H.g. Infra Engineering Ltd. · NSE:HGINFRA
H.g. Infra Engineering — Q3 FY26 Earnings Presentation
15 slides from H.g. Infra Engineering's earnings presentation, Feb 12, 2026
Slide 1: Exchange filing cover letter for Investor Presentation Q3 & 9MFY26
HGIEL/HO/COMPLIANCE/2025-26/594 February 12, 2026 BSE Limited National Stock Exchange of India Limited Phiroze Jeejeebhoy Towers Exchange Plaza, C-1, Block G Dalal Street Bandra Kurla Complex, Bandra (East) Mumbai- 400 001 Mumbai- 400 051 Scrip Code- 541019/977063 Scrip Symbol- HGINFRA Dear Sir/Mada
Slide 2: H.G. Infra Engineering Ltd. Investor Presentation – Q3 & 9MFY26
H.G. INFRA ENGINEERING LTD. Building Highways, Connecting Destinations Celebrating 23 Years of Trust, Passion and Quality www.hginfra.com Investor Presentation – Q3 & 9MFY26
Slide 3: Operational & Orderbook Highlights
Operational & Orderbook Highlights
Slide 4: Robust & Diversified Orderbook as December 2025
Robust & Diversified Orderbook as December 2025 Project Authority Sector Type Type % Completion Orderbook Karnal Munak Road 94.2% 555 Uttar Pradesh 7.6% Varanasi Ranchi Kolkata Highway P 10 9.0% 10,101 Varanasi-Ranchi-Kolkata Highway P 13 NHAI 19.4% 6,449 Telangana 0.2% Other HAM Projects (OD-5, OD-
Slide 5: Significant Events and update on New Projects till Q3FY26
Significant Events and update on New Projects till Q3FY26 New Projects: Client Mode Project Name Tarif per MW Contract Duration EPC Cost State LOA Date 28.05.2025 Setting Up 300 MW/600MWh 12 Years from the project GUVNL BESS ₹2,85,600 ₹6,465 Mn Gujarat L1 intimation on battery energy Storage System
Slide 6: Significant Events and update on New Projects till Q3FY26
Significant Events and update on New Projects till Q3FY26 Declaration of provisional completion date: Client Project Name Completion Date 1 PCC-02 w.e.f 31.03.2025 OD-Package 05 (Odisha) vide dated 21.08.2025 2 PCC-02 w.e.f 31.03.2025 OD-Package 06 (Odisha) vide dated 21.08.2025 3 PCC-01 w.e.f. 28.0
Slide 7: Significant Events and update on New Projects till Q3FY26
Significant Events and update on New Projects till Q3FY26 Completion Certificate: Client Project Name Completion Date w.e.f 25.05.2023 1 Rewari Bypass Package -4 vide dated 02.05.2025 w.e.f 31.12.2023 2 Delhi-Vadodara Package-9 vide dated 16.10.2025 Agreement Signing: Client Mode Project Name State
Slide 8: Update on HAM Projects
Update on HAM Projects
Slide 9: Expanding HAM Projects
Expanding HAM Projects All figures in ₹ Million Expanding order book, equity commitment comfortably met Total Invested Awarding Grant Debt as on Project State Kms BPC Sanctioned Equity till Dec Authority Amount Dec 2025 Debt FY26 Khammam Devarapalle Pkg-1 NHAI Telangana 33.6 7,721* 3,088 3,100 1,270
Slide 10: Financial Highlights
Financial Highlights
Slide 11: Standalone Highlights – Q3 FY26 & 9M FY26
Standalone Highlights – Q3 FY26 & 9M FY26 All figures in INR Million Revenue EBITDA PAT 16.6% 15.5% 9.1% 6.7% 15,085 14,498 2,501 2,243 Q3FY26 1,366 969 Q3FY25 Q3FY26 Q3FY25 Q3FY26 Q3FY25 Q3FY26 14.1% 8.9% 6.7% 16.4% 40,789 43,128 3,647 6,678 2,896 9MFY26 6,066 9M FY25 9M FY26 9M FY25 9M FY26 9MFY25
Slide 12: Consolidated Highlights – Q3 FY26 & 9MFY26
Consolidated Highlights – Q3 FY26 & 9MFY26 All figures in INR Million Revenue EBITDA PAT 22.7% 21.7% 9.1% 6.6% 2,869 3,088 14,212 12,648 Q3FY26 1,151 941 Q3FY25 Q3FY26 Q3FY25 Q3FY26 Q3FY25 Q3FY26 20.3% 16% 9.7% 6.4% 22.2% 36,953 38,079 8,187 7,747 9MFY26 3,584 2,452 9MFY25 9MFY26 9MFY25 9MFY26 9MFY2
Slide 13: Q3 FY26 Profit & Loss Statement
Q3 FY26 Profit & Loss Statement Standalone Consolidated Particulars (Rs. Mn) Q3 FY26 Q3 FY25 YoY Q3 FY26 Q3 FY25 YoY Revenue From Operations 14,497.67 15,085.38 -3.9% 14,211.60 12,648.41 12.4% Cost of Materials Consumed 5,776.91 5,840.05 5,215.51 4,599.56 Contract & Site Cost 5,447.37 5,691.58 4,850
Slide 14: 9M FY26 Profit & Loss Statement
9M FY26 Profit & Loss Statement Standalone Consolidated Particulars (Rs. Mn) 9M FY26 9M FY25 YoY 9M FY26 9M FY25 YoY Revenue From Operations 43,127.57 40,788.71 5.7% 38,078.65 36,952.88 3.0% Cost of Materials Consumed 17,985.25 17,859.65 14,726.69 16,619.16 Contract & Site Cost 15,724.73 13,390.86 1
Slide 15: Thank you
COMPANY CONTACT Rajeev Mishra (CFO) rajeev.mishra@hginfra.com III Floor, Sheel Mohar Plaza, A-1, Tilak Marg, C-Scheme, Jaipur - 302001 INVESTOR RELATION CONTACT / Go India Advisors Saloni Ajmera saloni@goindiaadvisors.com +91 9930577801 Selina Sheikh selina@goindiaadvisors.com +91 84338 18768 Thank
H.G. Infra Engineering — Q3 FY26 Earnings Presentation on 6ix