H.g. Infra Engineering Ltd. · NSE:HGINFRA

H.g. Infra Engineering — Q1 FY26 Earnings Presentation

14 slides from H.g. Infra Engineering's earnings presentation, Aug 13, 2025

  1. Slide 1: Exchange filing cover letter: Investor Presentation Q1 FY26

    HGIEL/HO/COMPLIANCE/2025-26/521 August 13, 2025 BSE Limited National Stock Exchange of India Limited Phiroze Jeejeebhoy Towers Exchange Plaza, C-1, Block G Dalal Street Bandra Kurla Complex, Bandra (East) Mumbai- 400 001 Mumbai- 400 051 Scrip Code- 541019 Scrip Symbol- HGINFRA Dear Sir/Madam, Sub: I

  2. Slide 2: Diversifying and Progressing: Investor Presentation – Q1 FY26

    H.G. INFRA ENGINEERING Ltd. Potential. Prudence. Performance Diversifying and Progressing Investor Presentation – Q1 FY26 www.hginfra.com

  3. Slide 3: HG Infra: Redefining India's Infrastructure

    HG Infra : Redefining India’s Infrastructure 13 states Business Segments PAN India Presence across Roads & Railway & Solar Metro Highways 3000+ Modern Fleet Equipment 29+ Transmission Active Projects Battery Energy and Storage System Distribution 5300+ Employees BUIL DING BLO CKS OF H.G 22.5% 22.7%

  4. Slide 4: Q1 FY25-26 Operational Highlights

    Q1 FY25-26 Operational Highlights 3

  5. Slide 5: Robust & Diversified Orderbook as of June 2025

    Robust & Diversified Orderbook as of June 2025 Project Type Sector Authority % Completion Orderbook Presence in 13 States Karnal Munak Road 77.1% 2,039 Varanasi Ranchi Kolkata Highway P 10 6.2% 10,411 Varanasi-Ranchi-Kolkata Highway P 13 10.4% 7,169 Uttar Pradesh 8% Raipur-Visakhapatnam OD5 91.3% 1,

  6. Slide 6: Significant Events and update on Q1FY25-26

    Significant Events and update on Q1FY25-26 New Projects: Client Mode Project Name Tarif per MW Contract Duration EPC Cost State LOA Date 28.05.2025 Setting Up 300 MW/600MWh 12 Years from the project GUVNL BESS ₹2,85,600 ₹6,465 Mn Gujarat L1 intimation on commissioning date battery energy Storage Sys

  7. Slide 7: Significant Events and update on Q1FY25-26

    Significant Events and update on Q1FY25-26 Declaration of Completion date: Client Project Name Completion Date PCC-01 issued w.e.f. 04.01.2025 1 OD-Package 05 (Odisha) Vide intimation dated 25.04.2025 PCC-01 issued w.e.f. 08.01.2025 2 OD-Package 06 (Odisha) Vide intimation dated 25.04.2025 PCC-01 is

  8. Slide 8: Update on HAM Projects

    Update on HAM Projects 7

  9. Slide 9: Expanding HAM Projects

    Expanding HAM Projects All figures in ₹ Million Expanding order book, equity commitment comfortably met Total Invested Awarding Grant Debt as on Jun Project State Kms BPC Sanctioned Equity till Jun Authority Amount 2026 Debt FY26 Khammam Devarapalle Pkg-1 NHAI Telangana 33.6 7,721* 3,088 3,100 1,115

  10. Slide 10: Q1 FY25-26 Financials Highlights

    Q1 FY25-26 Financials Highlights 9

  11. Slide 11: Standalone Results Highlights Q1FY26

    Standalone Results Highlights Q1FY26 Revenue from Operations (Rs. Mn) EBITDA (Rs. Mn) & EBITDA Margin % 17,092 16.16% 13.79% 15,059 2,433 2,357 Q1 FY25 Q1 FY26 Q1 FY25 Q1 FY26 Profit Before Tax (Rs. Mn) & PBT Margin % Profit After Tax (Rs. Mn) & PAT Margin % 12.59% 9.79% 9.27% 7.34% 1,897 1,674 1,39

  12. Slide 12: Q1 FY26 Profit & Loss Statement

    Q1 FY26 Profit & Loss Statement Standalone Consolidated Particulars (Rs. Mn) Q1 FY26 Q1 FY25 YoY Q1 FY26 Q1 FY25 YoY Revenue From Operations 17,092.43 15,058.81 13.5% 14,822.02 15,280.39 -3.0% Cost of Materials Consumed 7,957.52 6,748.61 6,334.20 6,748.61 Contract & Site Cost 5,520.24 4,918.44 4,606

  13. Slide 13: Disclaimer

    Disclaimer This presentation and the accompanying slides (the “Presentation”), which have been prepared by HG Infra Engineering Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any s

  14. Slide 14: Thank you

    COMPANY CONTACT Rajeev Mishra (CFO) rajeev.mishra@hginfra.com III Floor, Sheel Mohar Plaza, A-1, Tilak Marg, C-Scheme, Jaipur - 302001 INVESTOR RELATION CONTACT / Go India Advisors Saloni Ajmera +91 9930577801 saloni@goindiaadvisors.com Selina Sheikh +91 84338 18768 selina@goindiaadvisors.com Thank

H.G. Infra Engineering — Q1 FY26 Earnings Presentation on 6ix