Iron Road Ltd · ASX:IRD

Iron Road — 11th SA Exploration and Mining Conference (December 2014)

18 slides from Iron Road's conference presentation, Dec 5, 2014

  1. Slide 1: Central Eyre Iron Project: Beyond the Definitive Feasibility Study

    Central Eyre Iron Project Beyond the Definitive Feasibility Study www.ironroadlimited.com.au Larry Ingle, General Manager  11th SA Exploration and Mining Conference  5th December 2014

  2. Slide 2: Cautionary Statements

    Cautionary Statements Forward Looking Statements This announcement contains certain statements with respect to future matters which may constitute "forward-looking statements". Such statements are only predictions and are subject to inherent risks and uncertainties which could cause actual values, r

  3. Slide 3: Cautionary Statements

    Cautionary Statements Modelling based upon 25 year mine life, consisting of: • Initial 17 years using Proven and Probable Mining Reserve of 2,071Mt @ 15.5% iron (200x100m, 100x50m diamond drill spacing). • Further eight years using 28% Measured, 24% Indicated and 48% Inferred Resources of 1,303Mt @

  4. Slide 4: CEIP Snapshot

    CEIP Snapshot • Magnetite project with three components – mine and integrated logistics chain comprising rail & port development. • Production of 21.5Mtpa premium iron concentrate ~67% Fe & ~ -125µm (p80). • Coarse-grained iron concentrate to be marketed as high quality sinter blend stock. • Mineral

  5. Slide 5: CEIP Components

    CEIP Components Mine • Two pits, largest 6.5km long, 1.2km wide. • Includes beneficiation plant, integrated waste landform & rail loadout. Infrastructure Corridor • Single corridor- 148km heavy rail, service road, power line & water pipeline. • Multi-user. Port • Twin capesize berths, no dredging, 7

  6. Slide 6: DFS Project Metrics

    DFS Project Metrics Mine Life 25+ years Project IRR Capital Cost Capital Intensity Operating Cost (per Annual Tonne) (FOB) /t 21% US$3.98B US$185 US$44.33 Ungeared, post-tax 6 * see Appendix 3 for key financial assumptions

  7. Slide 7: Innovation using Proven Technologies

    Innovation using Proven Technologies In-Pit Crushing & Conveying (IPCC) • Mine purpose designed for IPCC, semi-mobile crushers in pit. • Trucks deliver both ore & waste to crushers, conveyed to surface. High Density Modularisation (Beneficiation Plant) • Modules wet commissioned in construction yard

  8. Slide 8: Post-DFS Work

    Post-DFS Work Mining • IPCC with mobile crushers- shovel / loader direct tip into crusher- from diesel  surplus electrical energy, long term contract. • Thiess-RWE JV pit re-optimisation  taking into account expanded Mineral Resource Estimate & Mineral Reserve. Beneficiation • Inclusion of regrind

  9. Slide 9: Transition to Optimised Mining Method

    Transition to Optimised Mining Method Traditional load & haul IPCC IPCC Semi-mobile crushers Mobile crushers 93 x 350t trucks 32 x 350t trucks 12 x 350t trucks (est.) 800kL diesel (pd) 150kL diesel (pd) 50kL diesel (pd) 1150 employees 350 employees 250 employees (est.) CAPEX US$1350 CAPEX US$480 CAP

  10. Slide 10: Beneficiation Comparison

    Beneficiation Comparison Scenario 1 Scenario 2 DFS Current Optimisation Study 21.5Mtpa pellet feed 21.5Mtpa Pellet Feed 21.5Mtpa Sinter Feed 24Mtpa Sinter Feed Fine grind Fine grind Coarse grind Coarse grind p80 < -40µm p80 < -40µm p80 < -125µm p80 < -120µm with gravity circuit with gravity circuit

  11. Slide 11: Stage IX Drilling

    Stage IX Drilling Section 11 560540E

  12. Slide 12: Stage IX Drilling

    Stage IX Drilling 200m Lso0m Lsoom Scale 200m 200 Metres [Gi Mineral Resource (OFS) Mineralised Envelope (Stage IX Driling) Significant intersection (240m and >8% Fe) DFS Pit Shell with Stage IX Driling (November 2014) Cross - Section 560540E Looking West Stage IX Drilling IRD526 /IRD523 A 762m @ 14

  13. Slide 13: Collaborative Research – PhD Project

    Collaborative Research – PhD Project Influence of crustal architecture and reworking on iron formations of the southern Gawler Craton - Kathleen Lane PRICE METASEDIMENTS Current understanding of ~730Ma geological age Previous understanding of geological age 13

  14. Slide 14: Collaborative Research

    Collaborative Research “Age constraints on the timing of iron ore mineralisation in the southeastern Gawler Craton” Warramboo K. Lane, L. Jagodzinski, R. Dutch, A. Reid, M. Hand. Magnetite Gneiss Australian Journal of Earth Sciences (in prep.) Price Metasediments 14

  15. Slide 15: Thank-you

    Visit us at Table 17 in the Expo Area Thank-you • Geology is driving the approach to mining • Mineralogy is driving the approach to metallurgy 15 • Opportunity is driving the approach to engineering the project

  16. Slide 16: Appendix 1 – CEIP Resource Statement & Indicative Concentrate Specifications

    Appendix 1 – CEIP Resource Statement & Indicative Concentrate Specifications CEIP Global Mineral Resource Tonnes Fe SiO2 Al2O3 P Location Classification (Mt) (%) (%) (%) (%) Measured 2,222 15.69 53.70 12.84 0.08 Murphy South/Rob Roy Indicated 474 15.6 53.7 12.8 0.08 Inferred 667 16 53 12 0.08 Boo Lo

  17. Slide 17: Appendix 2 – CEIP Reserve Statement

    Appendix 2 – CEIP Reserve Statement CEIP Global Mineral Reserve Tonnes Fe Location Classification (Mt) (%) Proved 1,871 15.6 Murphy South/Rob Roy Probable 200 15.1 Total 2,071 15.5 The information in this report that relates to Reserves estimated for Murphy South / Rob Roy (MSRR) is based on and fai

  18. Slide 18: Appendix 3 – Key DFS Financial Assumptions

    Appendix 3 – Key DFS Financial Assumptions Key Financial Assumptions (real 2013 terms) Capital cost estimate (incl. contingencies) US$3.98 billion Pre-stripping and preparatory mining works US$0.48 billion Capital intensity US$185 per annual tonne FOB operating cost (ex state royalty) US$44.33/dmt (