Aurelia Metals Limited · ASX:AMI

Aurelia Metals — Q4 2025 Earnings Presentation

13 slides from Aurelia Metals's earnings presentation, Jul 21, 2025

  1. Slide 1: June 2025 Quarterly Update

    JUNE 2025 QUARTERLY UPDATE rsonal use only 21 July 2025 ASX Code: AMI

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS This presentation has been prepared by Aurelia Metals Limited (‘AMI’ or the ‘Company’). It should By its very nature, production and exploration for gold and base metals is a high risk business and is not rsonal use only not be considered as an offer or invitation to subsc

  3. Slide 3: June 2025 Quarter Highlights

    JUNE 2025 QUARTER HIGHLIGHTS rsonal use only FY25 production and cost Federation mining ramping guidance achieved up in line with plan Peak mine development Cash balance remains exceeded 1,000m/qtr target strong at $110M JUNE 2025 QUARTERLY | 21 JULY 2025 | PAGE 3

  4. Slide 4: Group Production and Costs

    GROUP PRODUCTION AND COSTS Production and cost guidance achieved for all metrics rsonal use only Unit Sep 24 Dec 24 Mar 25 Jun 25 FY25 Measure FY25 Guidance Qtr Qtr Qtr Qtr Gold produced koz 10.5 11.0 16.6 7.3 45.4 ✓ 40 – 50 Copper produced kt 1.2 0.7 0.5 0.3 2.7 ✓ 2.5 – 3.5 Zinc produced kt 2.3 3.8

  5. Slide 5: Sustainability

    SUSTAINABILITY Safeguarding our social licence to operate rsonal use only Group Total Recordable Injury Frequency Group Recordable Environmental Rate (TRIFR) - 12 month moving average Incident Frequency Rate (REIFR) - 12 month moving average 15 2.0 1.5 10 1.0 5 0.5 0 0.0 Jul-24 Nov-24 Dec-24 Jan-25

  6. Slide 6: Peak

    PEAK Productivity improvements remain a key focus Development metres rsonal use only 915 888 1,041 730 724 • Ore mining sequence in line with FY25 guidance Jun 24 Qtr Sep 24 Qtr Dec 24 Qtr Mar 25 Qtr Jun 25 Qtr • Development of 1,041m was above 1,000m/qtr target Mining unit cost / tonne 140 • Work i

  7. Slide 7: Federation

    FEDERATION Development and mining activity ramping up in line with plan rsonal use only • Mine development increased to 1,134m in the quarter • Decline development prioritised to provide infill drilling platforms • Ore mined increased to 53kt for the quarter. Total of 106kt for FY25 • Processed 55kt

  8. Slide 8: Great Cobar Project Underway

    GREAT COBAR PROJECT UNDERWAY Development commenced in July 2025 rsonal use only • Jumbo, loader and truck delivered to site • Services established to decline face • Recruitment of key roles completed • Decline development of 2.1km planned for FY26 • Capital guidance of $20-25M for FY26 JUNE 2025 QUA

  9. Slide 9: Peak Plant Projects

    PEAK PLANT PROJECTS Advancing as planned rsonal use only (1) Tailings and Process Water Management Project • Construction of the thickener advancing on schedule (2) Tertiary Ball Mill and (3) Materials Handling Projects • Feasibility Studies being finalised for approval • Capital estimate below Scop

  10. Slide 10: Exploration

    EXPLORATION Regional programs continue to support organic growth rsonal use only Nymagee • Intersected high-grade Cu and Zn-Pb mineralisation1 – 5.2m (3.8m ETW) @ 3.0% Cu, 5g/t Ag in NMD106 from 132.0m – 4.1m (3.2m ETW) @ 9.9% Zn, 5.7% Pb, 0.3% Cu, 78g/t Ag in NMD106 from 292.4m • Downhole Electroma

  11. Slide 11: Balance Sheet

    BALANCE SHEET Total liquidity of over $145M available to fund growth rsonal use only Group cash A$M1 ~36 ~146 14.0 12.8 110.1 106.7 (1.9) (2.4) (15.2) (3.8) Mar-25 Peak Growth Exploration Corp, Tax, Care & Financing Jun-25 Loan Total cash bal. ops capital Interest Maint cash cash bal. note liquidity

  12. Slide 12: Key Focus Areas

    KEY FOCUS AREAS Expanding margin, cash flow and developing copper growth options rsonal use only Disciplined capital allocation to retain strong cash balance quarter on quarter Safely deliver improved productivity from our operations to maximise cash from assets Safely ramping up Federation producti

  13. Slide 13: Contact

    CONTACT T: +61 7 3180 5000 E: office@aureliametals.com.au Level 10, 10 Felix Street rsonal use only BRISBANE QLD 4000 GPO Box 7 BRISBANE QLD 4001 aureliametals.com