  1. Slide 1: Spring Hill Gold Project Pre-Feasibility Study and Maiden Ore Reserve

    Slide 1: Spring Hill Gold Project Pre-Feasibility Study and Maiden Ore Reserve

    rsonal use only ASX: PC2 | FSE: D6A Spring Hill Gold Project Pre-Feasibility Study and Maiden Ore Reserve Ashley Pattison Executive Chair & CEO PFS Results Presentation | 24 November 2026 |

  2. Slide 2: Important Notices and Disclaimer

    Slide 2: Important Notices and Disclaimer

    Important Notices and Disclaimer Overview General This presentation has been prepared by PC Gold Limited ACN 609 609 047 (PC Gold or the Company) to provide In this presentation references to 'PC Gold', 'PC Gold Group', 'the Group', 'we', 'us' and 'our' are to PC Gold and summary information about P

  3. Slide 3: Important Notices and Disclaimer

    Slide 3: Important Notices and Disclaimer

    Important Notices and Disclaimer Competent Persons Statement – Mineral Resources Competent Persons Statement – Exploration Target The information in this presentation that relates to the estimation and reporting of Mineral Resources is based on The information in this presentation that relates to Ex

  4. Slide 4: Important Notices and Disclaimer

    Slide 4: Important Notices and Disclaimer

    Important Notices and Disclaimer Production Targets and Forecast Financial Information Non-IFRS Financial Information This presentation includes production targets and forecast financial information derived from production targets. This presentation includes financial measures that are not recognise

  5. Slide 5: Highlights

    Slide 5: Highlights

    rsonal use only 1 Highlights ASX: PC2 | FSE: D6A 5

  6. Slide 6: PFS and maiden Ore Reserve mark a major milestone for PC Gold

    Slide 6: PFS and maiden Ore Reserve mark a major milestone for PC Gold

    PFS and maiden Ore Reserve mark a major milestone for PC Gold Spring Hill moves from resource growth to a defined, funded development project 0.95Moz ~120koz 9.5 years A$1,591M 66% 1.92Moz rsonal use only July 2026 Interim MRE 2 Maiden Ore Reserve Gold pa (first 5 years) Mine life NPV5 (real, pre-ta

  7. Slide 7: Corporate Overview

    Slide 7: Corporate Overview

    Corporate Overview ASX : PC2 A$0.735 ~387M ~A$285M ~A$85.5M ~A$199M 1.92Moz rsonal use only Mineral Resource at Share price¹ Shares on issue² Market capitalisation² Cash at 30-Sep-26 Enterprise value³ 0.3g/t Au cut-off Indicated Resource 1.23Moz EV / Resource oz ~A$104/oz Performance rights 17.1M Li

  8. Slide 8: Experienced and Proven Team

    Slide 8: Experienced and Proven Team

    Experienced and Proven Team BOARD OF DIRECTORS rsonal use only Ash Pattison Rob Jewson Kevin Puil Rick Clark Matt Scully Executive Chair & CEO Non-Executive Director Non-Executive Director Non-Executive Director Non-Executive Director MANAGEMENT Sean Church Peter Harris Ben Broad Wei Li Briohny McMa

  9. Slide 9: Spring Hill is located in the +20Moz Pine Creek Goldfield, NT

    Slide 9: Spring Hill is located in the +20Moz Pine Creek Goldfield, NT

    Spring Hill is located in the +20Moz Pine Creek Goldfield, NT Location Highlights Low Risk Jurisdiction rsonal use only  100% owned 1,035ha granted Mining Lease within a 10,600ha EL package  ML free of Native Title; Federal and NT approvals for Stage 1 open pit mining  World-class +20Moz Pine Cre

  10. Slide 10: PFS Outcomes

    Slide 10: PFS Outcomes

    rsonal use only 2 PFS Outcomes ASX: PC2 | FSE: D6A 10

  11. Slide 11: PFS confirms a standalone, high-margin development

    Slide 11: PFS confirms a standalone, high-margin development

    PFS confirms a standalone, high-margin development A 9.5-year open pit and underground operation feeding a 4Mtpa CIL plant in the Pine Creek Goldfield A$1,591M 66% 1.3 years A$2,870/oz A$413M A$277M rsonal use only NPV5 (pre-tax) IRR (pre-tax) Payback LOM AISC³ Pre-production capital Avg annual free

  12. Slide 12: Spring Hill has outgrown its original plan

    Slide 12: Spring Hill has outgrown its original plan

    Spring Hill has outgrown its original plan PFS proves standalone economics and defines the footprint for revised permits What has changed from earlier expectations Pathway for Permitting & Optimisation rsonal use only Item Earlier expectation PFS outcome 1.92Moz 4Mtpa Mineral Resource¹ 966koz @ 0.8g

  13. Slide 13: Mining, Processing & Costs

    Slide 13: Mining, Processing & Costs

    rsonal use only 3 Mining, Processing & Costs ASX: PC2 | FSE: D6A 13

  14. Slide 14: A long-life open pit and underground gold operation

    Slide 14: A long-life open pit and underground gold operation

    A long-life open pit and underground gold operation PFS mine plan produces ~1.03Moz Au over 9.5 years of production, peaking at ~129koz in CY33 Production Profile – koz Au Recovered by Calendar Year (LOM 1,028koz) Key Metrics rsonal use only Open pit (874koz) Underground (155koz) Production 180 Mine

  15. Slide 15: Bulk open pit mining with high-grade underground upside

    Slide 15: Bulk open pit mining with high-grade underground upside

    Bulk open pit mining with high-grade underground upside Conventional open pit mining of a sheeted vein system, complemented by the high-grade Link Zone Spring Hill Long Section – PFS Mine Design Open Pit Mining rsonal use only  Conventional drill, blast, load and haul  Pits at Hong Kong / Macau, M

  16. Slide 16: Conventional and robust processing flowsheet

    Slide 16: Conventional and robust processing flowsheet

    Conventional and robust processing flowsheet Single-stage crush, SABC grind to P80 106µm, gravity and six-stage CIL – ~94.1% expected LOM recovery Processing Plant Flowsheet – 4Mtpa CIL rsonal use only Primary SAG / Ball Gravity Carbon-in- Elution & Gold Room Crushing Milling Recovery Leach (CIL) El

  17. Slide 17: Pre-production capital of A$413M for a standalone operation

    Slide 17: Pre-production capital of A$413M for a standalone operation

    Pre-production capital of A$413M for a standalone operation Existing cash funds the DFS and early works through to a Final Investment Decision Pre-Production Capital Estimate Funding Pathway rsonal use only Area A$M Processing plant EPC (incl. first fills, spares and buildings) 227.9 ~A$85.5M A$3,44

  18. Slide 18: Competitive operating cost profile

    Slide 18: Competitive operating cost profile

    Competitive operating cost profile LOM AISC of ~A$2,870/oz positions Spring Hill in the lower half of Australian gold producers Life of Mine Costs AISC of Australian Producers – September 2026 Quarter (A$/oz) rsonal use only 4,214 4,267 Cost A$/oz 3,860 3,617 Mining 1,520 3,096 2,912 2,966 Processin

  19. Slide 19: Financials

    Slide 19: Financials

    rsonal use only 4 Financials ASX: PC2 | FSE: D6A 19

  20. Slide 20: Strong cash generation from first gold

    Slide 20: Strong cash generation from first gold

    Strong cash generation from first gold Pre-tax free cash flow of A$2.2B over the life of mine, with payback 1.3 years after first gold A$1,591M 66% A$1,239M 56% A$277M 1.3 years rsonal use only Pre-tax NPV5 Pre-tax IRR Post-tax NPV Post-tax IRR Avg annual FCF (pre-tax) Payback (pre-tax) Annual Cash

  21. Slide 21: Robust economics across a range of gold prices

    Slide 21: Robust economics across a range of gold prices

    Robust economics across a range of gold prices Spring Hill remains strongly NPV-positive at A$4,500/oz, the Ore Reserve price Pre-tax NPV5 by Gold Price (A$M) Other Pre-tax NPV5 Sensitivities (A$M) rsonal use only 2,681 Variable Low Base High 2,318 Grade (−/+10%) 1,192 1,591 1,991 1,955 Recovery (−/

  22. Slide 22: Fully funded through the DFS to a Final Investment Decision

    Slide 22: Fully funded through the DFS to a Final Investment Decision

    Fully funded through the DFS to a Final Investment Decision A$75M institutional placement completed with strong domestic and international demand Equity Raised Since IPO (A$M) Fully Funded 26/27 Workstreams rsonal use only A$75.0M 80,000m 25,000m 20,000m Surface resource RC grade control / Phase 1 d

  23. Slide 23: Approvals and Timeline

    Slide 23: Approvals and Timeline

    rsonal use only 5 Approvals and Timeline ASX: PC2 | FSE: D6A 23

  24. Slide 24: Approvals in place for open pit mining support a streamlined development path

    Slide 24: Approvals in place for open pit mining support a streamlined development path

    Approvals in place for open pit mining support a streamlined development path Key Approvals Development Advantages Mining Lease rsonal use only ✓ 1,035ha ML granted, within a 10,600ha EL package. Additional 443ha of ML applied for in Granted  Granted Mining Lease with no Native October 2026. Title

  25. Slide 25: Processing plant & TSF: approvals pathway

    Slide 25: Processing plant & TSF: approvals pathway

    Processing plant & TSF: approvals pathway EPBC referral to be lodged in Q1 2027 under the reformed EPBC framework, alongside Northern Territory approvals Assessed Against the New Approval Tests Path to Approval rsonal use only Referral lodged 1 Q1 2027 National No unacceptable Net gain Controlled ac

  26. Slide 26: ML application extends tenure over the full PFS site footprint

    Slide 26: ML application extends tenure over the full PFS site footprint

    ML application extends tenure over the full PFS site footprint Granted ML 23812 plus a 443ha ML application covering the TSF western extension and southern access corridor Mining Tenure rsonal use only  ML 23812 granted – 1,035ha, held by TM Gold Pty Ltd (PC Gold), expires January 2046  ML applica

  27. Slide 27: Strong local relationships support our social licence to operate

    Slide 27: Strong local relationships support our social licence to operate

    Strong local relationships support our social licence to operate Investing in Pine Creek and the Northern Territory as Spring Hill moves towards development Strong Foundations rsonal use only  No Native Title over the granted Mining Lease  Federal and NT environmental and mining approvals in place

  28. Slide 28: A clear pathway from PFS to first gold in Q1 CY29

    Slide 28: A clear pathway from PFS to first gold in Q1 CY29

    A clear pathway from PFS to first gold in Q1 CY29 Indicative Development Plan¹ 2025 2026 2027 2028 2029 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 rsonal use only A$24M A$75M placement & Board ✓ IPO – A$13.5M raised ✓ placement ✓ renewal Corporate 1.92Moz Interim MRE update (Mar-27) – On Track MRE ✓

  29. Slide 29: Resource, Reserve & Growth

    Slide 29: Resource, Reserve & Growth

    rsonal use only 6 Resource, Reserve & Growth ASX: PC2 | FSE: D6A 29

  30. Slide 30: 951koz maiden Ore Reserve underpins development

    Slide 30: 951koz maiden Ore Reserve underpins development

    951koz maiden Ore Reserve underpins development Probable Ore Reserve of 35.5Mt @ 0.83g/t Au for 951koz, from open pit and underground Spring Hill Maiden Ore Reserve Estimate Key Information Contained Source Tonnes (Mt) Grade (g/t Au)  Based on the July 2026 Interim MRE of 1.92Moz, including 1.23Moz

  31. Slide 31: Growing Resource base supports further Reserve growth

    Slide 31: Growing Resource base supports further Reserve growth

    Growing Resource base supports further Reserve growth The PFS is built on the July 2026 Interim MRE; the March 2027 MRE update will feed the DFS Pre-Feasibility Study Inputs Definitive Feasibility Study Inputs rsonal use only Published 21 July 2026 (25 April 2026 assay Mineral Resource Update cut-of

  32. Slide 32: Spring Hill Resource has grown 98% to 1.92Moz

    Slide 32: Spring Hill Resource has grown 98% to 1.92Moz

    Spring Hill Resource has grown 98% to 1.92Moz, with Indicated ounces up 155% Growth driven by 30,000m+ of drilling, Photon Assay re-assay and the new Link Zone discovery Spring Hill Mineral Resource (koz Au) rsonal use only Resource definition and infill drilling +751koz (+155%) Indicated up from 48

  33. Slide 33: 1.92Moz Resource provides the foundation for a maiden Ore Reserve

    Slide 33: 1.92Moz Resource provides the foundation for a maiden Ore Reserve

    1.92Moz Resource provides the foundation for a maiden Ore Reserve 75.9Mt @ 0.8g/t Au for 1.92Moz, including 47.3Mt @ 0.8g/t Au for 1.23Moz classified as Indicated Spring Hill Interim Mineral Resource – 3D View July 2026 Mineral Resource Estimate rsonal use only Category Tonnes (Mt) Grade (g/t Au) Co

  34. Slide 34: Resource defined over just 1.2km of strike and remains open

    Slide 34: Resource defined over just 1.2km of strike and remains open

    Resource defined over just 1.2km of strike and remains open in all directions Updated long section of the 1.92Moz Interim MRE – within only ~15% of the known mineralised strike Spring Hill Long Section – Interim MRE (July 2026) Key Information rsonal use only Open along strike and at depth Indicated

  35. Slide 35: Post-MRE drilling continues to return grades above the resource block model

    Slide 35: Post-MRE drilling continues to return grades above the resource block model

    Post-MRE drilling continues to return grades above the resource block model Results to be incorporated into the MRE update targeted for March 2027 Hong Kong Main Zone Macau Link Hong Kong / Link Link Zone (Sep 2026) South & Hong Kong Footwall Cross Section rsonal use only  29.65m @ 4.32g/t Au from

  36. Slide 36: October diamond results confirm thick, stacked high-grade zones

    Slide 36: October diamond results confirm thick, stacked high-grade zones

    October diamond results confirm thick, stacked high-grade zones at Spring Hill Five holes return ~70 gram-metres or more and the Link Zone intercept doubles in width – all feeding the March 2027 MRE Thick, Stacked Zones Link Zone – Additional Results Collar Plan – (Oct 2026) Assays Complete & Coarse

  37. Slide 37: Exploration RC drilling continues to extend mineralisation strike

    Slide 37: Exploration RC drilling continues to extend mineralisation strike

    Exploration RC drilling continues to extend mineralisation strike Results to be incorporated into the MRE update targeted for March 2027 Eastern Zone New North Link Macau Extended RC Collars along strike from MRE rsonal use only XRC018 (Eastern Lode) XRC004 (North Link) • 2m @ 7.08 g/t Au from 98m X

  38. Slide 38: Three high-grade domains offer underground upside alongside the bulk open pit

    Slide 38: Three high-grade domains offer underground upside alongside the bulk open pit

    Three high-grade domains offer underground upside alongside the bulk open pit Link Zone, Main Adit and the new Southern Adit target are all being tested in 2027 Link Zone Main Adit Southern Adit (New) rsonal use only 193koz @ 5.4g/t Au ~21koz @ ~30g/t Au 20.35m @ 13.04g/t Au Maiden Resource from jus

  39. Slide 39: Significant growth potential beyond the current Resource footprint

    Slide 39: Significant growth potential beyond the current Resource footprint

    Significant growth potential beyond the current Resource footprint Three key zones defined across a +3km corridor north of the MRE, plus extensions along strike Updated Targeting Domains (Cube) Open Pit Exploration Targets Resource Extension Targets rsonal use only  1–2Moz Exploration Target Lasagn

  40. Slide 40: Site infrastructure and drilling capacity in place to accelerate Spring Hill

    Slide 40: Site infrastructure and drilling capacity in place to accelerate Spring Hill

    Site infrastructure and drilling capacity in place to accelerate Spring Hill Pine Creek Camp Drilling Photon Assay rsonal use only Photon Assay Lab Location  Former Territory Iron camp low cost  Four rigs operating – three diamond and an  Photon Assay technology adopted and acquisition at Pine Cr

  41. Slide 41: A Unique Value Proposition

    Slide 41: A Unique Value Proposition

    A Unique Value Proposition ASX : PC2 rsonal use only Strong Team and Spring Hill is a Clear Pathway Focused Balance Sheet Growing Gold Asset to Development on Growth • Board strengthened with • Resource up 98% to • Federal and NT approvals • ~125,000m drill program proven mine builders Rick 1.92Moz

  42. Slide 42: Connect with PC Gold

    Slide 42: Connect with PC Gold

    rsonal use only ASX: PC2 | FSE: D6A Connect with PC Gold Ashley Pattison Executive Chair & CEO +61 8 6313 3996 | admin@pcgold.com.au Paul Berson Investor Relations +61 (0) 421 647 445 | paul@corporatestorytime.com U38/460 Stirling Highway, Peppermint Grove WA 6011 pcgold.com.au 42

  43. Slide 43: Appendix

    Slide 43: Appendix

    rsonal use only Appendix ASX: PC2 | FSE: D6A 43

  44. Slide 44: Three-stage open pit builds to a ~59ha final footprint

    Slide 44: Three-stage open pit builds to a ~59ha final footprint

    Three-stage open pit builds to a ~59ha final footprint PFS open pit design: 36.3Mt mined at 0.80g/t Au for 874koz Au recovered Stage 1 Stage 2 Stage 3 rsonal use only 23.0 ha 21.3 ha 58.6 ha Plan area Plan area Plan area 23.0 ha new ground · Crest RL 148–250 m 9.4 ha new ground · Crest RL 160–259 m

  45. Slide 45: Underground mine plan targets high-grade lodes below the open pit

    Slide 45: Underground mine plan targets high-grade lodes below the open pit

    Underground mine plan targets high-grade lodes below the open pit PFS underground design: 1.94Mt mined at 2.61g/t Au for 155koz Au recovered rsonal use only 1.94Mt underground ore mined 2.61g/t Au mined grade 155koz Au gold recovered pcgold.com.au Production target – refer to the Cautionary Statemen

  46. Slide 46: Four-stage TSF raised from RL 156.5m to RL 177.8m

    Slide 46: Four-stage TSF raised from RL 156.5m to RL 177.8m

    Four-stage TSF raised from RL 156.5m to RL 177.8m TSF footprint grows from 92ha at Stage 1 to 136ha at Stage 4 Stage 1 Stage 2 Stage 3 Stage 4 rsonal use only RL 156.5 m RL 163.5 m RL 170.5 m RL 177.8 m Embankment crest Embankment crest Embankment crest Embankment crest Embankment 17.1 ha Embankment

  47. Slide 47: Infrastructure layout supports a simple, low-risk development

    Slide 47: Infrastructure layout supports a simple, low-risk development

    Infrastructure layout supports a simple, low-risk development Granted Mining Lease, established regional infrastructure and a camp already in hand Tailings Storage Facility Power rsonal use only  ~36.9Mt design capacity; capacity for  Diesel versus Gas assessed in the the full 38.2Mt production ta

  48. Slide 48: Gas-fired power cuts unit energy cost by ~59% vs diesel

    Slide 48: Gas-fired power cuts unit energy cost by ~59% vs diesel

    Gas-fired power cuts unit energy cost by ~59% vs diesel PFS preferred option: 31.9MVA Jenbacher gas power station for a 15.6MW average plant load Power Option Comparison All-in Power Cost (c/kWh) rsonal use only Item Diesel Gas 37.1c Supply basis BOO Model BOO Model Generation fleet 26 x KTA50 G12 1

  49. Slide 49: 3.5km gas spur line connects Spring Hill to the network

    Slide 49: 3.5km gas spur line connects Spring Hill to the network

    3.5km gas spur line connects Spring Hill to the network A$12.7M gas spur line capital estimate (ATCO, P80): A$10.6M in pre-production capital, A$2.1M committed pre-FID Gas Spur Line Route Options Spur Line Route rsonal use only  3.5km DN100 Class 600 buried steel spur line built to AS2885, from a t

  50. Slide 50: Pre-Feasibility Study consultants

    Slide 50: Pre-Feasibility Study consultants

    Pre-Feasibility Study consultants Independent specialists engaged across every PFS workstream rsonal use only Resource Estimation Mining Engineering Process Engineering Metallurgical Testwork Geotechnical Hydrogeology & Water Tailings Storage Power Supply Environmental & Approvals Assaying pcgold.co

  51. Slide 51: Appendix: Spring Hill Mineral Resource by Zone

    Slide 51: Appendix: Spring Hill Mineral Resource by Zone

    Appendix: Spring Hill Mineral Resource by Zone Spring Hill Mineral Resource Estimate by Zone – July 2026 Interim MRE vs June 2024 MRE (0.3g/t Au cut-off) July 2026 Interim MRE June 2024 MRE rsonal use only Zone Tonnes Grade (g/t Au) Ounces Au Tonnes Grade (g/t Au) Ounces Au Indicated Hong Kong / Mac

  52. Slide 52: Appendix: Peer AISC source data

    Slide 52: Appendix: Peer AISC source data

    Appendix: Peer AISC source data Operation Company AISC A$/oz AISC as reported in each company's September 2026 quarterly report (released October 2026). Ramelius shown at group level. Group Evolution Mining 1,653 rsonal use only Karlawinda Capricorn Metals 2,005 Group (Mt Magnet hub) Ramelius Resour

Source: ASX announcement, Nov 24, 2026