Studies
| Study | Date | Project | Study | NPV | IRR |
|---|
| AGMR FILES AMENDED AND RESTATED TECHNICAL REPORT FOR THE RELIQUIAS MINE | Oct 28, 2024 | Reliquias Mine | Technical report | | |
|---|
| Silver Mountain Delivers Positive Preliminary Economic Assessment For Its Reliquias Project, Peru; Pre-Tax NPV 5% Of C$107 million, Pre-Tax IRR Of 57%, And Payback Of 1.8 Years | May 15, 2024 | Reliquias Project | Preliminary economic assessment | C$85M, after-tax, 5% | 51%, after-tax |
|---|
| SILVER MOUNTAIN FILES NI 43-101 TECHNICAL REPORT FOR PREVIOUSLY ANNOUNCED UPDATED MINERAL RESOURCE ESTIMATE AT THE RELIQUIAS PROJECT | Mar 19, 2024 | Reliquias project | Technical report | | |
|---|
| SILVER MOUNTAIN FILES NI 43-101 TECHNICAL REPORT FOR PREVIOUSLY ANNOUNCED MINERAL RESOURCE ESTIMATE AT THE RELIQUIAS MINE | May 15, 2023 | Reliquias mine | Technical report | | |
|---|
| SILVER MOUNTAIN DELIVERS INITIAL NI 43-101 COMPLIANT MINERAL RESOURCE ESTIMATE FOR RELIQUIAS MINE | Apr 12, 2023 | Reliquias mine | Technical report | | |
|---|