Musuma-1 Wellpad Completed

· Issued by Invictus Energy Limited

Filed with ASX · · 4 pages · English

• Musuma-1 wellpad construction completed, including all associated civil works and access road upgrades. • Drilling contractor Exalo has formally accepted and signed off the completed wellpad, clearing a key milestone ahead of the rig move. • Exalo Rig 202 to relocate from Mukuyu -2 to Musuma-1, ahead of rig-up and completion of remaining rig maintenance activities. • Following rig-up and mainten