Slide 1: CESC Limited Investor Update – Q4 FY`12
CESC Limited Investor Update –Q4 FY`12 1 1
Slide 2: Performance Summary – Q4 FY`12
Performance Summary – Q4 FY`12 Components Q4 FY`12 Q4 FY`11 % Change Generation (MU) 1997 1826 9% Sales (MU) 1811 1757 3% Sales (Rs Cr.) 1379 939 47% EBIDTA (Rs Cr.) 470 265 77% Net profit (Rs Cr.) 266 112 137% 2 2 2
Slide 3: Performance Summary – FY`12
Performance Summary – FY`12 Components FY`12 FY`11 % Change Generation (MU) 8938 8757 2% Sales (MU) 8396 8243 2% Export (MU) 126 108 17% Sales (Rs Cr.) 4669 4172 12% EBIDTA (Rs Cr.) 1272 1156 10% Net profit (Rs Cr.) 565 488 16% 3 3 3
Slide 4: Plant wise Generation – FY`12
Plant wise Generation – FY`12 5940 5439 1716 1866 1036 1089 Budge Budge Southern Titagarh FY`12 FY`11 4 4 4
Slide 5: Plant load factor (PLF) – FY`12
Plant load factor (PLF) – FY`12 Plant wise PLF is given below PLF (%) – (excl NCGS ) 88.0% PLF % FY`12 FY`11 85.2% Budge Budge 90.2 82.8 Southern 87.4 92.1 Titagarh 81.4 88.8 NCGS** 28 41.4 FY`12 FY`11 **Old Station 5 5 5
Slide 6: T&D Loss & Power Purchase – FY`12
T&D Loss & Power Purchase – FY`12 Net Power Purchase (MU) T&D Loss (Provisional) 1486 12.8% 12.9% 1385 FY`12 FY`11 FY`12 FY`11 6 6 6
Slide 7: Status of Projects Under Implementation
Status of Projects Under Implementation Haldia Phase 1 (600 MW TPP in Haldia, West Bengal) The project is under construction stage and on schedule Dhariwal Infrastructure Ltd (600 MW TPP in Chandrapur, Maharashtra) The project is under construction stage and on schedule Orissa power projec
Slide 8: 3" Ap-sanjiv Goenka
™ 3" Ap-sanjiv Goenka —r- Group
Slide 9: Spencer's Footprint – Mar 2012
Spencer’s Footprint – Mar 2012 Hypers Supers Dailies Regions States TA (‘000) SAS TOTAL >15 k 3k -15k <3k East WB 182 6 2 10 0 18 • TA Hypers – 606 K sft TOTAL 182 6 2 10 0 18 • TA Supers – 97 K sft West Maharashtra 91 2 0 11 0 13 • TA Small stores – 306K sft Gujarat 24 1 0 0 0 1 TOTAL 115 3 0 11 0
Slide 10: Hyper & Super footprint – Mar 2012
Hyper & Super footprint – Mar 2012 Hypers Supers NCR 26 Hypers – 606K sqft Hypers : Ghaziabad, Gurgaon, Dreamz, Haridwar Super : MMX mall, Indirapuram 15 Supers – 97K sqft Siliguri Luckno w Gorakhpur Allahabad Durgapur Vadodara Kolkata Mumbai Hypers : South City, Mani Square, Rash Behari, Axis mall
Slide 11: Highlights Q4 FY`12
Highlights Q4 FY`12 New Stores opened 1 Hyper Store opened – Haridwar (Uttrakhand) Improvement in Sales Average Sales have increased from Rs.957/sqft in FY`11 to Rs. 1060/ sqft in FY`12, a growth of 9.71% Same stores sales have increased from Rs.1000/sqft in FY`11 to Rs. 1147/ sqft in FY`1
Slide 12: Cautionary Statement
Cautionary Statement Statement in this “ Management Discussion and Analysis” describing the company’s objectives, projections, estimates, expectations or predictions may be “ forward looking statements” within the meaning of applicable securities law and regulations. Actual results could differ mate