Suntech Infra Solutions Limited · NSE:SUNTECH

Suntech Infra Solutions — H1 FY27 Earnings Presentation

38 slides from Suntech Infra Solutions's earnings presentation, Nov 23, 2026

  1. Slide 1: Cover letter to National Stock Exchange of India

    Slide 1: Cover letter to National Stock Exchange of India

    Date: 23.11.2026 To Listing Compliance Department National Stock Exchange of India Ltd, Exchange Plaza, C-1, Block G, Bandra Kurla Complex, Bandra (E), Mumbai – 400 051 NSE Symbol: SUNTECH ISIN: INE0SGZ01016 Subject: Investor Presentation Dear Sir / Madam, Pursuant to Regulation 30 read with Schedul

  2. Slide 2: H1 FY27 Investor Presentation

    Slide 2: H1 FY27 Investor Presentation

    SUN TECH SUNTECH INFRA SOLUTIONS LIMITED H1 FY27 INVESTOR PRESENTATION INVESTOR PRESENTATION 1

  3. Slide 3: Disclaimer

    Slide 3: Disclaimer

    Disclaimer This presentation and the accompanying slides (the “Presentation”), which have been prepared by Suntech Infra Solutions Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for an

  4. Slide 4: H1 FY27 Highlights

    Slide 4: H1 FY27 Highlights

    H1 FY27 Highlights INVESTOR PRESENTATION 3

  5. Slide 5: Financial performance: H1 FY27 vs H1 FY26

    Slide 5: Financial performance: H1 FY27 vs H1 FY26

    Financial performance: H1 FY27 vs H1 FY26 Total income (₹ Cr) EBITDA (₹ Cr) Profit after tax (₹ Cr) 18.78 100.53 6.02 13.66 68.96 3.02 H1 FY26 H1 FY27 H1 FY26 H1 FY27 H1 FY26 H1 FY27 +45.8% YoY +37.5% YoY +98.9% YoY H1 includes about three months of monsoon; the business is seasonal. Please see the

  6. Slide 6: Statement of profit and loss

    Slide 6: Statement of profit and loss

    Statement of profit and loss ₹ lakhs Particulars H1 FY27 H1 FY26 YoY growth Net sales 9,984.45 6,763.74 +47.62% Other income 68.51 132.21 – Total income 10,052.97 6,895.95 +45.78% Raw material expenses 3,030.10 2,931.00 Employee benefit expenses 1,685.07 1,086.12 Other expenses 3,459.73 1,512.81 Tot

  7. Slide 7: Seasonality: reading the H1 results in context

    Slide 7: Seasonality: reading the H1 results in context

    Seasonality: reading the H1 results in context H1 includes the monsoon 1 The first half of the financial year (April to September) includes about three months of monsoon, which affects the pace of site work in foundation, piling and civil construction. H1 and H2 are not directly comparable 2 Our bus

  8. Slide 8: Key Business Performance – H1 FY27

    Slide 8: Key Business Performance – H1 FY27

    Key Business Performance – H1 FY27 STRONG ORDER BOOK PROVIDING FY27 REVENUE VISIBILITY Expected Execution in H2 Segment Order Book (₹ Cr) FY27 (₹Cr) Construction and Piling Foundation 194.70 135.00 Construction Equipment Rental 9.50 9.50 Total 204.20 144.50 Healthy Order Book Ensuring Strong FY27 Ex

  9. Slide 9: Company Overview

    Slide 9: Company Overview

    ‘“OMPANY OVERVIEW

  10. Slide 10: Who we are

    Slide 10: Who we are

    Who we are Founded in 2009 Pan India Infrastructure Listed in National Stock Execution Company Exchange (NSE) Core Business Verticals Our Strength Bored cast-in-situ Ground Improvement - D-Walls, Piles, CFA Piles, Sheet Stone Columns Anchoring Piles 130+ 650+ Strong Execution & Owned Machines & Team

  11. Slide 11: Our Services

    Slide 11: Our Services

    Our Services Ground Bored Piles Civil Works Retention System Testing Works Equipment Rental Improvement Services • Bored Cast-in situ Piles • Stone Columns – Top/ • Pile Caps • Diaphragm Wall • Plate Load Test • Piling Rigs • Driven Cast-in-situ Piles Bottom Feed • Infrastructure Projects • Ground A

  12. Slide 12: Capital expenditure and fleet size

    Slide 12: Capital expenditure and fleet size

    Capital expenditure and fleet size Capex (₹ Cr) Total fleet size (no.) 27.60 103 100 90 18.75 8.05 FY25 FY26 H1 FY27 FY25 FY26 H1 FY27 Fleet size increased from 90 in FY25 to 103 in H1 FY27. H1 FY27 capex covers six months and should be read accordingly. INVESTOR PRESENTATION 11

  13. Slide 13: Business priorities

    Slide 13: Business priorities

    Business priorities 1 2 3 4 5 Order book Client engagement Capital efficiency Operational Sector execution control diversification Execute the ₹204.20 Deepen engagement Prioritise equipment Strengthen project Serve infrastructure, Cr order book with with project owners additions based on monitoring

  14. Slide 14: Growth Strategy

    Slide 14: Growth Strategy

    Growth Strategy ROBUST ORDER BOOK POSITION ➢ Strong order book of ₹204.20 Cr along with an order pipeline of over ₹800 Cr, ensuring healthy revenue visibility. Sustainable Business EXPANDING MARKET PENETRATION Growth ➢ Direct engagement with reputed owners and PMC consultants enhancing market credib

  15. Slide 15: Our Head Office Team

    Slide 15: Our Head Office Team

    Our Head Office Team 3 INVESTOR PRESENTATION 14

  16. Slide 16: HSE Standards and recognition

    Slide 16: HSE Standards and recognition

    HSE Standards and recognition @Safe environment www.suntechinfra.com INVESTOR PRESENTATION 15

  17. Slide 17: HSE Standards: Inspections

    Slide 17: HSE Standards: Inspections

    HSE Standards @Inspections www.suntechinfra.com INVESTOR PRESENTATION 16

  18. Slide 18: HSE Standards: Environment and awareness

    Slide 18: HSE Standards: Environment and awareness

    HSE Standards @Environment and awareness www.suntechinfra.com INVESTOR PRESENTATION 17

  19. Slide 19: Suntech Infra Owned Equipment's

    Slide 19: Suntech Infra Owned Equipment's

    Suntech Infra Owned Equipment’s Supporting Machines JCB TM’s Batching Plant Boom Placers Dumpers Excavators www.suntechinfra.com Miling Machine Vibro rollers Vibro Hammer INVESTOR PRESENTATION 18

  20. Slide 20: Suntech Infra Owned Equipment's

    Slide 20: Suntech Infra Owned Equipment's

    Suntech Infra Owned Equipment’s Piling Rigs Stone Column Rigs Service Cranes D-Wall Rigs www.suntechinfra.com INVESTOR PRESENTATION 19

  21. Slide 21: Key Projects at Suntech Infra Solutions – Ongoing

    Slide 21: Key Projects at Suntech Infra Solutions – Ongoing

    KEY PROJECTS AT SUNTECH INFRA SOLUTIONS – ON GOING

  22. Slide 22: L&T Constructions – NTPC Gadarwara

    Slide 22: L&T Constructions – NTPC Gadarwara

    L&T Constructions NTPC Gadarwara Super Thermal Power Project in Madhya Pradesh is an operational 1600 MW coal-based power plant comprising two units of 800 MW each. NTPC is planning a Stage- II expansion with an additional 2 × 800 MW ultra-supercritical units, for which Larsen & Toubro (L&T) has bee

  23. Slide 23: NTPC Gadarwara Super Thermal Power – L&T Constructions

    Slide 23: NTPC Gadarwara Super Thermal Power – L&T Constructions

    NTPC Gadarwara Super Thermal Power • L&T Constructions Parameter Details Owner / client NTPC Contractor L&T Constructions Project type BCIS piles Number of piles 3,285 nos. Depth of piles Approx. 28 m Reinforcement 4,435 MT Initial and routine (vertical, lateral, pull- Load testing out) Pile integri

  24. Slide 24: Virat Ramayan Mandir

    Slide 24: Virat Ramayan Mandir

    Virat Ramayan Mandir Viraat Ramayan Mandir Project, located in East Champaran, Bihar, is a large-scale temple development by the Mahavir Mandir Trust aimed to become the world’s largest Hindu temple upon completion. Inspired by Angkor Wat and major South Indian temple architecture, the ₹500 crore, t

  25. Slide 25: Virat Ramayan Mandir, Bihar

    Slide 25: Virat Ramayan Mandir, Bihar

    Virat Ramayan Mandir, Bihar • Asia’s Tallest Shivling - 33 Feet Parameter Details BCIS piles (₹17 Cr) and civil works (₹44 Project type Cr) Scope of works Bored piles Number of piles 3,310 nos. Depth of piles 23 m Reinforcement 1,061 MT Initial and routine (vertical, lateral, pull- Load testing out)

  26. Slide 26: NTPC, Thermal Power Plant

    Slide 26: NTPC, Thermal Power Plant

    NTPC, Thermal Power Plant The Nabinagar Super Thermal Power Project in Aurangabad district, Bihar, is being developed by Nabinagar Power Generating Company (NPGC), a joint venture of NTPC and Bihar State Electricity Board. Phase I comprises 3 × 660 MW units (1,980 MW), using coal from the North Kara

  27. Slide 27: Tata Projects, Nabi Nagar

    Slide 27: Tata Projects, Nabi Nagar

    Tata Projects, Nabi Nagar • Bored Piling Works at Thermal Power Plant Parameter Details Project value ₹17.94 Cr Project type BCIS piles Number of piles 1,200 nos. Depth of piles 22 m Reinforcement 794 MT Initial and routine (vertical, lateral, pull- Load testing out) Grade of concrete M25 Plant and

  28. Slide 28: Pile Foundations By Suntech

    Slide 28: Pile Foundations By Suntech

    Pile Foundations By Suntech DLF CREST – GURGAON IOCL REFINERIES – BIHAR & RAJASTHAN PREMIUM LUXURY RESIDENTIAL HIGH-RISE COMPLEX CIVIL FOUNDATION WORKS DELIVERED WITH PRECISION YAMUNA EXPRESSWAY POLICE BHAWAN – LUCKNOW ICONIC LUXURY HIGH-RISE DEVELOPMENT INVESTOR PRESENTATION 27

  29. Slide 29: Execution platform and systems

    Slide 29: Execution platform and systems

    Execution platform and systems Equipment base Engineering 130+ company-owned machines and setups, with a In-house design desk for design optimisation and value dedicated yard and mechanical support. engineering. Operational reach Safety and quality Nationwide presence and mobilisation capability. Le

  30. Slide 30: Pile Foundations By Suntech

    Slide 30: Pile Foundations By Suntech

    Pile Foundations By Suntech ATC TOWER, IGI AIRPORT – DELHI VERSACE TOWER – DELHI TALLEST AIR TRAFFIC CONTROL TOWER IN INDIA ICONIC LUXURY HIGH-RISE DEVELOPMENT INVESTOR PRESENTATION 29

  31. Slide 31: Why Suntech

    Slide 31: Why Suntech

    Why Suntech Suntech Infra Solutions stands as one of India’s most trusted partners for foundation and ground engineering works, equipped with 130+ machines, a highly skilled workforce, engineering-driven solutions, and a culture of safety and excellence. With a nationwide footprint, strong client tr

  32. Slide 32: Annual Financials

    Slide 32: Annual Financials

    Annual Financials INVESTOR PRESENTATION 31

  33. Slide 33: Key Financial Highlights

    Slide 33: Key Financial Highlights

    Key Financial Highlights Revenue EBITDA PAT EBITDA Margin PAT Margin 17,627.37 3,821.50 3,822.09 15,265.10 28.65 24.75 2,738.40 21.33 9,559.45 1,375.25 1,202.08 1211.36 12.57 7.94 7.68 FY24 FY25 FY26 FY24 FY25 FY26 FY24 FY25 FY26 All Amount In ₹ Lakhs & Margins in % INVESTOR PRESENTATION 32

  34. Slide 34: Profit & Loss Statement

    Slide 34: Profit & Loss Statement

    Profit & Loss Statement In ₹ Lakhs Particulars FY26 FY25 FY24 Revenues 17,627.37 15,265.10 9,559.45 Other Income 288.79 177.48 66.02 Total Income 17,916.16 15,442.58 9,625.48 Expenditure Raw Materials 6,992.79 4,016.27 2,077.50 Employee costs 2,614.52 2,510.32 1,843.78 Other expenses 4,486.76 5,094.

  35. Slide 35: Balance Sheet

    Slide 35: Balance Sheet

    BALANCE SHEET In ₹ Lakhs Equities & Liabilities FY26 FY25 FY24 Assets FY26 FY25 FY24 Equity 1,936.26 1,538.82 256.47 Non-Current Assets Reserves 7,562.66 3,496.82 3,567.81 Fixed Assets 7,853.76 6,607.62 6,230.39 Net Worth 9,498.92 5,035.64 3,824.28 Deferred Tax Assets 152.94 151.31 179.44 Non-Curren

  36. Slide 36: Key Ratios

    Slide 36: Key Ratios

    KEY RATIOS ROE In % ROCE In % Debt to Equity In Times 31.43 1.47 1.43 20.18 24.06 17.50 13.95 0.82 14.48 FY24 FY25 FY26 FY24 FY25 FY26 FY24 FY25 FY26 Current Ratio In Times Earnings Per Share In ₹ 1.65 11.05 1.43 1.10 7.48 6.21 FY24 FY25 FY26 FY24 FY25 FY26 INVESTOR PRESENTATION 35

  37. Slide 37: Stock Data

    Slide 37: Stock Data

    STOCK DATA As on 20/11/2026 As on 30/09/2026 SHAREHOLDING PATTERN NSE CODE: SUNTECH | INE0SGZ01016 Share Price (₹) 37.90 29.92% Market Capitalization (₹ Cr) 73.38 No. of Shares 1,93,62,600 Face Value (₹) 10.00 70.08% 52 week High-Low (₹) 53.95 – 28.70 Promoter & Promoter Group Public INVESTOR PRESEN

  38. Slide 38: Thank You!

    Slide 38: Thank You!

    THANK YOU! Execution Builds Trust. Trust Builds Growth Suntech Infra Solutions Limited 604/05/06, NDM 2 Building, Netaji Subhash Place, Pitampura, New Delhi, Delhi, 110034 Phone: +91 9818265777 Email: info@suntechinfra.com Website: www.suntechinfra.com Investor Relations Advisor EquibridgeX Advisors

Source: company website