Tharisa Plc · JSE:THA

Tharisa — Investor Presentation (June 2024)

40 slides from Tharisa's investor presentation, Jun 10, 2024

  1. Slide 1: This is Tharisa

    THIS IS THARISA JUNE 2024 tharisa® @.

  2. Slide 2: Why Mining, Why Now, Why Tharisa

    WHY MINING • WHY NOW • WHY THARISA NOW THARISA MINING  OECD forecasts that global materials  Mine builders and operators  “If it is not grown it is mined” demand will more than double in 2060  Multi-generational assets of strategic  Critical to supply into the clean energy  Significant global

  3. Slide 3: Continued Macro Adversity

    CONTINUED MACRO ADVERSITY HEADWINDS TAILWINDS COMMODITIES MACRO  Co-product business model  Electricity constraints in South Africa  Buoyant chrome commodity market  Transport infrastructure challenges  Counter cyclical commodities in basket  Geopolitical complexities  Fundamentals for both c

  4. Slide 4: 10 Years Listed on the JSE

    10 YEARS LISTED ON THE JSE 4 enriching lives through innovating the resources company of the future

  5. Slide 5: The Vital Numbers

    US$1 344/oz US$288/t THE VITAL NUMBERS down 39.3% PGM BASKET PRICE up 16.9% MET GRADE PRICE REVENUE EBITDA NET PROFIT AFTER TAX US$369.1 m US$79.6 m US$38.8 m up 10.1% down 2.0% down 29.1% (HY2023: US$335.3 m) (HY2023: US$81.2 m) (HY2023: US$54.7 m) NET CASH FROM OPERATING ACTIVITIES CAPITAL EXPENDI

  6. Slide 6: Commodities: PGMs

    US$1 460/oz COMMODITIES SPOT PGM BASKET PRICE Ru Ir Ru 14,4% 1,9% 4,2% Au PGMS Ir 4,4% 8,0%  Primary supply reduction should be main catalyst for PGM price Au Rh 4,3% increases 0,2% THARISA KARO Pt  Recycling less of a supply contributor as vehicle ownership periods Rh MINERALS PLATINUM 42,0% PRIL

  7. Slide 7: Commodities: Chrome

    US$310/t COMMODITIES SPOT MET GRADE PRICE CHROME  No substitution for chrome in stainless steel production METALLURGICAL GRADE PRICE AND PORT STOCKS (US$/t) and (Mt)  Stainless steel demand growth for 2023 of ~5%, Chinese production increased 12.6% for 2023 310 3,5  Chrome prices remain robust on

  8. Slide 8: Some Detail on Chrome

    SOME DETAIL ON CHROME CHROME  Chromium is the 14th most abundant metal in the lithosphere Other  Chromite or chrome ore is the commercial name of iron chromium Finland 9% oxide 2%  Global chromite resources are estimated at over 12 billion tonnes Kazakhstan 5% with reserves estimated at 470 milli

  9. Slide 9: Supply

    SUPPLY Finland Other Zimbabwe 2% 8%  Global chrome production in 2022 was 39.7 Mt 3%  Over the last 15 years, on average South Africa has accounted for more Turkey than 55% of global production 4%  South Africa is the largest producer reporting 25.8 Mt in 2023 India 8%  South Africa exported ove

  10. Slide 10: Chrome Concentrate Products

    CHROME CONCENTRATE PRODUCTS 94.7%  Metallurgical grade: characterised by a Cr2O3 content of 42% to 46%, this type of chrome ore is METALLURGICAL GRADE used primarily in metallurgical applications and more specifically to create ferrochrome, which is in turn is used to produce stainless steel and ot

  11. Slide 11: Demand

    DEMAND  Demand for chrome concentrates is dominated by its in metallurgical applications being ~95% 0.6 t > 0.25 t > 1t  Stainless steel is the largest demand from metallurgical applications, and as such the dynamics of the stainless steel industry heavily impact the chrome market CHROME ORE FERRO

  12. Slide 12: Ferrochrome Production

    FERROCHROME PRODUCTION 9 Millions  China is the largest global ferrochrome producer, having taken over from 8 South African in 2012 and since then China has doubled its ferrochrome output capacity 7 6  Ferrochrome production is centred from Asia other regions include India and Indonesia 5 4  In 2

  13. Slide 13: Stainless Steel

    STAINLESS STEEL Applicances & electronics  Stainless steel demand has been driven by China, accounting for more 9% than 60% of global production, with global production being reported at Metal goods 58.5 Mt for 2023 37%  Stainless steel is produced from processing ferrochrome and nickel Industrial

  14. Slide 14: Stainless Steel Growth Projection

    STAINLESS STEEL GROWTH PROJECTION Source SMR enriching lives through innovating the resources company of the future 14

  15. Slide 15: Stainless Steel Growth Projection

    STAINLESS STEEL GROWTH PROJECTION Source SMR enriching lives through innovating the resources company of the future 15

  16. Slide 16: Stainless Steel Growth Projection

    STAINLESS STEEL GROWTH PROJECTION Source SMR enriching lives through innovating the resources company of the future 16

  17. Slide 17: Pricing and Port Stocks

      enriching lives through innovating the resources company of the future at at 2.6 Mt of chrome concentrates PRICING AND PORT STOCKS Spot pricing at US$310/t – US$315/t CIF China Port stocks remain at lower levels compared to previous years 0 50 100 150 200 250 300 350 2 Jan 2020 18 Feb 2020 23 Ma

  18. Slide 18: Tharisa in Context

    THARISA IN CONTEXT  Total resource of 844.8 Mt containing 166.2 Mt of Cr2O3  Total reserve of 85.1 Mt containing 15.1 Mt of Cr2O3  Fourth largest chrome producer in South Africa  1.5 Mtpa of chrome products  Provides China and Indonesia with ~10% of its chrome requirements  One quarter of spec

  19. Slide 19: Strategy

    STRATEGY x on, 3 - See e ete

  20. Slide 20: Vision 2025

    VISION 2025 EXPANSION expand and roll out the business sustainably OPTIMISATION optimise existing operations INNOVATION continue to invest in innovative thinking DIVERSIFICATION become a globally diversified business INVESTMENT be the investment of choice in our chosen sector ENRICHMENT responsibly

  21. Slide 21: Security of Raw Material Supply Through Shallow Multigenerational Assets

    39.4 Moz & 11.3 Moz 166.2 Mt IN CONTAINED PGMS (6E) IN CONTAINED CHROME Karo Platinum SECURITY OF RAW MATERIAL SUPPLY Redox One Tharisa Mine Arxo Metals Renewable Energy Centre THROUGH SHALLOW MULTIGENERATIONAL MINERAL ASSETS, ENABLED BY TECHNOLOGY AND Dortmund Victoria Falls Harare INNOVATION Arxo

  22. Slide 22: Tharisa Minerals

    THARISA MINERALS UNLOCKING STRATEGIC VALUE AND FLEXIBILITY  LTIFR 0.05 per 200 000 man hours worked  Reef tonnes mined 2.1 Mt, down 0.8%  Reef milled 2.8 Mt, up 0.2%  PGM production 71.1 koz, down 7.7%  Chrome production 865.6 kt, up 9.9%  Accelerating underground studies, ensuring sustainable

  23. Slide 23: Karo Project

    KARO PROJECT MULTIGENERATIONAL PGM DEVELOPMENT ASSET – LONG TERM STRATEGIC VIEW THROUGH THE CYCLE  LTIFR 0.11 per 200 000 man hours worked  Construction continues steadily with value engineering running in parallel  Finalising fiscal regime necessary for a tier one project  Current market condit

  24. Slide 24: An Ethos of Innovation

    AN ETHOS OF INNOVATION ARXO METALS BENEFICIATION SITE  Commercial pyrometallurgical site – producing novel alloys  Unique PGM refining process proven ARXO METALS TECHNOLOGY DEVELOPMENT CENTRE  Facility to run laboratory and pilot scale test work – downstream focus ARXO METALS RENEWABLE ENERGY CEN

  25. Slide 25: Mine to Megawatt

    MINE TO MEGAWATT DECARBONISATION CIRCULAR ECONOMY PGMS CHROME PATHWAYS  Producing lower carbon  Catalytic properties  Stainless steel requirement in  Electrification (solar project) renewable energy generation minerals  Slower BEV uptake, hybrid  Circularity (use of our (solar, wind, nuclear,

  26. Slide 26: Financial Highlights

    FINANCIAL HIGHLIGHTS

  27. Slide 27: Financial Resilience Through Our Co-Production Model

    FINANCIAL RESILIENCE THROUGH OUR CO-PRODUCTION MODEL MULTI COMMODITIES CASH FLOW GENERATIVE CAPITAL DISCIPLINE CONTINUED INVESTMENT  Share repurchase programme Technology and downstream  Co-production model  Net cash flows from operations of US$5 m beneficiation investment  Polymetallic basket

  28. Slide 28: Multi Commodity Revenue Stream

    MULTI COMMODITY REVENUE STREAM Agency and Manufacturing and trading consulting… 9,8% FCA REVENUE* PGM Chrome 26,0% 63,2% US$369.1 m Revenue increase of 10.1% Benefits of co-production model PGM sales of 70.6 koz Average PGM basket price of US$1 344/oz Au Ni Cu Ru Specialty 1,5% 3,2% grade Metallurgi

  29. Slide 29: EBITDA Waterfall

    EBITDA WATERFALL 29 enriching lives through innovating the resources company of the future

  30. Slide 30: Unit Costs

    UNIT COSTS % Units HY2024 HY2023 change Overheads 10,4% Labour Cubes mined Mm3 8.7 7.3 19.2 13,6% Cost per cube mined* US$/m3 10.6 10.9 (2.8) Reef tonnes mined Mt 2.1 2.1 Consumables Mining Cost per reef tonne mined* US$/t 44.1 37.7 17.0 3,6% ON MINE CASH 24,8% COSTS Tonnes milled Mt 2.8 2.8 Electri

  31. Slide 31: Resilient Gross Profit

    RESILIENT GROSS PROFIT GROSS PROFIT AND MARGIN 300 ,0 (US$ m) 40,0% 34,8% 35,8% 35,0% 32,1% 250 ,0 245,7 30,0% US$81.4 m 200 ,0 207,4 25,0% Gross profit decrease of 13.0% 23,6% 22,1% 150 ,0 20,0% 153,3 130,4 15,0% Weakening ZAR to US$ exchange rate of 6.3% partially offset inflation 100 ,0 Stable gr

  32. Slide 32: Investing in the Future

    INVESTING IN THE FUTURE Land and buildings Other US$0,6 m US$1,8 m R+D and innovation US$2,3 m Mining fleet US$10,4 m US$114.1 m Assets and Total capital spent HY2024 CAPITAL infrastructure SPENT* US$4,3 m Sustainable operations enabled by continued investment in asset base Includes: Deferred stripp

  33. Slide 33: Balance Sheet

    BALANCE SHEET FREE CASH FLOW (US$ m) US$198.5 m Cash and cash equivalents* Cash generative despite PGM pricing environment and inflationary pressures Net cash flow from operations of US$86.2 m Net cash of US$86.3 m* US$112.3 m Leases 1,9% Total debt Bond 24,3% Short term US$49.4 m 89.4% US$ denomina

  34. Slide 34: Returns to Shareholders

    3.6% RETURNS TO SHAREHOLDERS DIVIDEND YIELD (TTM) US 1.5 cents Interim dividend 15, 0 24,5%* 24.5%* of NPAT including share repurchase programme underway 13, 0 22,0% Policy minimum of 15% of NPAT 20,5% 19,2% 18,5% 11, 0 17,8% 17,1% 17,7% 17,3% 16,3% 17,0% 9,0 US$5 m 12,0% 9,0 7,0 Share repurchase pr

  35. Slide 35: Guidance & Value Proposition

    GUIDANCE & VALUE PROPOSITION

  36. Slide 36: Guidance

    GUIDANCE FY2024 GUIDANCE  PGMs (6E basis) of 145 koz to 155 koz  Chrome concentrates of 1.7 Mt to 1.8 Mt 36 enriching lives through innovating the resources company of the future

  37. Slide 37: Long Term Value Play

    LONG TERM VALUE PLAY Critical commodities Diversification, beneficiation and energy transition Co-producer of PGMs and chrome concentrates, mine two commodities critical to a sustainable future Maxmising the value of our commodities by using innovation and technology 1 6 OUR Output to double at Inte

  38. Slide 38: Tharisa Is an End to End Critical Metals and Energy Solution Provider

    THARISA IS AN END TO END CRITICAL METALS AND ENERGY SOLUTION PROVIDER INNOVATING THE RESOURCES COMPANY OF THE FUTURE 15 years 10 years 9 years ~US$100 m ~US$695 m operations cash generative profitable returned to capital invested shareholders

  39. Slide 39: Questions

    QUESTIONS Kgopotso Mashiane Junior Operations Metallurgist

  40. Slide 40: Disclaimer

    DISCLAIMER These Presentation Materials are for information purposes only and must not be used or relied upon for the purpose of making any investment decision or engaging in any investment activity. Whilst the information contained herein has been prepared in good faith, neither Tharisa plc (the ‘C

Tharisa — Investor Presentation (June 2024) on 6ix