Sasol Limited · JSE:SOL

Sasol — Corporate Update

13 slides from Sasol's corporate update

  1. Slide 1: C3 Stabilisation Project

    C3 Stabilisation Project better together ... we deliver

  2. Slide 2: Construction of a propylene feed stabilisation facility

    The C3 stabilisation project was tasked with the construction of a propylene feed stabilisation facility. This included the fabrication and installation of six of the largest pressure vessels ever fabricated in South Africa, consisting of one de-propaniser drum and five propylene storage bullets. Th

  3. Slide 3: Proudly manufactured in South Africa for Sasol

    | proudly manufactured in South Africa for Sasol

  4. Slide 4: Stabilising the C3 value chain at Sasol Secunda

    The C3 stabilisation project will stabilise the C3 valve chain at the Sasol Secunda plant by de- linking the extremely tight integration between the upstream synthol reactors, propylene extraction units and the downstream chemical plants with the appropriate buffer and storage facilities. This invol

  5. Slide 5: er ae aa ms ae

    er ae aa ms ae Ty ea een a eel ey Nei Naess (SS. * Sess: S22 fT RS SS XPS > AES A AF,

  6. Slide 6: Project objective: increase propylene extraction and feed availability

    The main objective of the project was two-fold: To increase the extraction of propylene and increase the availability of propylene feed for beneficiation in the downstream units. With this new capacity, Sasol aims to reach 85% extraction and monetise an additional 58 000 tons per annum propylene. be

  7. Slide 7: Safety

    Safety Total Hours Worked : 2 078 440. Total RC Free Hours: 1 130 740. Manpower Peak: 1001 people on site. RCR: 0.19. better together ... we deliver 7

  8. Slide 8: > 22110/2013. 12-10 -

    > 22110/2013. 12-10 -

  9. Slide 9: Overall Progress

    Overall Progress TCCC (Total Care Custody and Control): 7 April 2014. Ready for Commissioning (RFC): 30 May 2014. Ready for Operation (RFO): 22 June 2014. Beneficial Operation (BO): 27 June 2014 (Board Commitment: 30 June 2014). better together ... we deliver 9

  10. Slide 10: Slide 10

  11. Slide 11: The project made history on a number of fronts

    The project made history on a number of fronts. The team installed five of the largest pressurised vessels ever constructed on South African soil and the foam glass fire proofing on the bullets has never been applied on this scale before. better together ... we deliver 11

  12. Slide 12: better together ... we deliver

    better together ... we deliver 12

  13. Slide 13: Group Technology Project of the Year 2014

    Group Technology Project of the Year 2014 C3 Stabilisation Project better together ... we deliver