  1. Slide 1: The New Force in Rare Earths: AGM Corporate Presentation

    Slide 1: The New Force in Rare Earths: AGM Corporate Presentation

    For personal use only The New Force in Rare Earths AGM Corporate Presentation Building a globally significant, vertically integrated, mine-to-oxide rare earths business 23 November 2026 Lindian Resources Limited ASX: LIN | www.lindianresources.com.au | ACN 090 772 222

  2. Slide 2: Important Information

    Slide 2: Important Information

    Important Information Disclaimer Competent Persons’ Statement For personal use only This presentation includes indicative timetables (including first production at Kangankunde, first SARECO processing and the Stage 2 FID), The information in this presentation that relates to Exploration Results, Met

  3. Slide 3: Board & Leadership

    Slide 3: Board & Leadership

    Board & Leadership Experienced team delivering the mine-to-oxide strategy For personal use only BOARD OF DIRECTORS Robert Martin Zac Komur Teck Lim Anastasia Gotjamanos Executive Chairman Executive Director Non-Executive Director Group General Counsel & Company Secretary MANAGEMENT Rajesh Agrawal Ha

  4. Slide 4: Rare Earths Peer Landscape

    Slide 4: Rare Earths Peer Landscape

    Rare Earths Peer Landscape Kangankunde: one of few rare earths projects entering production in 2026 For personal use only Market Cap represented by bubble sizes1 Exploration / Scoping PFS / PEA DFS / 2027+ Production FID / 2026 Production Production Meteoric Resources NL Market Cap: A$9.94bn St Geor

  5. Slide 5: From Strategy to Execution

    Slide 5: From Strategy to Execution

    From Strategy to Execution Building a Western-aligned, mine-to-oxide rare earths business For personal use only One world-class deposit. One operating processing plant. A multi-decade supply chain into global markets. MINE in MALAWI SARECO, Kazakhstan ~120,000tpa Fully permitted pathway from 20,000t

  6. Slide 6: Delivered Milestones, Near-Term Catalysts

    Slide 6: Delivered Milestones, Near-Term Catalysts

    Delivered Milestones, Near-Term Catalysts A track record of delivery, with first production, first shipment and Stage 2 decisions next For personal use only DELIVERED UPCOMING CATALYSTS Aug 2025 Apr 2026 Nov 2026 Dec 2026 Jan 2027 Stage 1 FID approved; Feb 2026 A$100m institutional Aug 2026 30,000dm

  7. Slide 7: Lindian's Progress Since the Last AGM

    Slide 7: Lindian's Progress Since the Last AGM

    Lindian’s Progress Since the Last AGM 1 10 November 2025 to 23 November 2026: from funded developer to vertically integrated producer For personal use only A Year of Significant Progress: Building an Integrated Rare Earths Business Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 AGM 10 Nov 2025 AGM 23 Nov 2

  8. Slide 8: Then vs Now: Twelve Months of Transformation

    Slide 8: Then vs Now: Twelve Months of Transformation

    Then vs Now: Twelve Months of Transformation Lindian at the 2025 AGM compared with Lindian today For personal use only Same site, twelve months apart Security gate Nov 2025 Security gate today Motor control centres Regrind mill THEN 2025 AGM, 10 November 2025 NOW November 2026 Kangankunde Stage 1 67

  9. Slide 9: Strategic Partnerships: Iluka and Carester

    Slide 9: Strategic Partnerships: Iluka and Carester

    Strategic Partnerships: Iluka and Carester 1 Long-term offtake into government-backed refineries in Australia and France For personal use only • 15 + 15 year strategic offtake: 6,000 tonnes per annum of Stage 1 monazite concentrate • 10 + 5 + 5 year binding offtake for a minimum 70% of SARECO’s heav

  10. Slide 10: Current Project Snapshot

    Slide 10: Current Project Snapshot

    Current Project Snapshot Kangankunde mine and SARECO MREC plant: first production December 2026 For personal use only KANGANKUNDE - MALAWI SARECO - KAZAKHSTAN Mine & concentrator | First production Dec 2026; first Nacala shipment Jan 2027 Cracking & leaching plant | First production Dec 2026; 100% o

  11. Slide 11: Kangankunde: A Tier NdPr Resource

    Slide 11: Kangankunde: A Tier NdPr Resource

    Kangankunde: A Tier 1 NdPr Resource Largest contained NdPr among selected global rare earth projects For personal use only USES OF RARE EARTH ELEMENTS MINERAL RESOURCE NDPR CONTAINED (KT)1 LANTHANIDE SERIES (PERIODIC TABLE) Kangankunde; 0.43% NdPr 1,132 OTHER2 LIGHT RARE EARTHS (LREE) HEAVY RARE EAR

  12. Slide 12: Kangankunde: Infrastructure-Ready Location

    Slide 12: Kangankunde: Infrastructure-Ready Location

    Kangankunde: Infrastructure-Ready Location Established power, water and transport links support low-cost production For personal use only Outcropping, high-grade orebody One of the largest high-grade rare earth deposits in the world, with relatively uniform mineralisation1 Very low strip ratio 0.2:1

  13. Slide 13: Immediate Downstream Margin Through SARECO

    Slide 13: Immediate Downstream Margin Through SARECO

    Immediate Downstream Margin Through SARECO The only operating commercial-scale MREC plant outside China, MP Materials, Serra Verde and Lynas For personal use only No greenfield build Acquired for US$20m (100% basis) vs >A$500m for a comparable greenfield CLP; avoids multi-year permitting1 Higher pay

  14. Slide 14: Progress in Pictures

    Slide 14: Progress in Pictures

    Progress in Pictures Significant progress across Malawi and Kazakhstan as both projects advance towards production For personal use only Kangankunde - Malawi SARECO - Kazakhstan

  15. Slide 15: The New Force in Rare Earths

    Slide 15: The New Force in Rare Earths

    For personal use only The New Force in Rare Earths Lindian Resources Limited ABN 53 090 772 222 Level 15, 240 St Georges Terrace Perth WA 6000 Australia T: +61 8 6401 4300 E: info@lindianresources.com.au www.lindianresources.com.au

  16. Slide 16: Kangankunde: Resources & Reserves

    Slide 16: Kangankunde: Resources & Reserves

    Kangankunde: Resources & Reserves Mineral Resource Inclusive of Reserves @ 0.5% TREO Cut-off Grade Competent Persons’ Statement For personal use only The information in this presentation that relates to Exploration Results, Metallurgy Results, and Mineral Resource Classification Tonnes TREO NdPr% of

  17. Slide 17: Appendix A: Source Data – Mineral Resources

    Slide 17: Appendix A: Source Data – Mineral Resources

    Appendix A: Source Data – Mineral Resources 1 For personal use only Company Information Mineral Resources (Measured) Mineral Resources (Indicated) Mineral Resources (Inferred) Mineral Resources (Total) Source Project Contained Contained Contained Contained Contained Contained Contained Contained Com

Source: ASX announcement, Nov 23, 2026