Alara Resources Limited · ASX:AUQ
Alara Resources — Investor Presentation (March 2013)
30 slides from Alara Resources's investor presentation, Mar 18, 2013
Slide 1: ASX/Media Release: Investor Presentation
Alara Resources Limited Telephone | +61 8 9214 9787 A.B.N. 27 122 892 719 Facsimile | +61 8 9322 1515 Level 14, The Forrest Centre Web | www.alararesources.com 221 St Georges Terrace Email | info@alararesources.com Perth Western Australia 6000 ASX/MEDIA RELEASE For personal use only Monday, 18 March
Slide 2: Alara Resources Limited Investor Presentation March 2013
Alara Resources Limited For personal use only Investor Presentation March 2013 ASX: AUQ www.alararesources.com www.alararesources.com
Slide 3: Company Profile
Company Profile For personal use only Board of Directors Company Data Ian Williams AO ASX Code AUQ Chairman Market Capital (13 March 2013) $34M 40+ years of mining industry experience, including Hamersley Iron, Rio Tinto, Century Zinc and Pasminco Issued Capital Awarded Order of Australia for servic
Slide 4: Key Projects Summary
Key Projects Summary For personal use only Saudi Arabia: Khnaiguiyah Zinc-Copper Project (50%) • DFS upgraded from 1.5Mtpa to 2Mtpa throughput; completion in April 2013. • Production profile ~90,000tpa zinc and 6,250tpa copper in the first four years. • Total mine life of 14 years. • Capex estimated
Slide 5: Project Locations
Project Locations For personal use only Khnaiguiyah (50%) Washihi (75% Earn In) Zinc-Copper, Saudi Arabia Copper-Gold, Oman Khnaiguiyah & Marjan Washihi & Daris Projects Projects (Saudi Arabia) (Oman) Perth Marjan (50%) Daris (50%) Zinc-Gold-Silver, Saudi Arabia Copper-Gold, Oman © Alara Resources L
Slide 6: Saudi Arabia
Saudi Arabia For personal use only • 380km2 of licence areas, including a granted mining licence • Environmental permit granted • Land for sourcing water acquired (15kms from the proposed mine) © Alara Resources Limited www.alararesources.com 5
Slide 7: Khnaiguiyah Zinc-Copper Project
Khnaiguiyah Zinc-Copper Project For personal use only • All deposits remain open along strike and depth • Considerable upside along known and other shear zones yet to be explored • Campaign mining and processing of distinct zinc, zinc-copper and copper ‘domains’ • Standard processing - crushing, gri
Slide 8: Khnaiguiyah DFS Update
Khnaiguiyah DFS Update For personal use only DFS is nearing completion • Final DFS report expected April 2013 • Annual mine scheduling, and quarterly mine scheduling for first four years, completed • Capital cost estimate US$257M including US$32M in contingencies/other • Plant throughput increased f
Slide 9: DFS Update – Mining & Milling
DFS Update – Mining & Milling For personal use only The current plan sees mining completed in 9 years. Processing from years 10 to 14 will be from the stockpiles at 2Mtpa. Mining Total • Mined & Processed (tonnes, Years 1 to 9) 18,000,000 • Mined grade (Zn) 4.0% • Mined grade (Cu) 0.34% • Strip rati
Slide 10: DFS Update – Production & Costs
DFS Update – Production & Costs For personal use only Production Total • Mine life 14 years • Average annual production first 4 years (Zn) 90ktpa • Average annual production first 4 years (Cu) 6.25ktpa • Average annual production first 7 years (Zn) 82.5ktpa • Average annual production first 7 years
Slide 11: Expected Production Output
Expected Production Output For personal use only 140 Zn production (kt) Cu production (kt) 120 100 80 60 40 20 0 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 © Alara Resources Limited www.alararesources.com 10
Slide 12: Zinc Price Forecasts
Zinc Price Forecasts For personal use only Current Price Khnaiguiyah Targeting production of 72,000t to 120,000t zinc as concentrate © Alara Resources Limited www.alararesources.com 11
Slide 13: DFS - Capex Summary
DFS - Capex Summary For personal use only • Capex based on a contracting strategy and fixed lump sum prices • Mobile mining equipment is proposed to be leased • Tender bids have been received, reviewed and compiled into the Capex as follows: Item US$M Process facilities including design, engineering
Slide 14: Funding
Funding For personal use only • The Saudi Arabia Industrial Development Fund (SIDF) provides loans of up to 75% for industrial and mining development in Saudi Arabia • SIDF has advanced over US$25 billion since inception (1974) • SIDF advanced US$2.2B in 2011, including financing of Al Masane Copper
Slide 15: Saudi Industrial Development Fund (SIDF)
Saudi Industrial Development Fund (SIDF) For personal use only • Established by royal decree (1974) to issue soft loans for the private sector to help develop and enlarge the industrial base of the Kingdom. • Projects must be financially and technically viable – a feasibility study is required • The
Slide 16: JV Partner - Manajem (United Arabian Mining Company)
JV Partner - Manajem (United Arabian Mining Company) For personal use only • Set up in 2004 – one of the first Saudi private companies in the mining sector • Board comprises: Chairman – Engr. Mohamed Abdalah Al Hatlani (25% shareholder) CFO/Deputy Chairman – Mr. Nassir Ali Al Agel (33.3%) Dire
Slide 17: Timetable
Timetable For personal use only 2011 2012 2013 2014 May May May Aug Aug Aug Nov Nov Nov Nov Sep Sep Sep Dec Dec Dec Dec Mar Mar Mar Mar Feb Jun Feb Jun Feb Jun Feb Apr Apr Apr Apr Jan Jan Jan Jan Oct Oct Oct Oct Jul Jul Jul Finalise formal JV agreements Mining Licence granted to project* E
Slide 18: Management Team
Management Team For personal use only Shanker Madan – Managing Director 35+ years of mining industry experience, including BHP, Rio Tinto and Hamersley Iron. Justin Richard – Country Manager, Saudi Arabia 20+ years of experience, including Corporate Counsel and head of legal for UGL Limited’s resour
Slide 19: Site Layout
Site Layout For personal use only Processing Plant The processing plant Co-Disposal Facility will be located between Mineralised Zones 2 and 3. K2 Pit Accommodation K1 Pit The accommodation Low Grade camp is being Stockpile Pad designed to house up to 500 people (including families) Processing Plant
Slide 20: Conceptual Site Model
Conceptual Site Model For personal use only © Alara Resources Limited www.alararesources.com 19
Slide 21: Drill Hole Locations
Drill Hole Locations For personal use only Total drilling: 71,816m in 622 drill holes Zone 1: 8,245m in 88 drill holes (50m x 50m) Pit size 650m x 300m Zone 2: 25,839m in 245 drill holes (25m x 50m) - Pit size 1,300m x 500m Zone 3: 33,698m in 263 drill holes (12.5 - 25m x 25 - 50m) - Pit size 900 x
Slide 22: Significant exploration upside
Significant exploration upside For personal use only Zinc and copper mineralisation is focused along the carbonatised shear zones. Numerous additional shears have been identified and are yet to be drilled. Strong potential exists to significantly grow the resource base. Zone 4 is yet to be drilled o
Slide 23: Khnaiguiyah Zone – Section
Khnaiguiyah Zone 2 – Section 11 For personal use only © Alara Resources Limited www.alararesources.com 22
Slide 24: JORC Resource Statement
JORC Resource Statement For personal use only The current JORC Resources at Khnaiguiyah are: • Measured & Indicated (Domains 1 & 2) – 25.32Mt @ 4.03% Zn and 0.17% Cu • Measured & Indicated (Domain 3) – 8.53Mt @ 0.64% Cu • Inferred (Domains 1 & 2) – 4.32Mt @ 2.90% Zn and 0.03% Cu Table 1: Khnaiguiyah
Slide 25: Oman
Oman For personal use only © Alara Resources Limited www.alararesources.com 24
Slide 26: Washihi Copper-Gold Project
Washihi Copper-Gold Project For personal use only The Washihi Copper-Gold Project is located approximately 100km south-southeast of Alara’s Daris Copper-Gold Project and adjacent to a high quality bitumen road. Initial JORC Resource estimate1 (excludes the recent drilling outlined below): • 6.9Mt In
Slide 27: Conclusions
Conclusions For personal use only • Strong Team – in place and highly experienced • Supportive Government – mining licence and environmental approvals received • Long life, Low cost – 14 year mine life, strong margins • Attractive Payback – higher production and lower costs in early years • Growing
Slide 28: Pipeline Summary
Pipeline Summary For personal use only Design / Exploration Feasibility Production Construction JORC Measured and Indicated Resource Saudi Arabia: Khnaiguiyah Zinc, Copper (Alara 50%) • 25.32 million tonnes @ 4.03% Zn & 0.17% Cu; • DFS completion expected in Q1 2013. Plus: • +71,000m drilling comple
Slide 29: JORC Code Competent Person Statements
JORC Code Competent Person Statements For personal use only The information in this presentation that relates to Zinc and Copper Mineral Resources within Mineralised Zones 1, 2 and 4 in relation to the Khnaiguiyah Project (Saudi Arabia) is based on information compiled by Mr Ravindra Sharma, who is
Slide 30: Alara Resources Limited Contact and Disclaimer
Alara Resources Limited For personal use only ABN: 27 122 892 719 ASX Code: AUQ Level 14, The Forrest Centre 221 St Georges Terrace Perth, Western Australia 6000 Telephone: +61 8 9214 9787 Facsimile: +61 8 9322 1515 info@alararesources.com www.alararesources.com DISCLAIMER This presentation contains