  1. Slide 1: CCC Presentation Hera-Federation Complex Project Update

    Slide 1: CCC Presentation Hera-Federation Complex Project Update

    CCC Presentation Hera-Federation Complex Project Update 12 December 2023 ASX Code: AMI

  2. Slide 2: Acknowledgement of Country

    Slide 2: Acknowledgement of Country

    Acknowledgement of Country • Aurelia Metals Ltd respectfully acknowledges the Ngiyampaa Nation as the Traditional Custodians of this land – both past and present. • We know this land has history, custodians and stories, spanning tens of thousands of years, that endure to this day. • We pay our respe

  3. Slide 3: Federation Hera Complex Progress

    Slide 3: Federation Hera Complex Progress

    3 Federation Hera Complex Progress Tracking Key Dates of Interest (as of 13 June 2023): • Redpath Mining Contractors remobilisation recommence Mid- July 2023 Restart decline early - August 2023 • Hera to Peak and Burthong Road Upgrades late August 2023 Starting - September 2023. Works under way with

  4. Slide 4: Federation Mine Development

    Slide 4: Federation Mine Development

    4 Federation Mine Development FIRST 3 MONTHS OF WORK PROGRAM: • Decline, sumps and stockpile development • Single heading development, ventilated and power down decline from surface Federation development @ end Oct 2023 Note: Assumes 1 Aug 2023 Decline resumption

  5. Slide 5: Federation Mine Development

    Slide 5: Federation Mine Development

    5 Federation Mine Development Mine development November 2023 mining achieved 217.7m advance Federation development 30 November 2023 Note: Assumes 1 Aug 2023 Decline resumption

  6. Slide 6: Federation Hera Complex Overview

    Slide 6: Federation Hera Complex Overview

    6 Federation Hera Complex Overview Road Upgrade Works Drainage works, gravel re-sheeting and lime stabilisation works are underway with works still forecast to be completed end of February

  7. Slide 7: Environment and Community

    Slide 7: Environment and Community

    Environment and Community 12 December 2023 ASX Code: AMI

  8. Slide 8: Environment and Community: Priorities and improvement initiatives

    Slide 8: Environment and Community: Priorities and improvement initiatives

    8 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Priorities and improvement initiatives • Continue to provide input to the drafting of new Federation management plans. Air Quality and Green House Gas, Blasting, Waste Rock and the Environmental Management S

  9. Slide 9: Environment and Community: Complaints (continued)

    Slide 9: Environment and Community: Complaints (continued)

    9 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Complaints (continued) 6 December 2023 – Complaint trucks being parked on roads to the north of the village. Complainant has been responded to: • I have inspected the area and it is operated by Nicholsons of

  10. Slide 10: Nymagee Map

    Slide 10: Nymagee Map

    10 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Nymagee Map

  11. Slide 11: Complaints (continued): Burthong Road Drainage

    Slide 11: Complaints (continued): Burthong Road Drainage

    11 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Complaints (continued) Burthong Road Drainage – there has been ongoing discussions with owners of Four Corners Farm Stay and Four Corners Homestead in response to concerns that water would not be able to cr

  12. Slide 12: Four Corners entrance

    Slide 12: Four Corners entrance

    12 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Four Corners entrance

  13. Slide 13: Exploration

    Slide 13: Exploration

    Exploration 12 December 2023 ASX Code: AMI

  14. Slide 14: Exploration: Nymagee copper mine

    Slide 14: Exploration: Nymagee copper mine

    14 Exploration Nymagee copper mine Works are ongoing and planning to finish up by the end of the year with results due in the 1st quarter of 2024.