Slide 1: C3 Stabilisation Project
C3 Stabilisation Project better together ... we deliver
Slide 2: Construction of a propylene feed stabilisation facility
The C3 stabilisation project was tasked with the construction of a propylene feed stabilisation facility. This included the fabrication and installation of six of the largest pressure vessels ever fabricated in South Africa, consisting of one de-propaniser drum and five propylene storage bullets. Th
Slide 3: Proudly manufactured in South Africa for Sasol
| proudly manufactured in South Africa for Sasol
Slide 4: Stabilising the C3 value chain at Sasol Secunda
The C3 stabilisation project will stabilise the C3 valve chain at the Sasol Secunda plant by de- linking the extremely tight integration between the upstream synthol reactors, propylene extraction units and the downstream chemical plants with the appropriate buffer and storage facilities. This invol
Slide 5: er ae aa ms ae
er ae aa ms ae Ty ea een a eel ey Nei Naess (SS. * Sess: S22 fT RS SS XPS > AES A AF,
Slide 6: Project objective: increase propylene extraction and feed availability
The main objective of the project was two-fold: To increase the extraction of propylene and increase the availability of propylene feed for beneficiation in the downstream units. With this new capacity, Sasol aims to reach 85% extraction and monetise an additional 58 000 tons per annum propylene. be
Slide 7: Safety
Safety Total Hours Worked : 2 078 440. Total RC Free Hours: 1 130 740. Manpower Peak: 1001 people on site. RCR: 0.19. better together ... we deliver 7
Slide 8: > 22110/2013. 12-10 -
> 22110/2013. 12-10 -
Slide 9: Overall Progress
Overall Progress TCCC (Total Care Custody and Control): 7 April 2014. Ready for Commissioning (RFC): 30 May 2014. Ready for Operation (RFO): 22 June 2014. Beneficial Operation (BO): 27 June 2014 (Board Commitment: 30 June 2014). better together ... we deliver 9
Slide 10: Slide 10
Slide 11: The project made history on a number of fronts
The project made history on a number of fronts. The team installed five of the largest pressurised vessels ever constructed on South African soil and the foam glass fire proofing on the bullets has never been applied on this scale before. better together ... we deliver 11
Slide 12: better together ... we deliver
better together ... we deliver 12
Slide 13: Group Technology Project of the Year 2014
Group Technology Project of the Year 2014 C3 Stabilisation Project better together ... we deliver