  1. Slide 1: Grand Canal Industrial Estates Inc. Berbice Deep Water Port

    Grand Canal Industrial Estates Inc. Berbice Deep Water Port August 2022

  2. Slide 2: Company Overview

    Company Overview CGX Energy Inc. (Ontario) 100% 100% 100% 62% CGX Energy CGX Resources GCIE Holdings ON Energy Inc Management Inc. (Bahamas) Ltd. (Barbados) (Guyana) Corp. (Delaware) 100% 100% CGX Resources Grand Canal Inc. (Guyana Industrial Estates Registered Inc. (Guyana) Branch) 32% 66.667% 100%

  3. Slide 3: Grand Canal Industrial Estates (GCIE) Company Details

    Grand Canal Industrial Estates (GCIE) Company Details Berbice Deep Water Port • Grand Canal Industrial Estates Inc. incorporated in Guyana June 30, 2010 • Office registered at 234 Lance Gibbs and Irving Streets, Georgetown • Principal objectives are to build and operate the Berbice Deep Water Port o

  4. Slide 4: GCIE Vision: Multi-Service Port

    GCIE Vision Berbice Deep Water Port Multi-Service Port Oil and Gas Exploration and Production Services Commodity Import/Export Regional Shipping Phase 1 Target: 2023 • 90m x 30m wharf platform build-out, channel access via a 49m long x 12m wide trestle • Access channel intended draft 7m and basin al

  5. Slide 5: Factors Motivating Berbice Deep Water Port in Guyana

    Berbice Deep Water Port in Guyana Factors Motivating • Two functional Commercial Oil and Gas Ports available in Guyana • Berbice Port located East of Georgetown Harbour • Strong desire for local ports in region • New port being built on Demerara River • Congested Georgetown Harbour has little room f

  6. Slide 6: GCIE Near Term – Phase 1 Objectives

    GCIE Near Term – Phase 1 Objectives 2023 Build and operate initial phase of the Berbice Deep Water Port to service the highly active offshore oil and gas exploration industry and agricultural sector in the Guyana-Suriname Area • 90x30 meter wharf platform and 49x12 meter approach trestle from shorel

  7. Slide 7: Berbice Deep Water Port Expansion 2024–2025

    Berbice Deep Water Port Expansion 2024 – 2025 Targeted Expansion Oil and Gas Exploration and Production Services Agricultural Export Commodity Import/Export Regional Shipping www.cgxenergy.com 7

  8. Slide 8: Grand Canal Industrial Estates (GCIE) Site Advantages

    Grand Canal Industrial Estates (GCIE) Site Advantages GCIE Selection Criteria for Site Location (Shore-base and Port Facility) • Berbice River is one of three major rivers in Guyana, spanning 600 km long, and 2.3 km wide at project location • Berbice River channel was dredged and maintained at a dep

  9. Slide 9: Grand Canal Industrial Estates (GCIE) Site Advantages

    Grand Canal Industrial Estates (GCIE) Site Advantages In 2010, Guyana Lands and Surveys Commission, in its land use planning map for Region 6, listed the area for development of a Deep-sea Port, New Airport Runway of 1.2km, and an Industrial Park • The GCIE location can service import/export of agri

  10. Slide 10: Project Status Update

    Berbice Deep Water Port Project STATUS UPDATE www.cgxenergy.com 10

  11. Slide 11: Access Bridge

    Access Bridge Contract Summary Component Name: Construction of Access Bridge Progress: 100% Completed Timeline: 6th April 2021 to 23rd December 2021 Contractor: Home Designs Engineering Associates (Berbice) Particulars: Connects Corentyne highway to access road Specifications - 40 tons per axle capa

  12. Slide 12: Quayside Laydown Yard

    Quayside Laydown Yard Contract Summary Specifications Component Name: Quayside Laydown Yard - 5 tons per sq meter (load capacity) Progress: 100% completed - 200 meters x 200 meters Timeline: 10th June 2021 to 15th July 2022 - 40,000 square meters Contractor: BK International Inc. www.cgxenergy.com 1

  13. Slide 13: Rip Rap Flood Protection

    Rip Rap Flood Protection Contract Summary Specifications Component Name: Rip Rap Flood Protection - 400m Rip Rap flood protection Progress: 100% completed - 56m Northern flood protection Timeline: 10th June 2021 to 5th August 2022 - 20m Southern flood protection Contractor: BK International Inc. www

  14. Slide 14: Water to Port

    Water to Port Contract Summary Specifications Component Name: Water to Port - 2.7km of 150mm Pipeline Progress: 100% completed - Installed to GWI specifications Timeline: 4 October 2021 to 15th November 2021 th - Verified and approved by GWI Contractor: Mohamed Ahmad Construction Works (Berbice) www

  15. Slide 15: Power to Port

    Power to Port Contract Summary Component Name: Power to Port Progress: 100% completed Timeline: 16 October 2020 to 15th December 2021 th Contractor: Guyana Power and Light Inc. Specifications - 70 KVA transformer - Installed by GPL - 3-phase capacity with stepdown to 110/220 2-phase www.cgxenergy.co

  16. Slide 16: Access Road to Port Site

    Access Road to Port Site Contract Summary Component Name: Seawell Road Rehabilitation Progress: 100% completed Timeline: 5 November 2020 to 2nd February 2022 th Contractor: KP Jagdeo General Contractors (Berbice) Specifications - ASHTO Standards - 2.6 km from access bridge to port site - 5 m wide wi

  17. Slide 17: Concrete Drain and Residents' Concrete Bridges

    Concrete Drain and Residents’ Concrete Bridges The First 200 meters of the access road, adjacent to the Seawell village residents, was fully paved with the construction of a concrete drain and concrete bridges for each resident. The contract for Access Road was amended to include this component. Spe

  18. Slide 18: Bramfield Logistics Yard

    Bramfield Logistics Yard The CGX Laydown Yard has been fully operational since 2010 with zero safety incidents. Furthermore, in July 2005, August 2005, and June 2005 CGX staged three onshore wells, and in January 2012, one offshore well from this Laydown Yard, with zero incidents. Located along the

  19. Slide 19: Bramfield Logistics Yard to Port

    Bramfield Logistics Yard to Port Specifications Completed road connecting the GCIE’s Berbice Deep Water Port site to the Bramfield Logistics Yard 3.2km away www.cgxenergy.com 19