  1. Slide 1: PEA Presentation October 2020

    PEA PRESENTATION October 2020 Photo by Magda Biernat

  2. Slide 2: Forward Looking Statements

    Forward Looking Statements The reader is advised that the PEA summarized in this presentation is preliminary in nature and is intended to provide an initial, high- level review of the project’s economic potential and design options. The PEA mine plan and economic model includes numerous assumptions

  3. Slide 3: Corporate Structure

    Corporate Structure Stock Symbol NBY - TSX-V Major Shareholders (fully diluted) Share Price $0.81 Osisko Gold Royalties 20% Management 8% Shares Outstanding 52 M Caisse Dépôt Placement 4% Options 4M Warrants 3M Market Cap $42 M Cash on hand $1.4 M 52-week High/Low 3M Share Performance 1,000 $1.00 80

  4. Slide 4: Board & Management

    Board & Management Management Directors Claude Dufresne, P.eng. - President & CEO Serge Savard. - Chairman + 20 years Nb business: Ex-NHL, Businessman, Real Estate Iamgold, Camet, Cambior Derek Teevan, MES - VP Aboriginal & Governmental Jacques Bonneau, P.Geo - Director + 20 years permitting: Ex-Maz

  5. Slide 5: An Investment in NioBay

    An Investment in NioBay Minable Historic Resource with Team Capable of Bringing it Through to Production Our Value Experienced Team A Team that has Built Mines in the Region Claude Dufresne P. Eng. - CEO & Director Jacques Bonneau, P.GEO - Director • 40+ years experience in the mining industry • Ex-

  6. Slide 6: Niobium – A Green Metal

    Niobium – A Green Metal Why Niobium? • Niobium transforms materials. Materials that can build greener structures, help make energy cleaner and mobility more sustainable. • $10 of Niobium reduces the weight of a mid-sized car by 15kt 150kg leads to ~ 5% increased fuel efficiency + 0.02% Nb $25M Savin

  7. Slide 7: James Bay Niobium Project

    James Bay Niobium Project Description Project Map • 42 km south of Moosonee, in the James Bay Lowlands, Ontario, Canada • 42 km south of Moosonee, ON • Airport (2 runways, 1.2km & 1km) • Rail line from Cochrane (4X week) • Powerline 38 km from project • Winter Road (Wetum Road) – 12km from project •

  8. Slide 8: 2020 Mineral Resource Estimate

    2020 Mineral Resource Estimate • The Updated MRE 2020 was published by Roscoe Postle Associates Inc following 2020 winter program (versus 2018 NI43-101) based underground mine. Tonnes Grade Contained Nb2O5 Classification (cut-off 0.3%Nb2O5) (Mt) (%Nb2O5) (Mkg) Indicated 30 (+4 or 14%) 0.53 158 (+19

  9. Slide 9: PEA Mining Scenarios

    PEA Mining Scenarios 1. 1. Open Pit 2. Open 2. Open Pit Pit + Underground + Underground 3. Underground 3. Underground + Employment/contractor Opportunity + Employment/contractor Opportunity + Lower footprint (borrow pit ?) + Lower mining cost + Lower footprint + Carbon Free possibility (EV fleet) +

  10. Slide 10: PEA Summary

    PEA Summary Open Pit + Open Pit Underground UG Pre-Tax Internal Rate of Return (IRR) 33.6% 33.4% 26.0% Pre-Tax Net Present Value (NPV) 8% $1,475 M $1,268 M $1,104 M • Very Robust Economics Pre-Tax Payback (years) 2.6 years 2.5 years 3.8 years After-Tax Internal Rate of Return (IRR) 27.5% 27.0% 21.6%

  11. Slide 11: Niobium Peer Group Comparison

    Niobium Peer Group Comparison Niobay’s James Bay has competitive resources and high recoveries amongst Niobium Peer Group Resources (Mt) Recoveries (%) OPEX Comparison (US$/kg Nb) 90 85% $140 84Mt2 82%1 $122.531 $120 80 80% 78% 75Mt4 72Mt3 $96.672 71Mt $100 70 75% $80 60 70% $60 65%4 50 65% 63%2 $37

  12. Slide 12: Niobium Peer Group Comparison

    Niobium Peer Group Comparison NPV/ CAPEX Mine life / Payback CAPEX / LOM Nb Prod. 2,500 $6.881 $7.00 Niocorp1 Elk Creek, NioCorp 12.6 1 2,000 $6.00 $5.00 1,500 James Bay OP, NioBay 9.4 NPV (C$ M) $4.00 US$/ kg Nb $3.572 1,000 $2.943 $2.884 Niobay $3.00 Panda Hill, Cradle 6.3 3 $2.39 Cradle3 $2.00 50

  13. Slide 13: High Value Relative to Base Metals

    High Value Relative to Base Metals The project is well positioned to deliver high returns will relatively low initial capital requirement compared to Exploration/ Development stage base metal projects  NAV/CAPEX of 1.98x vs. 1.42x P/NAV1 NAV/CAPEX1 Eva, Copper Mountain, Australia, Cu 0.29x Vermelho

  14. Slide 14: High Value Relative to Base Metals

    High Value Relative to Base Metals Project (Mt) (C$ M) (C$ M) Payback Project NPV/ P/ life/ Company Country Project Metal Resource NPV Capex IRR Years Life CAPEX NAV Payback Sol Gold Ecuador Cascabel Cu 2,429 5,741 3,584 25.9% 3.6 55 1.60x 0.15 15.3 Capstone Chile Santo Domingo Cu 392 2,191 2,878 23

  15. Slide 15: Additional Information

    ADDITIONAL INFORMATION TSXV:NBY 15

  16. Slide 16: James Bay Niobium Project PEA

    James Bay Niobium Project PEA PEA Financial Highlights Compelling Results Open Pit+ Scenario Open Pit Underground Underground NPV/Capex – 1.98x Average Annual LOM Nb Production T Nb 5,470 6,213 6,283 • Profitability index key comparison against base Net Revenue metals and Niobium company peers Net R

  17. Slide 17: LOM Production and Processing Summary

    James Bay Niobium Project PEA LOM Production and Processing Summary Open Pit+ Scenario Open Pit Underground Underground LOM Production OP Total tonnage mined kt 198,143 24,317 - Ore tonnage mined kt 70,845 9,764 - Ore grade mined % Nb2O5 0.44 0.51 - UG Total tonnage mined kt - 43,929 53,625 Ore tonn

  18. Slide 18: Design and Optimization

    Design and Optimization Processing Plant Design Criteria Mining Optimization Criteria General OP OP+UG UG Category OP OP+UG UG Annual production tpy 2,400,000 Niobium price US$/kg Nb 45.00 Mill throughput tpd 6,600 Marketing & converter costs US$/kg Nb 5.00 Mill availability % 93 Royalty costs US$/k

  19. Slide 19: James Bay Project LOM Costs

    James Bay Project LOM Costs Capital and Operating Cost Breakdown Pre-Production CAPEX (C$ 000) Open Pit OP + UG Underground Infrastructure 133,575 133,575 112,615 Power & Electrical 31,485 31,485 31,485 Water & Tailings 31,413 13,575 20,482 Mobile Equipment 5,612 5,612 5,612 Mining - - 117,729 Minin

  20. Slide 20: Niobium Peer Group Comparison

    Niobium Peer Group Comparison 1 2 3 (C$ M) Scenario 1 Scenario 2 Scenario 3 Key Asset James Bay James Bay James Bay Elk Creek Aley Panda Hill4 Location Ontario Ontario Ontario Nebraska BC Tanzania Stage Exploration Exploration Exploration Feasibility Halted Halted Mine Type OP OP+UG UG UG OP OP Mark

  21. Slide 21: Niobium vs Scandium

    Niobium vs Scandium The global Scandium market is on the verge of oversupply. Combined, Scandium International’s Nyngan Project and NioCorp’s Elk Creek Project would add ~105tpa of Scandium to the global market, 3x current demand of ~20tpa. Scandium Demand & Supply Niobium Demand & Supply 110 220,00

  22. Slide 22: Processing Schedule Scenarios

    Processing Schedule Scenarios Scenario 1: Open Pit Scenario 2: Open Pit + Underground 2,500 0.60% 2,500 0.60% Ore Grade 9%Nb2O5) Ore Grade (%Nb2O5) 2,000 0.50% 2,000 0.50% Ore Processed (kt) Ore Processed (kt) 0.40% 1,500 0.40% 1,500 0.30% 1,000 0.30% 1,000 0.20% 500 0.20% 500 0.10% - 0.10% - - Ore

  23. Slide 23: Production Schedule Scenarios

    Production Schedule Scenarios Scenario 1: Open Pit Scenario 2: Open Pit + Underground 8,000 8000 7,000 7000 Niobium Production (t) 6,000 6000 Nobum Production (t) 5,000 5000 4,000 4000 3,000 3000 2,000 2000 1,000 1000 - 0 Scenario 3: Underground 8,000 7,000 Niobium Production (t) 6,000 5,000 4,000 3

  24. Slide 24: Scenario 1: Open Pit Economics

    James Bay Niobium Project Economics Scenario 1: Open Pit Economics Project After-tax Free Cashflow 400 4,000 350 3,500 300 3,000 250 2,500 NPV & IRR Sensitivity to Niobium Price 200 2,000 Cumulative Cashflow ($C M) Niobium Price ($US/kg Nb) $35 $40 $45 $50 $55 150 1,500 Cashflow (C$ M) 100 1,000 Aft

  25. Slide 25: Scenario 2: Open Pit + Underground Economics

    James Bay Niobium Project Economics Scenario 2: Open Pit + Underground Economics Project After-tax Free Cashflow 300 3,000 250 2,500 200 2,000 150 1,500 NPV & IRR Sensitivity to Niobium Price Cumulative Cashflow ($C M) 100 1,000 Niobium Price ($US/kg Nb) $35 $40 $45 $50 $55 Cashflow (C$ M) 50 500 Af

  26. Slide 26: Scenario 3: Underground Economics

    James Bay Niobium Project Economics Scenario 3: Underground Economics Project After-tax Free Cashflow 300 3,000 250 2,500 200 2,000 150 1,500 NPV & IRR Sensitivity to Niobium Price Cumulative Cashflow ($C M) 100 1,000 Niobium Price ($US/kg Nb) $35 $40 $45 $50 $55 After-Tax NPV8 210 472 733 992 1,251

  27. Slide 27: Open Pit Mining Fleet

    Open Pit Mining Fleet Haul Truck Komatsu HD605-8 Excavator PC1250-8 70t (X 9) 7m3 (X 2) Wheel Loader Komatsu WA800 Track Dozer D155AX-8 8.2m3 (X 1) 317HP (X 3) TSXV:NBY 27

  28. Slide 28: Underground Mining Fleet

    Underground Mining Fleet Sandvick LH621 Loader Sandvick TH663i Truck Tramming capacity : 21t Payload capacity : 63 t (X 6) Sandvick Articulated Sandvick DD422i Jumbo ITH DU421-C Hole size: 89 – 216 mm Hole size:43 – 64 mm TSXV:NBY 28

  29. Slide 29: Niobium Processing

    Niobium Processing Crushing & Grinding • The primary grinding will be done using a Semi autogenous ( SAG ) mill in close circuit with cyclone at a final product passing 500 microns Gravity Crushing Drying & • The characteristics of the James Bay ore provide the opportunity to Converter remove a sign

  30. Slide 30: Corporate Social Responsibility

    Corporate Social Responsibility How we Intend to support local communities: • Watershed Protection and Maintenance • Employment Opportunities Community • Health Care and Services Impact • Access to education • Minimize Footprint and Preserve Natural Ecology TSXV:NBY 30

  31. Slide 31: Thank You !

    Thank You ! Claude Dufresne, P.Eng. President & CEO NioBay Metals Inc 300-1100 Ave Canadiens-de-Montreal Montreal, QC H3B 2S2 cdufresne@niobaymetals.com TSXV:NBY 31

  32. Slide 32: Appendix

    NioBay! METALS Appendix TSXV:NBY 32

  33. Slide 33: Niobium Market

    NioBay! METALS Niobium Market TSXV:NBY 33

  34. Slide 34: What is Niobium?

    What is Niobium? Additive in steelmaking process. Niobium improves steel properties. Production of High Strength Low Alloy Steel TSXV:NBY 34

  35. Slide 35: Niobium Demand Globally

    Niobium Demand Globally World Consumption (t Nb) 75,000 60,000 Down 17% Q1 2020 45,000 (COVID-19) 30,000 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 $45 Price Ferro-Niobium $40 USD/kg Nb $35 $30 Down 2% Q1 2020 (COVID-19) $25 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 TSXV:NBY Sour

  36. Slide 36: Niobium Demand by Region

    Niobium Demand by Region 2019 2009 Others 26% China Others 25% 30% China 36,500 t 38% 82,000 t Nb Nb N.A. 17% N.A. Europe 15% 28% Europe 21% TSXV:NBY Source: HIS Markit for ferro-niobium market 36

  37. Slide 37: Niobium Supply

    Niobium Supply Capacity 100,000 tpy Nb +500M t @ 2.5% Nb2O5 2019 Sales Price setter – cost: <10$/kg Nb Araxa, Brazil Capacity 8,500 tpy Nb 50M t @ 1% Nb2O5 8% Poor recovery, Chinese owned Cost: +12$/kg Nb, 11% Catalao, Brazil 82,000 t Capacity 7,000 tpy Nb Nb +75M t @ 0.56% Nb2O5 80% Only U/G Nb ope

  38. Slide 38: Marketing Strategy

    Marketing Strategy Sale FeNb (t Nb) 250,000 James Bay Project aims to supply no more than 5% WS No ‘action’ anticipated by CBMM 200,000 150,000 CBMM sales continue to grow 100,000 50,000 - 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 World James Bay CBMM TSXV:

  39. Slide 39: Marketing Strategy

    Marketing Strategy Looking to become the smallest producer with 5% market share 90% 6.0% 5.5% 85% 5.0% Step-Up possibility ? 4.5% 80% 4.0% 75% 3.5% 3.0% 70% 2.5% James Bay Sand Box 65% 2.0% 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 CBMM Step-Up James Bay TS

  40. Slide 40: 2020 Winter Drill Program

    2020 Winter Drill Program 600N 400N 200N 0 TSXV:NBY 40

  41. Slide 41: Resources Classification

    Resources Classification Unexplored area TSXV:NBY 41

  42. Slide 42: Trend Analysis

    Trend Analysis % Nb2O5 Unexplored area TSXV:NBY 42

  43. Slide 43: Moose Cree First Nation

    Moose Cree First Nation • Chief & Council elected July 2019 (4 years term) • Favorable to engage with resource developers • Seeking opportunities for local community • Signed a “Protection Agreement’’ for early exploration programs (December 2019) • Regular Information Sessions with Community on the

  44. Slide 44: Regulatory Roadmap

    Regulatory Roadmap TSXV:NBY 44

  45. Slide 45: Next Steps for 2020 & H1 2021 (JBN)

    Next Steps for 2020 & H1 2021 (JBN) • Mineral Resource Update NI43-101 • Protocol Development MCFN • RPA – July 2020 COMPLETED • Seeking support till construction decision • Q3 2020 • Metallurgical test works • SGS Lakefield – Q3 2020 • Geophysics (fall 2020) • First set results support historical (