  1. Slide 1: Developing Canada's Premier Copper-Gold Mine

    TSX WRN NYSE AMERICAN WRN DEVELOPING CANADA’S PREMIER COPPER-GOLD MINE Corporate Presentation July 2023

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS The information provided in this presentation is not intended to be a comprehensive review of all relating to interpretation of drill results and the geological continuity and grade of mineral matters and developments concerning Western Copper and Gold Corporation and its

  3. Slide 3: Corporate Overview

    CORPORATE OVERVIEW TRADING Toronto Stock Exchange, TOP WRN Rio Tinto Canada 7.8% NYSE American SHAREHOLDERS May 31, 2023 Cash & Short-Term Fidelity Management & Research CASH 6.2% Investments C$43.2 M Co. LLC POSITION Mar 31, 2023 + Strategic Investments* (*pro-forma) Mitsubishi Materials 5.0% Short

  4. Slide 4: WRN & Casino Copper-Gold Project

    WRN & CASINO COPPER-GOLD PROJECT CLEAR INVESTMENT THESIS • One of the largest copper-gold projects in Canada • Located in the Yukon – emerging mining district • New Feasibility Study shows robust economics and long life • Strong copper market CONTINUING TO ADD VALUE • Significant resource expansion

  5. Slide 5: Strategic Investments

    STRATEGIC INVESTMENTS C$25.6M C$21.3M RIO TINTO OWNERSHIP MITSUBISHI OWNERSHIP ~ 8.0%* ~ 5.0% OF WESTERN’S OF WESTERN’S OUTSTANDING OUTSTANDING COMMON SHARES Rio Tinto invested May 2021 Mitsubishi invested March 2023 COMMON SHARES RIO TINTO KEY RIGHTS* MITSUBISHI KEY RIGHTS* Rio has the right to app

  6. Slide 6: Working with Strategic Partners

    WORKING WITH STRATEGIC PARTNERS  Drilling and Exploration program complete • Advanced Metallurgical program  Metallurgical program complete • Drilling program  Tailings facility review complete • Engineering review  Feasibility Study review complete • Project Execution plan  Permitting review c

  7. Slide 7: Copper Key to Limiting Climate Change

    THE WORLD NEEDS A LOT MORE COPPER • To keep global warming under 1.5 degrees, annual COPPER copper supply needs to grow by more than 12 Mt in 12 million tonnes the next 10 years – growth only 7 Mt in the past 20 years copper equal to KEY TO LIMITING • There are limited copper projects under developm

  8. Slide 8: Canada's Critical Minerals Strategy

    CANADA’S CRITICAL MINERALS STRATEGY Over the LOM, Casino is expected to produce 4.27 billion lbs of POWERING THE GREEN AND copper, which equals: DIGITAL ECONOMY FOR • 5 million fully electric buses or 23 million electric CANADA AND THE WORLD battery vehicles • Solar power systems contain ~11,000 lbs

  9. Slide 9: An Attractive Copper/Gold Mine

    CASINO COPPER-GOLD AN ATTRACTIVE COPPER/GOLD MINE Contained 46% 34% Metal Value Distribution COPPER GOLD in the M&I Mill Resource COPPER GOLD 7.6 Billion lbs 14.8 Million oz M+I Resources M+I Resources +3.1 Billion lbs +6.3 Million oz Inferred Resources Inferred Resources 4% 17% SILVER MOLY Source:

  10. Slide 10: 5th Largest Undeveloped Copper-Gold Project Controlled by a Junior

    5th LARGEST UNDEVELOPED COPPER-GOLD PROJECT CONTROLLED BY A JUNIOR Alaska 80 Junior controlled copper project BC 150 97 Major controlled copper project 70 WRN’s Casino Copper-Gold project COPPER EQUIVALENT (B LBS) 60 CASINO 50 COPPER-GOLD PROJECT Ecuador Argentina 40 x Yukon 30 Minnesota Nevada Arge

  11. Slide 11: 8th Largest Gold Project Controlled by a Junior

    8th LARGEST GOLD PROJECT CONTROLLED BY A JUNIOR 70 107 106 Junior controlled project 60 WRN’s Casino Copper-Gold project CASINO CONTAINED GOLD (M oz) 50 COPPER-GOLD PROJECT 40 30 x 20 10 0 Source: S&P TSX | NYSE AMERICAN | WRN 11

  12. Slide 12: Casino Copper-Gold Project

    CASINO COPPER-GOLD PROJECT TSX | NYSE AMERICAN | WRN

  13. Slide 13: Casino Copper-Gold Deposit

    CASINO COPPER-GOLD DEPOSIT HEAP LEACH RESERVE 209.6 Million Tonnes @ 0.28 g/t AuEq (P&P) Core Zone CuEq Final Pit Outline 1.0 0.8 0.6 0.4 0.3 0.2 0.1 MILL RESERVE 1.22 Billion Tonnes @ 0.40% CuEq (P&P) Notes: Looking North, North longitudinal section +6958634.51. Based on Casino Copper-Gold 2022 Fea

  14. Slide 14: Core Zone Grades Confirmed by Drilling

    CORE ZONE GRADES CONFIRMED BY DRILLING Results confirmed or, in some cases, improved upon historical drilling Casino Copper-Gold Core Zone 800 m X 500 m zone in the centre of the deposit DDH21-07 Primarily breccia geology DDH21-09 289.6 m 1.01% CuEq from 36.6 m 65.8 m 2.53% CuEq Grades significantly

  15. Slide 15: Grades in Line with Peers

    CASINO COPPER-GOLD PROJECT GRADES IN LINE WITH PEERS Casino Mill Yr 1-4 (174 Mt) CASINO COPPER-GOLD Casino Mill LOM (1.22 Bt) PROJECT Operating Mine Average Copper Mountain - CMMC (702 Mt) Gibraltar - TKO (706 Mt) Highland Valley - TCK (1.21 Bt) PEERS Developing Mine Average Mt. Milligan - CG (150 M

  16. Slide 16: Feasibility Study Summary

    CASINO COPPER-GOLD PROJECT FEASIBILITY STUDY SUMMARY $2.33 Billion 18.1% 0.43:1 3 years NPV IRR STRIP RATIO PAYBACK AFTER-TAX (8%) AFTER-TAX LOM 27 years $10 Billion MINE LIFE – Mill operation LOM CASH FLOW AFTER-TAX Metal Prices Cu US$3.60/lb Au US$1,700/oz Ag US$22/oz Mo US$14/lb Note: Based on Ca

  17. Slide 17: Economic Throughout the Commodity Cycle

    CASINO COPPER-GOLD PROJECT ECONOMIC THROUGHOUT THE COMMODITY CYCLE ECONOMICS BASE CASE SPOT* Copper (US$/lb) 3.60 3.75 Gold (US$/oz) 1,700 1,925 Molybdenum (US$/lb) 14.00 24.00 Silver (US$/oz) 22.00 23.00 Foreign Exchange (US$:C$) 0.80 0.75 NPV @ 8% (after-tax) (C$ M) 2,334 4,470 IRR (100% equity) (

  18. Slide 18: Significant Contribution from Early Years

    CASINO COPPER-GOLD PROJECT SIGNIFICANT CONTRIBUTION FROM EARLY YEARS YEARS LIFE OF 1-4 MINE AVERAGE Cash Flow (Pre-tax) (C$ M) 1,033 662 ANNUAL CASH FLOW & Cash Flow (After-tax) (C$ M) 951 517 COSTS Net Smelter Return ($/t ore milled) 43.15 29.08 Operating Cost ($/t ore milled) 11.16 AVERAGE Copper

  19. Slide 19: Feasibility Study Operating Cash Costs

    CASINO COPPER-GOLD PROJECT FEASIBILITY STUDY OPERATING CASH COSTS BASE CASE BY- Copper Cash Cost PRODUCT (0.80) Net of By-Products (US$/lb) COSTS CO- Copper Cash Cost 1.54 PRODUCT Co-Product (US$/lb) COSTS Gold Cash Cost 799 Co-Product (US$/oz) Note: Based on Casino Copper-Gold 2022 Feasibility Stud

  20. Slide 20: Feasibility Study Capital Costs

    CASINO COPPER-GOLD PROJECT FEASIBILITY STUDY CAPITAL COSTS PROJECTED CAPITAL COSTS C$ Millions PROCESS PLANT & Project Directs (including freight) $2,116 INFRASTRUCTURE Project Indirects $431 Contingency $369 Subtotal Process Plant $2,916 and Infrastructure MINE COSTS Mine Equipment $433 Mine Prepro

  21. Slide 21: ESG Commitment

    ESG COMMITMENT SOCIAL ENVIRONMENTAL GOVERNANCE Committed to health and safety Committed to exceeding best Committed to high ethical and committed to the protection practices in protecting the standards and building of cultural values environment long term value • Ongoing Engagement with Local • Acce

  22. Slide 22: Working with the Community

    WORKING WITH THE COMMUNITY • Closure by rock/sand cover limiting Tailings Facility Redesign the need for tailings “pond” Reduced Risk, Reduced • Several other changes to the design Environmental Impact and to reduce construction risk Improved Safety • Redesign incorporates the outcomes of the BATT s

  23. Slide 23: Access Road Funding Secured

    CASINO COPPER-GOLD PROJECT ACCESS ROAD FUNDING SECURED Committed from C$130 Million Governments for the Casino Funding Copper-Gold Access Road Construction started early 2022 Agreements reached with First Nations on key aspects of remaining road Canadian Prime Minister Justin Trudeau and Former Yuko

  24. Slide 24: Developments on Power

    DEVELOPMENTS ON POWER Connecting Yukon’s Power Grid Supporting Canada’s future Green .. Economy • Casino Base Case is to use an LNG power plant • Discussions initiated in January with Yukon, BC and Federal governments to connect the BC and Yukon power grids • Included in Yukon Minister Streicker’s m

  25. Slide 25: Casino Permitting Timeline

    CASINO PERMITTING TIMELINE TASK YEAR 1 YEAR 2 YEAR 3 YEAR 4 YESAB Process Establish Panel Technical Analysis Potential Public Hearings Construction Start Panel Report Decision Land use Preparation Permit for Casino Road Obtain Permits Type A Water Preparation Use License Water Board Process Quartz M

  26. Slide 26: Key Asset in an Emerging New District

    KEY ASSET IN AN EMERGING NEW DISTRICT Major miners in area – Rio Tinto, Newmont, Agnico-Eagle, Kinross, and others ~ 30 million ounces of gold in district* Significant exploration upside Government commitment to fund access to area Coffee project recently completed Environmental Assessment Community

  27. Slide 27: Enterprise Value/Project NPV Benchmarking

    ENTERPRISE VALUE/PROJECT NPV (STUDY) BENCHMARKING (x) WRN trades at 0.16x NPV, a discount to its peers WESTERN 1.82x COPPER & GOLD 1.41x 0.49x 0.30x 0.21x 0.16x 0.09x 0.09x 0.08x 0.07x 0.03x 0.03x 0.03x 0.02x (Filo del Sol ) Northern Dynasty Trilogy Metals (Cascabel) Highland Copper (North Island) S

  28. Slide 28: Enterprise Value/Copper Equivalent Resource Benchmarking

    ENTERPRISE VALUE/COPPER EQUIVALENT RESOURCE BENCHMARKING (US¢/lb CuEq) WRN is undervalued with greater growth opportunity compared to its peers WESTERN COPPER & GOLD ¢28.6 ¢12.5 ¢11.8 ¢1.9 ¢1.6 ¢1.4 ¢1.2 ¢0.8 ¢0.4 ¢0.4 ¢0.2 ¢0.2 ¢0.1 ¢0.1 (Filo del Sol ) Northern Dynasty Trilogy Metals (Cascabel) Hi

  29. Slide 29: Path Forward and Investment Highlights

    PATH FORWARD AND INVESTMENT HIGHLIGHTS Casino Copper and Gold Significant Yukon – Clear path to Project already ticks copper and an emerging unlock value many of the boxes gold project mining district Continuing partnership Submit Upcoming with strategic investors EA proposal Catalysts in evaluation

  30. Slide 30: Analyst Coverage

    ANALYST COVERAGE CORMARK SECURITIES H.C. WAINWRIGHT & CO. AGENTIS CAPITAL Stefan Ioannou Heiko F. Ihle, CFA Michael Gray, MSc 416 943 4222 212 356 0500 778 952 0978 TSX | NYSE AMERICAN | WRN 30

  31. Slide 31: Appendix

    APPENDIX TSX | NYSE AMERICAN | WRN

  32. Slide 32: Key Management Team with Successful Track Record

    KEY MANAGEMENT TEAM WITH SUCCESSFUL TRACK RECORD Former investment Metallurgical Engineer with 30 years leadership and banker with a focus significant management development experience on capital markets and metallurgical overseeing the de-risking and mergers experience in increasingly and advanceme

  33. Slide 33: Board of Directors

    BOARD OF DIRECTORS Ken Williamson, Former investment banker. Mr. Williamson has served on B.A.Sc., MBA, P.Eng the boards of Eicon Technology Corporation, Glamis Gold Director & Interim Chairman Ltd., BioteQ Environmental Technologies Inc., Uranium One Inc., BlackRock Ventures Inc., Quadra FNX Mining

  34. Slide 34: Significant Positive Economic Impact on the Yukon

    SIGNIFICANT POSITIVE ECONOMIC IMPACT ON THE YUKON Economic Impact of the development of Casino Copper- Gold on the Yukon and Canada Over the Life of the Project, Casino is estimated to Each year Casino is estimated to • Contribute $44.3 billion to Canada’s GDP • Contribute $1.3 billion to Yukon’s ec

  35. Slide 35: Share vs Copper Price Performance

    SHARE VS COPPER PRICE PERFORMANCE WRN trades inline, in some cases outperforms, the copper price Copper WRN May 17, 2021 Nov 23, 2022 Mar 24, 2023 Apr 11, 2023 U$5.50 C$3.50 Rio Tinto C$25.6M Rio Tinto Mitsubishi Materials Rio Tinto Exercise Strategic Investment Extends Rights C$21.3M Participation

  36. Slide 36: Economic Throughout the Commodity Cycle

    CASINO COPPER-GOLD PROJECT ECONOMIC THROUGHOUT THE COMMODITY CYCLE COPPER PRICE ($US) $3.00 $3.50 $3.60 $4.00 $4.50 $5.00 $5.50 NPV 8% (C$M) $866 $1,437 $1,551 $2,006 $2,571 $3,136 $3,701 $1,300 IRR % 12.1% 14.5% 14.9% 16.7% 18.7% 20.7% 22.5% Payback (yrs) 5.0 4.1 4.0 3.6 3.2 2.9 2.7 NPV 8% (C$M) $1

  37. Slide 37: History

    HISTORY 1917: First known record of mineral claim 1930’s: Discovery of silver-lead veins 1965-1980: 370 tonnes of hand-cobbed lead/silver ore sent to Trail, BC 1967: ID of Cu porphyry potential Brameda, Quintana & Teck diamond drill 12,300 m +RC drill 5,200 m 1991: Archer, Cathro and Associates diam

  38. Slide 38: Project Team

    CASINO COPPER-GOLD PROJECT PROJECT TEAM Engineering Lead: M3 Engineering & Development • Geotechnical: Knight Piésold • Mining: Independent Mining Consultants, Inc. • Metallurgical: ALS Metallurgical, International Metallurgical & Environmental, Arcadis (Chile) • Access road: Associated Engineering

  39. Slide 39: Excellent Location

    CASINO COPPER-GOLD PROJECT EXCELLENT LOCATION Yukon, Canada – Low political risk Population 40,000 Casino project is located 380 km from Whitehorse, Yukon 560 km from year-round port at Skagway, Alaska Mine and mill are in Selkirk First Nation Traditional Territory – same territory as the Minto mine

  40. Slide 40: Property Geology

    CASINO COPPER-GOLD PROJECT PROPERTY GEOLOGY Note: High grade zone dips off section. East-west longitudinal section 6958400 N. Based on Casino Copper-Gold 2022 FS. See “Notes” in Appendix. TSX | NYSE AMERICAN | WRN 40

  41. Slide 41: Mining

    CASINO COPPER-GOLD PROJECT MINING Pit designs for five mining phases were developed to produce 45.4 M tonnes per year of mill feed ore Mill material is limited to approximately 1.2 billion tonnes due to TMF capacity The pits were designed with 40 m wide ramps, 20 m benches. 45 degree overall pit slo

  42. Slide 42: Processing

    CASINO COPPER-GOLD PROJECT PROCESSING Milling • Throughput: average LOM 120,000 tonnes per day • Grinding Circuit: 40 ft SAG Mill (29 MW) + 2 x 28 ft Ball Mills (22 MW each) • Medium – soft ore: BWi – 14.5 kWh/t, 200 µm primary grind Flotation • Conventional copper/moly circuit • Recoveries: Copper

  43. Slide 43: Excellent Concentrate Quality

    CASINO COPPER-GOLD PROJECT EXCELLENT CONCENTRATE QUALITY ELEMENT AVG VALUE UNIT ELEMENT AVG VALUE UNIT Copper 28 % Molybdenum 57.4 % Gold 25 g/t MOLYBDENUM CONCENTRATE Copper 0.39 % Silver 120 COPPER CONCENTRATE g/t Rhenium 133.5 g/t Molybdenum 0.05 % Iron 0.8 % Iron 26 % Sulphur 37.9 % Sulphur 36 %

  44. Slide 44: Infrastructure Roads

    CASINO COPPER-GOLD PROJECT INFASTRUCTURE ROADS Straight-Forward Road Access All roads are well maintained and used year-round • 380 km from Whitehorse • 560 km from Skagway, Alaska (concentrate load-out facility) - 358 km – existing major highway - 70 km – existing road to be upgraded by Yukon Gover

  45. Slide 45: Infrastructure Power & Port

    CASINO COPPER-GOLD PROJECT INFRASTRUCTURE POWER & PORT Power • Power to be supplied by 3 gas turbine generators & 1 steam turbine generator for a combined installed capacity of > 200 MW • Fuel – LNG trucked from Ft. Nelson • MOU signed with Ferus Natural Gas Fuels Inc. to supply LNG • City of Whiteh

  46. Slide 46: Feasibility Study Operating Cost

    CASINO COPPER-GOLD PROJECT FEASIBILITY STUDY OPERATING COST LOM (C$/TONNE) MILLING Milling $6.42 OPERATION Mining $4.28 General & Administrative $0.46 Total $11.16 HEAP LEACH Heap Leach Operation $1.93 OPERATION ADR/SART $4.80 Total $6.73 Note: Based on Casino Copper-Gold 2022 FS at base case metal

  47. Slide 47: Comparable Opex

    CASINO COPPER-GOLD PROJECT COMPARABLE OPEX Mill Throughput Casino Copper-Gold (FS) 120,000 tpd Copper Mountain (2020) 45,000 tpd Copper Mountain (2021) Mount Milligan (2020) 60,000 tpd Mount Milligan (2021) Gibraltar (2020) 85,000 tpd Gibraltar (2021) Highland Valley (2020) 155,000 tpd Highland Vall

  48. Slide 48: Comparable Capex

    Unit Capex (US$/t CuEq/y) $0 $10,000 $15,000 $20,000 $25,000 $30,000 $35,000 $40,000 $5,000 Florence Copper ($0.2 B) Los Helados ($1.2 B) Agua Rica ($2.2 B) Carrapateena ($0.7 B) Mantoverde ($0.8 B) Pumpkin Hollow ($1.1 B) CASINO COPPER-GOLD PROJECT Josemaria ($2 B) Resolution ($6 B) Ann Mason ($1.4

  49. Slide 49: Appendix

    CASINO COPPER-GOLD PROJECT ANA AND CASINO B Note: See “Notes” in Appendix TSX | NYSE AMERICAN | WRN 49

  50. Slide 50: 2022 Casino Copper-Gold Resource

    2022 CASINO COPPER-GOLD RESOURCE MILL RESOURCE ($6.11/t NSR CUTOFF) NSR Copper Gold Moly Silver CuEq Copper Gold Moly Silver Class Mt (C$/t) (%) (g/t) (%) (g/t) (%) (M lb) (M oz) (M lb) (M oz) Measured 144.9 40.09 0.30 0.38 0.024 2.1 0.64 953 1.8 75.2 9.6 Indicated 2,114.2 20.34 0.14 0.16 0.015 1.4

  51. Slide 51: 2022 Casino Copper-Gold Resource

    2022 CASINO COPPER-GOLD RESOURCE TOTAL RESOURCE (MILL + HEAP LEACH) NSR Copper Gold Silver Copper Gold Silver Class Mt (C$/t) (%) (g/t) (g/t) (M lb) (M oz) (M oz) Measured 188.2 36.34 0.24 0.40 2.2 1,005.0 2.4 13.3 Indicated 2,302.6 19.61 0.13 0.17 1.4 6,638.1 12.4 103.9 M+I 2,490.7 20.88 0.14 0.18

  52. Slide 52: 2022 Casino Copper-Gold Reserve

    2022 CASINO COPPER-GOLD RESERVE MILL RESERVE NSR Copper Gold Moly Silver CuEq Copper Gold Moly Silver Class Mt (C$/t) (%) (g/t) (%) (g/t) (%) (M lb) (M oz) (M lb) (M oz) Proven 140.1 38.50 0.31 0.39 0.024 2.1 0.67 944 1.8 74.9 9.4 Probable 1,076.9 23.68 0.17 0.19 0.021 1.6 0.36 4,135 6.7 497.1 55.5

  53. Slide 53: Notes

    NOTES “Casino Copper-Gold Feasibility Study” • NSR value for hypogene sulphide mill material is: Technical report entitled “Casino Copper-Gold Project, Form 43-101 F1 - NSR (C$/t) = $73.81 x copper (%) + $41.16 x gold (g/t) + $213.78 x moly (%) + Technical Report Feasibility Study” dated June 13, 20

  54. Slide 54: Notes

    NOTES “Casino Copper-Gold Feasibility Study” • NSR value for leach material is Mineral Reserve - NSR (C$/t) = $14.05 x copper (%) + $47.44 x gold (g/t) + $0.210 x silver (g/t), based on recoveries of 18% copper, 80% gold and 26% silver. • The Mineral Reserve estimate has an effective date of June 13