 41.23 - kt, 35% Total Q1 Q2 Q3 Q4 Total 2011 2012 2012 2012 2012 2012 Safety stoppages Unit 2010

Slide 8: Market review
SECTION 3 = Market review =~

Slide 9: Platinum production forecast downwards from 2011 estimates
Platinum production forecast downwards from 2011 estimates > Global platinum production dropped ca 8.6% to South African planned platinum production forecast 5.6Moz in 2012 (Pt koz) > Platinum recycling reduced by ca 85koz to 1.76Moz 6 000 due to softer prices resulting in total supply for 2012 decl

Slide 10: Platinum demand expected to grow marginally in 2013
Platinum demand expected to grow marginally in 2013… Platinum demand 7 900 7 800 koz 7 700 y-o-y growth=1.9% 7 850 7 600 7 710 7 500 Auto Jewellery Other +40 koz -20 koz +130 koz 7 400 US W.Europe Japan China India ROW US W.Europe Japan China ROW 2012 Auto Jewellery Chemical Electrical Glass Other O

Slide 11: Palladium market deficit expected to widen further
Palladium market deficit expected to widen further… Palladium demand 9 800 9 700 koz 9 600 y-o-y growth = 3.2% 9 500 9 770 9 400 9 460 9 300 Auto Jewellery Other +210 koz +30 koz +60 koz 9 200 US W.Europe Japan China India ROW US W.Europe Japan China ROW 2012 Auto Jewellery Chemical Electrical Denta

Slide 12: Rhodium close to balance with market set to tighten in 2014
Rhodium close to balance with market set to tighten in 2014 to Rhodium demand 1 020 1 000 980 960 koz 940 year-on-year growth = 6.8% 1 000 920 940 Auto Total 900 +60 koz +60 koz 880 US W.Europe Japan China India ROW 2012 Auto Chemical Electrical Glass Other 2013 Source: SFA Oxford > Rhodium market e

Slide 13: Operational review and project update
SECTION 4 Operational review and project update > 13

Slide 14: Operational review
Operational review > Operating strategy > Increase development > IMS face length up 25% • Increase development • Cost increase > Tonnes milled up 3% • Increase IMS • Grade dilution • Develop UG2 platform • Improved flexibility • UG2 • Stockpile > Head grade down 6.4% • Development dilution > Mining

Slide 15: Mining
Mining Description Unit 2010 2011 2012 Var Var % Tonnes delivered - Total kt 2366 2284 2384 100 4% Production losses Tonnes delivered - MER kt 2288 2026 1899 -127 -6% 200 Tonnes delivered - UG2 kt 78 258 425 167 65% UG2% % 3% 11% 18% 7% 7% 68 kt 70 kt 150 Surface sources (MER) kt 0 0 60 60 100% 7.8

Slide 16: Grade forecast
Grade forecast Grade forecast 5.00 25% 4.50 4.00 20% 3.50 Grade (4E) g/t 3.00 15% 2.50 2.00 10% 1.50 1.00 5% 0.50 0.00 0% 2010 2011 2012 2013 2014 2015 2016 2017 Grade (4E) g/t UG2 BRPM > Forecast • Forecast grades at 4.1 - 4.2g/t 4E • Normalisation of development to stoping ratio • UG2 contribution

Slide 17: Concentrating
Concentrating Description Unit 2010 2011 2012 Var Var % BRPM Concentrator recovery Tonnes milled - Total kt 2407 2305 2375 70 3% Tonnes milled - MER kt 2329 2047 1898 -149 -7% 87.83 14% 91.00 86.49 87.21 Tonnes milled - UG2 kt 78 258 417 159 61% Tonnes milled - Stockpile (MER) kt 0 0 60 60 100% 81.0

Slide 18: Labour
Labour Description Unit 2010 2011 2012 Var Var % Working cost labour Labour - Total No. 7670 7942 7743 199 3% 8 000 6 793 6 553 Labour - working cost No. 6793 6553 6057 496 8% 7 000 6 057 Labour - capital No. 877 1389 1686 -297 -21% 6 000 Stoping effeciency - total m 2 /crew 343 308 307 -1 0% 5 000

Slide 19: Operating expenditure
Operating expenditure Description Unit 2010 2011 2012 Var Var % Key drivers Cash operating costs R'm 1700 1802 2051 -248 -14% Cash unit cost R/t 707 782 864 -82 -10% > Inflation Cash unit cost R/4E oz 5901 6399 7616 -1217 -19% • Electricity (16.7%) Cash unit cost R/Pt oz 9076 9863 11775 -1911 -19% •

Slide 20: Operating expenditure continued
Operating expenditure….continued Cash cost breakdown Process unit costs 1 002 2011 cash costs 2012 cash costs 902 802 120 Sundries 12% 702 124 Sundries 13% 111 134 Utilities 8% Labour R/t milled 602 120 Utilities 8% Labour 37% 105 37% 502 402 Stores 20% Stores 21% 302 609 539 490 202 Contractors 21%

Slide 21: Capital expenditure
Capital expenditure BRPM JV capital cashflow Description Unit 2010 2011 2012 Var Var % 3 500 225 200 Total capex R'm 966 1164 1192 29 2% 3 000 192 214 Expansion R'm 490 638 646 8 1% 2 500 Styldrift I R'm 480 631 635 4 1% 175 Styldrfit II R'm 0 5 9 4 -80% 2 000 228 R'm BRPM concentrator upgrade R'm 9

Slide 22: BRPM replacement projects
BRPM replacement projects Phase II : Decline extension : level 6 to level 10 Description Unit Plan Act Var > North shaft completed : Sept 2011 N# % complete % Complete Complete Complete > South shaft completed : Sept 2012 S# % complete % Complete Complete Complete > R110 million saving Cost at compl

Slide 23: Styldrift I Project
Styldrift I Project > 23

Slide 24: Styldrift project progress
Styldrift project progress Description Unit Plan Actual Var Optimisation study Progress • Bord widths reduced from 13m to 8m Overall progress % 32 34 1.9 • Ramp-up extended from 27 to 36 months Main shaft m 616 614 -2 • Footwall trucking replaced by on reef conveyors Service shaft m 635 636 1 • Shaf

Slide 25: 600 level reef intersection: Merensky Reef grade profile
600 level reef intersection Merensky Reef grade profile Grade (g/t) 4E 0 2 4 6 8 10 12 14 16 18 20 22 0.1 0.2 Mining Width 0.3 1.8 to 2.0m 0.4 Merensky Pyroxenite 0.5 0.6 0.7 BRC chrome Pegmatoidal Pyroxenite 0.8 0.9 Width (m) 1.0 1.1 Bottom Reef Contact 1.2 1.3 1.4 Mottled Anorthosite 1.5 1.6 1.7 1

Slide 26: Styldrift schedule & cash flow
Styldrift schedule & cash flow Project Phase 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Engineering & Design 2008 - 2015 Pre-Sink Infrastructure 2009 - 2011 • Rock winder Surface Infrastructure 2010 - 2016 • Main offices • Change house Main Shaft Sinking • Surface silos 2011 - 2014

Slide 27: Surface layout
Surface layout SD # & Plant BRPM N# BRPM Plant BRPM S# BRPM Tailings SD Tailings RBPLAT ANNUAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2012 > 27

Slide 28: Styldrift II Study Project
Styldrift II Study Project > 28

Slide 29: Styldrift II
Styldrift II > Concept study • Completed in May 2012 • Technical review completed in October 2012 • Pre-feasibility study approved > Pre-feasibility • Initiated in November 2012 • Completion planned for H2 2014 > Additional 27 000m of exploration drilling planned for 2013 RBPLAT ANNUAL RESULTS FOR T

Slide 30: Financial review
SECTION 5 Financial review > 30

Slide 31: Key financial performance indicators
Key financial performance indicators Year ended Year ended Description Unit % Change 31 December 2012 31 December 2011 Average basket price* R/Pt oz 16 404 16 282 0.7 Average Rand:US$ received R/US$ 8.21 7.26 13.1 Revenue R’m 2 865.3 2 974.9 3.7 Cost of sales R’m 2 525.5 2 408.7 4.9 Gross profit R’m

Slide 32: Key financial performance indicators continued
Key financial performance indicators… continued Year ended Year ended Description Unit % Change 31 December 2012 31 December 2011 Headline earnings R’m 170.3 273.7 37.8 Weighted average shares outstanding #’m 164.0 163.7 0.2 HEPS R/share 1.04 1.67 37.7 Fair Value depreciation and amortisation R/shar

Slide 33: Key financial performance indicators continued
Key financial performance indicators…continued Year ended Year ended Description Unit % Change 31 December 2012 31 December 2011 Cash generated by operating activities R’m 732.6 1 025.1 28.9 Cash, net of debt (incl. pref share investment) R’m 910.5 1 364.1 33.3 Capital expenditure (100% BRPM) R’m 1

Slide 34: Revenue contribution by metal
Revenue contribution by metal 2012 1.3% 2.3% Year ended Average price 0.6% Description 31 December 2012 achieved* 3.7% 0.3% Pt 68.1% 4.2% Sales volume (US$) Pd 11.7% Ni 8.0% Platinum (oz) 174 665 1 552/oz 8.0% Rh 4.2% Au 3.7% 11.7% Palladium (oz) 72 007 649/oz Cu 2.3% 68.1% Ir 1.3% Gold (oz) 8 761 1

Slide 35: Cost of sales breakdown
Cost of sales breakdown 2012 2012 2011 2011 Description R million % of Total R million % of Total Labour 753.1 34.3% 673.9 35.7% Utilities 171.1 7.8% 144.5 7.6% Contractor costs 478.4 21.8% 377.0 19.9% Materials and other mining costs 648.0 29.5% 583.3 30.9% Total cash costs excl once–off costs 2 05

Slide 36: Headline earnings variance analysis
Headline earnings variance analysis 347.0 400 69.5 350 190.7 173.2 144.4 258.8 273.3 300 16.1 250 200 12.1 54.0 170.3 27.2 32.1 107.9 150 78.0 100 2.6 1.4 50 0 RBPLAT ANNUAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2012 > 36

Slide 37: Cash flow analysis
Cash flow analysis 2 500.0 732.6 238.0 2 000.0 310.0 625.9 1 500.0 1364.0 R’m 1 000.0 RBPlat 4.2 910.5 980.8 8.0 RBPlat 599.4 500.0 BRPM JV BRPM JV 383.2 311.1 0.0 Cashand Cash andcash cash Cash generated by SIB Capex Replacement Capex Expansion Capex Increase in Reduction in the Cashand Cash andcas

Slide 38: Year in review and future outlook
Year in review and future outlook 2012 2013 Cash management Capex funding > Deferment of R462 million in project capital > Accelerated Styldrift I capital expenditure expenditure profile > Utilisation of surplus funds to fund shortfall > Increased utilisation of surplus cash on expansion capital exp

Slide 39: Outlook and Conclusion
SECTION 6 Outlook and Conclusion > 39

Slide 40: Long-term Merensky bias
Long-term Merensky bias > Industry : 2000 vs 2012 • Merensky contribution declined from 70% to 30% • Average head grade reduced by 40% • Platinum production per employee reduce by 40% > Styldrift • High grade Merensky • Pt:Pd ratio of 2.3 : 1 • High base metal revenue contribution • Low cost mechani

Slide 41: Styldrift project benchmark
Styldrift project benchmark 3 al 2 bult la la Ama pala ds ift 1 ekra Impa Impa Tow K4 ndel e nlan izw RBP # S# Im N r e d Styld Kare Paar Wes RBP 20# 16# 17# 0.00 500.00 1 000.00 1 500.00 Source : SFA Oxford 2 000.00 2 500.00 South Africa: 2010 South Africa: 2020 > Styldrift is a high quality Merens

Slide 42: We believe our strategic goals remain relevant
We believe our strategic goals remain relevant... Outlook Key focus areas Market > Platinum and palladium deficits expected to > Further safety performance improvements continue to widen due to constrained output from South Africa, this is expected to have a > Operating costs positive impact on meta

Slide 43: www.bafokengplatinum.co.za
The Pivot, No 1 Monte Casino Boulevard Block C, Floor 4, Fourways Johannesburg, 2021 PO Box 2283 Fourways, 2055 South Africa Telephone: +27 (0)10 590 4510 Telefax: +27 086 572 8047 www.bafokengplatinum.co.za
Source: Internet Archive copy of implats.co.za
More decks from Royal Bafokeng Platinum Ltd
Renaissance Capital Metals & Mining Conference 202118 slides · May 2021
H1 2020 Earnings Presentation39 slides · 2020
Merger or Acquisition (October 2019)11 slides · Oct 16, 2019
RBPlat Analyst Roundtable 201910 slides · Aug 6, 2019
Technical Presentation (February 2019)34 slides · Feb 1, 2019
Fact Sheet (2019)11 slides · 2019