Environmental Clean Technologies Limited · ASX:ECT
Environmental Clean Technologies — Shareholder Meeting (November 2013)
17 slides from Environmental Clean Technologies's shareholder meeting presentation, Nov 29, 2013
Slide 1: Annual General Meeting Shareholder Update
Annual General Meeting Shareholder Update 29 November 2013
Slide 2: Overview
Overview § The year just passed § Our Strategy § The year ahead
Slide 3: 2013 – Great Progress, Great Frustration
2013 – Great Progress, Great Frustra7on § Key Markets for our technologies § Coldry acEvity & update § Matmor acEvity & update
Slide 4: Key Markets – Thermal Coal
2013: Key Markets – Thermal Coal
Slide 5: Key Markets - Iron & Steel
2013: Key Markets -‐ Iron & Steel § Industry over-‐capacity conEnues to be a structural problem § Project Coking coal supply shorJall has received some respite with decreased growth in China § CompeEEon basis is driven by cost – Cost advantage is King – Coking coal & Iron ore pricing is largely
Slide 6: Coldry
2013: Coldry § ProspecEve targets & applicaEons § Design for Commercial DemonstraEon § ALDP § India strategy
Slide 7: Coldry – Targets & Applications
2013: Coldry – Targets & Applica7ons § ApplicaEons: § Targets – Thermal / Power generaEon – Thermal • Blend • Aus DomesEc • Solo • Aus Export – Conversion – “Gateway” • O/S DomesEc • Pyrolysis – Conversion • GasificaEon – Metallurgical – Matmor • Matmor • ECT § LV CDP § India CDP
Slide 8: Design Works
2013: Design Works § Work concluded in August 2013 -‐ CDP – Ready to proceed with the right constructor here in Aus – Same engineering will be used as the basis for other installaEons, with engineering customisaEon as needed for specific requirements • e.g. India different coal & climate
Slide 9: Design works – Other outcomes
2013: Design works – Other outcomes § SubstanEally improved Materials & Energy balance modeling capability – Simulate other coals, climates & waste heat integraEon opEons § “Full scale” Packed Bed Dryer tesEng unit – Capacity to validate modeling – Expanded product tesEng capability
Slide 10: ALDP
2013: ALDP § Advanced Lignite DemonstraEon Program § The Company submiaed our applicaEons as required under the process, and provided all required responses § The program is behind schedule § There is no further update available from either the Federal or State Governments
Slide 11: Matmor – Current Activity
2013: Matmor – Current Ac7vity § Necessarily needs to follow Coldry commercialisaEon so it can draw upon suitable feedstock § AcEvity in 2013 has focused upon beaer understanding the applicable footprint of Matmor technology
Slide 12: Strategy: Coldry
Strategy: Coldry § Deploy CDP to demonstrate and act as ‘the best collateral possible’ § De-‐risk adopEon through cost reducEon – India Manufacturing plans § Expand adopEon prospects – Geographically – more Lignite fields – ApplicaEon – integraEon within other processes as a Gateway • e.g. front
Slide 13: Strategy: Coldry – India
Strategy: Coldry – India § ECT’s India strategy is to: – Develop prospecEve Coldry projects in India – Develop an equipment supplier base to provide lowest possible cost suitable equipment to Coldry projects globally to enhance project economics § Prospects: – Three major Lignite fields; Tamil Nadu
Slide 14: Strategy: Matmor
Strategy: Matmor § Secure Financial & Technical partner to support Pilot Plant development – Market to companies who will be able to benefit the most, e.g. • Coking coal cost / supply risk • Waste stream avoidance • “Ferro+” applicaEons § Select engineering provider, & develop Pilot Plant engineeri
Slide 15: The year ahead – Coldry
The year ahead § Coldry – A change in emphasis – Detailed design now complete – Emphasis shiis to more ‘MarkeEng’ • The best element of markeEng for FOAK is a demonstraEon plant • Hence, focus is on CDP (two key targets) and the project development work to support, e.g. India Manufacturing strategy
Slide 16: The year ahead – Matmor
The year ahead § Matmor – Increase in development works – Structured plan to move to Pilot Plant • Financial & Technical partner search conEnues – Several prospects in play • Engineering partner search to commence – High temperature PyroMet engineering is best offshore • Test Plant work plans to sup
Slide 17: Thank you.
Thank you. § Ashley Moore Managing Director § info@ectltd.com.au § +613 9909 6784 § www.ectltd.com.au