Atalaya Mining Copper Sa · LSE:ATYM

Atalaya Mining Copper Sa — Q1 2025 Earnings Presentation

28 slides from Atalaya Mining Copper Sa's earnings presentation, May 29, 2025

  1. Slide 1: European copper producer with operations in Spain

    European copper producer with operations in Spain Q1 2025 Financial Results 29 May 2025

  2. Slide 2: Disclaimer

    Disclaimer The information contained in this document (“Presentation”) has been prepared by Atalaya Mining (the “Company”). While the information contained herein has been prepared in good faith, neither the Company nor any of its shareholders, directors, officers, agents, employees or advisers give

  3. Slide 3: Disclaimer: Technical Disclosure

    Disclaimer: Technical Disclosure Technical Disclosure – Proyecto Riotinto Unless otherwise noted, all scientific and technical information relating to Proyecto Riotinto is based on and derived from a Competent Persons Report (CPR) entitled “An Independent Competent Persons Report on the Mineral Asse

  4. Slide 4: Q1 2025 Financial Results

    Q1 2025 Financial Results

  5. Slide 5: Review of Q1 2025

    Review of Q1 2025 Strong results including the highest quarterly EBITDA in Atalaya history ‒ Copper production of 14.3 kt, the best quarter since Q2 2021, mainly due to higher grades and higher ore processed Operating ‒ Cash Cost of $2.25/lb, due to higher production, higher silver credits and lower

  6. Slide 6: Q1 2025 Production Results

    Q1 2025 Production Results Strong start to 2025 with best quarter of production since Q2 2021 Copper production Ore Throughput (Mt) 14,291 tonnes Cu 10,666 tonnes Cu | Q1 2024 Throughput & recoveries 4.2 Mt ore processed 0.42% Cu grade Copper Recovery 3.7 Mt | Q1 2024 0.34% | Q1 2024 80.98% Cu recov

  7. Slide 7: Q1 2025 Financial Results

    Q1 2025 Financial Results Strong results including the highest quarterly EBITDA in Atalaya history Income statement highlights Revenues (€m) Revenue: €130.7m Op. costs: €(78.2)m €69.9m | Q1 2024 €(59.7)m | Q1 2024 EBITDA: €52.5m Profits: €30.5m €10.3m | Q1 2024 €1.6m | Q1 2024 Cash flow statement hi

  8. Slide 8: Cash Costs & AISC Breakdown

    Cash Costs & AISC Breakdown Good cost performance driven by higher production and lower offsite costs $/lb Copper Payable Q1 2025 Q1 2024 FY2024 FY2023 ▪ Q1 2025 Cash Mining 0.85 0.99 1.07 0.86 Cost and AISC were well Processing 0.80 0.91 0.90 0.89 below FY2025 Other site operating costs 0.51 0.67 0

  9. Slide 9: AISC Benchmarking

    AISC Benchmarking ATYM cost positioning is competitive vs. notable copper producer peers Reported AISC (US$/lb) Atalaya 29Metals Capstone First Quantum Constancia Copper Mountain Candelaria Caserones Neves-Corvo Lumwana Zaldívar (Hudbay) (now Hudbay) (Lundin) (Lundin) (now Boliden) (Barrick) (Antofa

  10. Slide 10: 2025 Outlook

    ATALAYA MINING > 2025 Outlook

  11. Slide 11: 2025 Guidance: Unchanged

    2025 Guidance: Unchanged Strong start to 2025 supports full-year outlook Operational Guidance ▪ Production Ore mined Mt 15 – 16 ‒ Q1 2025 was best quarter of production since Q2 2021 Waste mined (1) Mt 37 – 43 ‒ Guidance is weighted slightly towards H1 2025 Ore processed Mt 15.5 – 15.8 ▪ Costs Coppe

  12. Slide 12: San Dionisio

    San Dionisio Granted environmental approval; expected to contribute higher-grade material May 2025 Copper Resource Grade (M&I) 12

  13. Slide 13: Highway Relocation Progress

    Highway Relocation Progress Development progress continues 13

  14. Slide 14: E-LIX Phase I Plant

    E-LIX Phase I Plant Ramp-up continues, with novel leaching section performing well Illustrative Recoveries 14

  15. Slide 15: PMV: Access Ramp

    PMV: Access Ramp Ramp works to begin in coming months; initial focus on high grade copper zone Wireframes of Mineralised Zones Planned Ramp Access for MV and MJ 15

  16. Slide 16: Touro: Positive Attributes

    Touro: Positive Attributes Low capital intensity and good ore characteristics to drive strong economics Touro(1) Riotinto Copper Production ktpa ~30 50+ Initial Capex US$m $250 – 300 Capex Intensity US$/t produced <$10,000 Strip Ratio w:o ~2.0 ~2.2 Copper Grade ~0.42% 0.37% Copper Recovery ~90% ~85%

  17. Slide 17: Key Activities for 2025

    Key Activities for 2025 San Dionisio: Environmental authorisation approved; stripping activities continue Masa Valverde: Start development of access ramp Touro: Advance permitting process under Galicia’s strategic industrial project legislation E-LIX: Finalise commissioning and ramp-up San Antonio:

  18. Slide 18: Conclusion

    ATALAYA MINING > Conclusion

  19. Slide 19: Illustrative Production Potential

    Illustrative Production Potential Growth driven by higher grades at Riotinto and potential Touro development Copper Equivalent Production (kt)(1)(2) 1. Recovered metal in concentrate. 2. Copper Equivalent production is calculated from results presented in the 2023 Riotinto PEA and based on $3.50/lb

  20. Slide 20: Conclusion

    Conclusion ▪ MAP 48 – 52 kt copper production $742m Enterprise Value ▪ ASSETS 2025 guidance Equivalent to ~$15,000/t copper production >100 ktpa CuEq potential from existing projects €38m net cash No streams or royalties Low risk growth drivers: ‒ Higher grades ‒ Satellite deposits €78m dividends de

  21. Slide 21: Appendix

    ATALAYA MINING > Appendix

  22. Slide 22: Key Information

    Key Information Capitalisation Share Price Performance (GBp) Ticker - LSE: Main Market ATYM Share price (26-May-25) GBp 411.5 Basic shares m 140.8 Fully-diluted shares m 146.2 Market capitalisation (basic) £m 579 Market capitalisation (basic) US$m $786 Cash (at 31-Mar) €m 70 Debt (at 31-Mar) €m 32 E

  23. Slide 23: Earn-in Agreements in Sweden

    Earn-in Agreements in Sweden Opportunity to enter prospective mining districts with an experienced partner ▪ In November 2024, Atalaya announced agreements with Mineral Prospektering i Sverige AB ("MPS“) whereby Atalaya can earn initial 75% interests in the Skellefte Belt and Rockliden projects ‒ Su

  24. Slide 24: Electricity Prices in Spain

    Electricity Prices in Spain Stability has returned to market electricity prices Spot Market + Adjustment in Spanish System (€/MWh)(1)(2) 1. Source: OMI, Polo Español S.A. (OMIE), day-ahead operations program 2. Since 15-Jun-2022, includes daily adjustment mechanism related to legislated gas cap 24

  25. Slide 25: Reserves and Resources

    Reserves and Resources Attributable Grade Contained Metal Contained Metal Asset Ownership Tonnage Cu Zn Pb Au Ag Cu Zn Pb Au Ag CuEq Cu CuEq Notes Mt g/t g/t Mt Mt Mt Moz Moz Mt Mt Mt Cerro Colorado 100% Reserves 132.0 0.37% - - - - 0.5 - - - - 0.5 0.5 0.5 M&I 156.6 0.37% 0.15% 0.03% - - 0.6 0.2 0.0

  26. Slide 26: Senior Management

    Senior Management Decades of operations, project development and financial expertise Alberto Lavandeira César Sánchez Enrique Delgado Chief Executive Officer, Director Chief Financial Officer Operations – General Manager, Proyecto Riotinto Over 40 years’ experience Former CFO of companies in Former

  27. Slide 27: Board of Directors

    Board of Directors Mining, capital markets, sustainability and finance expertise Non-Executive Over 30 years’ experience investing in mining and oil and gas companies. From 2010-2020, was a Managing Director at J.P. Neil Chair of the Morgan Asset Management. Before that, from 1990-2009, was Head of

  28. Slide 28: Atalaya Mining Copper, S.A. Investor Relations

    Contacts: Atalaya Mining Copper, S.A. Alberto Lavandeira, CEO +34 959 59 28 50 info@atalayamining.com Investor Relations Michael Rechsteiner michael.rechsteiner@atalayamining.com