Tharisa — The Oxford Platinum Lectures 2026

12 slides from Tharisa's conference presentation, May 15, 2026

  1. Slide 1: The Oxford Platinum Lectures 2026

    THE OXFORD PLATINUM LECTURES 2026 15 May 2026 Phoevos Pouroulis

  2. Slide 2: Video slide

    VIDEO SLIDE Ya KARO platinum

  3. Slide 3: Multigenerational mine under construction

    MULTIGENERATIONAL MINE UNDER CONSTRUCTION Highlights • 10+ year open-pit mine life, scalable to over 50 years with underground • Output of 226koz pa (OP) increasing to +360koz pa (UG) • Copper, nickel and cobalt by-products • 1 200 new direct jobs • US$241m investment to date 3

  4. Slide 4: Locality

    LOCALITY Ru Ir Rh 4% 2% o Safety 4% Hartley Platinu Zimplats • 2025 LTIFR: 0.00 Au m 641 kozpa 8% Pt Karo Ngezi 42% Platinum o Mineral Resource and Mineral Reserve US$2 417/oz Mine Unki Mine • Open pit resource: 11.2 Moz 6E PGM 11 May 2026 244 kozpa • Open pit reserve: 2.1 Moz 6E PGM Mimos a Mine •

  5. Slide 5: Mining right over 903ha

    MINING RIGHT OVER 23 903HA Solar plant Chirundazi Dam Camp 132kV Powerline TSF Karo Substation Mine Pit KPE SE Concentrator Chingazi Dam Mining Contractor 5

  6. Slide 6: Project derisked

    PROJECT DERISKED o Exploration • 60km of exploration drilling; high level of confidence; • Underground drilling of 26km completed, +50-year potential • Current CPR April 2026 o Mining • Mine design completed • EPSA appointed; mobilisation on track with open pit waste stripping underway o Processing

  7. Slide 7: Concentrator: major construction complete

    CONCENTRATOR: MAJOR CONSTRUCTION COMPLETE o Mill Building • Steel work 78% complete • Mills delivered; 90% of long lead equipment procured and in storage o MV/LV Buildings • MV building 37% complete • LV building (wet end) 100% complete 7

  8. Slide 8: Civil works

    CIVIL WORKS o Chirundazi Dam • 27% complete — forecast completion October 2026 • Bulk water secured for plant operations o Chiganzi Dam • Secondary water source supporting overall water strategy 8

  9. Slide 9: Power: substation and 132 kV line

    POWER: SUBSTATION AND 132 KV LINE o 132kv overhead line • 78% complete • 102 of 130 poles installed o Plant substation • Bulk power secured for operations • Karo substation integrated with grid connection 9

  10. Slide 10: Global PGM cost curve — December 2025

    GLOBAL PGM COST CURVE — DECEMBER 2025​ All-in Sustaining Cost (R/oz 6E) by producer | Tharisa & Karo anchor the lowest-cost quartile Tharisa is positioned in the lowest-cost quartile of global PGM production. Tharisa ~R11,000/oz AISC, net of chromite credits Karo (estimate, full production) ~R14,000

  11. Slide 11: Unlocking world class value

    UNLOCKING WORLD CLASS VALUE • Tier-1 asset, multi generational • De-risked, near-term production • Exceptional returns & low cost​ • NPV10.9% US$1.44bn (Spot OP&UG) • Strong ESG commitment​ and partnerships • Strategic location & market Impact​ replacing depleting reserves • US$241m investment to da

  12. Slide 12: Questions?

    QUESTIONS? 12