Transurban Group Ltd. · ASX:TCL

Transurban — H1 FY2018 Earnings Presentation

75 slides from Transurban's earnings presentation, Feb 13, 2018

  1. Slide 1: ASX release: Investor Presentation

    asx release 13 February 2018 For personal use only Investor Presentation Please find attached the Investor Presentation that will be given to analysts this morning. Amanda Street Company Secretary Investor enquiries Media enquiries Jessica O’Brien Tim Salathiel General Manager Investor Relations and

  2. Slide 2: Results for six months ended 31 December 2017

    Results for six For personal use only months ended 31 December 2017 13 February 2018

  3. Slide 3: For personal use only

    For personal use only This publication is prepared by the Transurban Group comprising Transurban Holdings Limited (ACN 098 143 429), Transurban Holding Trust (ARSN 098 807 419) and Transurban International Limited (ACN 121 746 825). The responsible entity of Transurban Holding Trust is Transurban In

  4. Slide 4: Results highlights

    For personal use only • FY18 distribution guidance of 56.0 cps; growth of 8.7% over FY17 TOLL REVENUE EBITDA • Average traffic growth of 1.4% impacted by disruption from CTW, M2, GROWTH GROWTH LEP and GUN works • Continued focus on customer experience: – LinktGO GPS app launch – GLIDe back-office sy

  5. Slide 5: Strategy and core capabilities

    For personal use only To be the partner of choice with governments, providing effective and innovative urban road infrastructure and services utilising core capabilities Network Community Development Technology Operations Customer planning / engagement / delivery experience forecasting TRANSURBAN 1H

  6. Slide 6: Network and toll revenue contribution by region

    Network and toll Greater Sydney 40.5% Melbourne 33% Brisbane For personal use only 17% 9.5% revenue contribution Washington Area Toll revenue growth1 9.8% 14.2% 3.5% 17.9%2 EBITDA growth1 10.3% 17.5% 3.6% 19.9%2 ADT growth 2.9% (1.0)% 3.5% 3.4% Capital invested or $2.3 billion $5.1 billion $5.8 bill

  7. Slide 7: Committed projects and capital contribution

    For personal use only FY18 FY19 FY20 FY21 FY22 COMMITTED CITYLINK TULLA WIDENING Melbourne ($1.0 billion) – Complete4 PROJECTS/ PROJECTS WEBB DOCK ACCESS5 Melbourne – Complete UNDER CONSTRUCTION2 INNER CITY BYPASS Brisbane ($37.5 million) MONASH FREEWAY UPGRADE5 Melbourne LOGAN ENHANCEMENT PROJECT B

  8. Slide 8: Potential future projects timeline

    For personal use only FY18-19 FY20-22 FY23-25 FY26-28 FY29+ WESTCONNEX1 STAGE 1A Sydney – Complete STAGE 1B Sydney STAGE 2 Sydney STAGE 3A Sydney STAGE 3B Sydney POTENTIAL CENTENARY/WESTERN MOTORWAY WIDENING2 Brisbane NETWORK ENHANCEMENTS3 LOGAN MOTORWAY WIDENING2 Brisbane GATEWAY MOTORWAY WIDENING2

  9. Slide 9: Network potential in North America's most congested cities

    For personal use only NETWORK POTENTIAL IN NORTH AMERICA’S MOST CONGESTED CITIES1 50% GOVERNMENT SUPPORTIVE EXPERIENCE DEMOGRAPHICS IN PPP Los Angeles 40% Vancouver San Francisco Seattle Miami Toronto Congestion level 30% Montreal Austin TIME SAVINGS Boston NETWORK GWA (Washington D.C., VALUE TO 20%

  10. Slide 10: Transurban USA asset vs competitor forecast

    For personal use only NEW AUSTRALIAN TOLL ROAD ASSETS TRANSURBAN USA ASSET VS RECENT COMPETITOR FORECAST FOR COMPLETED SINCE 2010 COMPARABLE USA ROAD PROJECT Under competitor forecast, if accurate, drivers would experience Third-party toll prices almost 5 times higher than Revenue forecast on the co

  11. Slide 11: CityLink Tulla Widening lanes opened

    $1.3 billion1 CTW lanes opened three months ahead of schedule For personal use only Once completed, the project will deliver 15 to 20 minute travel time savings in each direction Significant travel speed and time savings already observed: – Almost 60% increase in average travel speed2 – Almost 40% d

  12. Slide 12: Construction commenced on West Gate Tunnel Project

    Construction commenced on WGTP 1 For personal use only Significant benefits for Victoria CityLink – First new major motorway project in Melbourne to commence construction since 2010 Improved access to the Port of Melbourne – Enables government to reallocate >$4 billion to other much needed infrastru

  13. Slide 13: Queensland customer experience investment

    $70 million capital expenditure in Queensland over four years, significantly For personal use only improving customer experience Tolling GLIDe back-office system roll out Billing and call centre • Upgrade of tolling system and • GLIDe back-office system creates greater flexibility for customers • Su

  14. Slide 14: Social investment in our communities

    For personal use only Social investment in our communities Transurban recognises the important role community organisations play in the wellbeing of neighbourhoods. Community grants are offered to support organisations who can have a positive impact in the communities where we operate • Heathwood Co

  15. Slide 15: Independent recognition of sustainability approach

    Independent recognition of Transurban’s approach to sustainability For personal use only • Dow Jones Sustainability Index: – Second-highest-rated company in the Transport and Transportation Infrastructure category, scoring in the 98th percentile • Global Real Estate Sustainability Infrastructure Ben

  16. Slide 16: Road safety and emerging technologies

    For personal use only Understanding the future of road safety and emerging technologies helps inform Transurban’s initiatives • Commissioned Monash University Accident Research Centre to analyse crashes on Transurban's Australian roads and compare performance to identified like roads The report foun

  17. Slide 17: Financial results

    For personal use only results Financial

  18. Slide 18: Statutory results and key drivers

    For personal use only 1H17 ($M) 1H18 ($M) KEY DRIVERS Toll revenue 1,032 1,131 Toll revenue • $99 million increase driven by traffic growth and toll price escalation EBITDA 769 850 across the Australian and GWA assets Net profit 88 331 EBITDA Interim distribution of 28.0 cps, 1H18 distribution inclu

  19. Slide 19: Proportional results

    For personal use only 1H17 ($M) 1H18 ($M) % CHANGE KEY DRIVERS Toll revenue 1,065 1,176 10.5% Toll revenue • $111 million increase driven by traffic growth and toll price escalation Other revenue 28 32 14.2% Total revenue 1,093 1,208 10.6% Total costs (276) (297) 7.6% Total costs • $21 million incre

  20. Slide 20: EBITDA margins by region

    For personal use only 1H17 FY17 1H18 • EBITDA margins have increased across all regions for 1H18 Sydney 80.9% 80.5% 81.2% • Melbourne EBITDA margin increase due to increases in toll revenue from truck toll multipliers Melbourne 86.0% 86.5% 88.5% • Margin growth for Brisbane tracking in line with exp

  21. Slide 21: Cost increases to support growth

    Cost increases to support growth in underlying business and strategic growth For personal use only project opportunities +7.6% (5) (2) 297 3 25 276 1H17 total costs Operations Maintenance Strategic growth projects Foreign exchange 1H18 total costs TRANSURBAN 1H18 RESULTS | 13 FEBRUARY 2018 20

  22. Slide 22: Free cash flow movement

    NWRG For personal use only 680 $174 million decrease due to prior period distributions from NWRG. Capital release proceeds as per NCX Development Agreement +15.0% FCF coverage FCF coverage for 33 1H18 is 101.2% (43) (174) 5 582 16 575 Net finance costs Working capital 65 $21 million increase in Incl

  23. Slide 23: Funding and debt capital market issuances

    1H18 DEBT CAPITAL MARKET ISSUANCES (TOTAL $1.3B) For personal use only Market Tenor Positioned to fund growth opportunities Private Activity 22 Years • Committed projects funded from existing balance sheet Bonds 17 Years • $1.9 billion raised in December 2017 through successful entitlement offer EUR

  24. Slide 24: Market updates

    For personal use only Market updates

  25. Slide 25: For personal use only

    For personal use only TRANSURBAN 1H18 RESULTS | 13 FEBRUARY 2018 24

  26. Slide 26: Sydney update: NorthConnex and future projects

    For personal use only Operations and maintenance Technology and customer • Re-sheeting of M7 now one third complete, • Successful launch of LinktGO GPS app in NSW with all major works expected to be finished • Working with the NSW Government to deliver mid-2018 Toll Relief Program NorthConnex update

  27. Slide 27: For personal use only

    For personal use only TRANSURBAN 1H18 RESULTS | 13 FEBRUARY 2018 26

  28. Slide 28: WestConnex process and investment approach

    For personal use only Process Transurban investment approach • Registered interest to participate in purchase of 51% • No asset is a must win of NSW Government’s infrastructure project • Proven disciplined approach to acquisitions – over 25% of portfolio • In consortium with long-standing partners a

  29. Slide 29: For personal use only

    For personal use only TRANSURBAN 1H18 RESULTS | 13 FEBRUARY 2018 28

  30. Slide 30: Melbourne update

    For personal use only Operations and maintenance Monash Freeway Upgrade Delivery and development • New control room to be built to consolidate • The final surface has been applied to • CTW new lanes opened three months operations of CityLink and WGTP sections of Monash Freeway over ahead of schedule

  31. Slide 31: West Gate Tunnel Project map

    For personal use only Western suburbs Eastern suburbs C B A A Road widening B Tunnelling C Elevated structure TRANSURBAN 1H18 RESULTS | 13 FEBRUARY 2018 30

  32. Slide 32: WGTP construction update

    For personal use only WGTP construction update Status • Construction commenced and completion • Two five-story tall (15.6 metres) / 90 metre expected in 2022 long / 4,000 tonne, purpose-built, tunnel • Approximately 700 people currently boring machines procured, commencing employed and 6,000 expecte

  33. Slide 33: For personal use only

    For personal use only TRANSURBAN 1H18 RESULTS | 13 FEBRUARY 2018 32

  34. Slide 34: Brisbane update and Toowoomba project

    For personal use only Operations and maintenance New project – Toowoomba • New tunnel network incident response and Second Range Crossing maintenance agreement commenced on • Awarded contract through Legacy Way and Go Between Bridge in 2017 competitive process to deliver • Transition to a holistic a

  35. Slide 35: Brisbane project updates

    For personal use only Inner City Bypass Logan Enhancement Project • Construction has passed halfway, with completion • Major construction commenced, with expected mid-2018 completion expected mid-2019 • Herston Road off-ramp dedicated bus lane opened • Total project cost $512 million in December 201

  36. Slide 36: For personal use only

    For personal use only TRANSURBAN 1H18 RESULTS | 13 FEBRUARY 2018 35

  37. Slide 37: Greater Washington Area update

    For personal use only Delivery Technology and customer • Early delivery of three kilometre 95 Express • Fair Travel Program launched, including Lanes Southern Extension in October 2017, heightened Virginia State Police enforcement providing improved traffic flow of HOV violations and vehicle occupan

  38. Slide 38: 95 Express Lanes Fredericksburg extension

    For personal use only Project summary • VDOT has accepted Transurban’s proposal to extend the 95 Express Lanes to the Fredericksburg region • The US$565 million project will extend the 95 Express Lanes by 16 kilometres (10 miles) • Design-build procurement process launched in January 2018 • Construc

  39. Slide 39: Executive leadership team

    For personal use only CORPORATE GEOGRAPHICAL MARKET HEADS Scott Charlton Adam Watson Sue Johnson Jennifer Aument CEO CFO2 Group Executive, President, North QLD America Vin Vassallo Tony Adams Andrew Head Michele Huey Group Executive, Group Executive, Group Executive, Group Executive, Development Pro

  40. Slide 40: Outlook and distribution guidance

    For personal use only Distribution Strong balance Applying Using technology Expanding Using skilled guidance of sheet to fund investment to enhance community resources and 56.0 cps - existing $11 billion discipline to customer engagement proven track record represents pipeline future experience and

  41. Slide 41: Supplementary information

    For personal use only Supplementary information

  42. Slide 42: Detailed financials

    For personal use only Supplementary information Detailed financials

  43. Slide 43: Toll revenue and ADT growth by region

    For personal use only DEC 17 QUARTER1 1H181 PROPORTIONAL PROPORTIONAL TOLL REVENUE ADT TOLL REVENUE ADT % CHANGE % CHANGE % CHANGE % CHANGE Sydney 7.5% 2.5% 9.8% 2.9% Melbourne 15.0% 0.3% 14.2% (1.0%) Brisbane 1.1% 3.0% 3.5% 3.5% GWA2 18.8% 2.0% 17.9% 3.4% 1. Compared to prior corresponding period.

  44. Slide 44: Asset toll revenue and traffic: Sydney and Melbourne

    For personal use only DEC 16 DEC 17 ASSET QUARTER QUARTER % CHANGE 1H17 1H18 % CHANGE Sydney M2 Total Toll Revenue ($M) $71 $76 7.1% $138 $152 9.5% Average Daily Trips (‘000) 131 133 2.1% 129 133 2.6% LCT Total Toll Revenue ($M) $24 $25 5.8% $46 $50 8.9% Average Daily Trips (‘000) 90 92 2.2% 89 92 2

  45. Slide 45: Asset toll revenue and traffic: Brisbane and GWA

    For personal use only DEC 16 DEC 17 ASSET QUARTER QUARTER % CHANGE 1H17 1H18 % CHANGE Brisbane Gateway Motorway Total Toll Revenue ($M) $55 $55 (1.3%) $110 $112 1.3% Average Daily Trips (‘000) 116 117 0.7% 116 118 1.2% Logan Motorway Total Toll Revenue ($M) $47 $47 1.6% $92 $95 4.3% Average Daily Tr

  46. Slide 46: Ownership and proportional toll revenue

    For personal use only DEC 17 QUARTER ($M) 1H18 ($M) OWNERSHIP 100% PROPORTIONAL 100% PROPORTIONAL M2 100.0% $76 $76 $152 $152 LCT 100.0% $25 $25 $50 $50 CCT 100.0% $17 $17 $34 $34 ED 75.1% $37 $28 $74 $56 M7 50.0% $110 $55 $223 $111 M5 50.0% $72 $36 $144 $72 CityLink 100.0% $196 $196 $388 $388 Gatew

  47. Slide 47: Statutory income statement

    For personal use only 1H17 ($M) 1H18 ($M) % CHANGE Toll revenue 1,032 1,131 9.6% Construction revenue 274 462 69.1% Other revenue 28 31 12.0% Total revenue 1,334 1,624 21.9% Employee benefit expense (78) (92) 17.7% Road operating costs (166) (163) (2.1%) Construction costs (274) (462) 69.1% Corporat

  48. Slide 48: Proportional earnings and EBITDA reconciliation

    For personal use only PROPORTIONAL EARNINGS 1H17 ($M) 1H18 ($M) % CHANGE Toll revenue 1,065 1,176 10.5% Other revenue 28 32 14.2% Total revenue 1,093 1,208 10.6% Total costs (276) (297) 7.6% EBITDA 817 911 11.6% RECONCILIATION OF STATUTORY EBITDA TO PROPORTIONAL EBITDA 1H17 ($M) 1H18 ($M) % CHANGE S

  49. Slide 49: Asset earnings 1H18

    For personal use only NET FINANCE INCOME TAX TOLL OTHER COST (EXP) / REVENUE REVENUE EBITDA D&A EXPENSE NPBT BENEFIT NPAT OWNERSHIP ASSET $M $M $M $M $M $M $M $M 100.0% M2 152 1 129 (37) (19) 73 4 77 100.0% LCT 50 – 33 (11) (15) 7 (2) 5 100.0% CCT 34 – 22 (12) (5) 5 (1) 4 75.1% ED 56 – 41 (19) (16)

  50. Slide 50: Asset earnings 1H17

    For personal use only NET FINANCE INCOME TAX TOLL OTHER COST (EXP) / REVENUE REVENUE EBITDA D&A EXPENSE NPBT BENEFIT NPAT OWNERSHIP ASSET $M $M $M $M $M $M $M $M 100.0% M2 138 1 118 (37) (19) 62 6 68 100.0% LCT 46 – 29 (11) (14) 4 (6) (2) 100.0% CCT 32 – 20 (12) (7) 1 – 1 75.1% ED 50 1 38 (19) (15)

  51. Slide 51: Net interest by asset 1H18

    For personal use only NON-CASH ITEMS CONCESSION PAYMENTS & STATUTORY MAINTENANCE NET PROPORTIONAL NET DEBT PROVISION INTEREST INTEREST INTEREST NET INTEREST CONTROLLED ENTITIES OWNERSHIP INTEREST FEES UNWIND CAPITALISATION ACCRUALS1 PAID PAID CityLink 100.00% (10) (3) 3 – – (10) (10) M2 100.00% (19)

  52. Slide 52: Net interest by asset 1H17

    For personal use only NON-CASH ITEMS CONCESSION PAYMENTS & STATUTORY MAINTENANCE NET PROPORTIONAL NET DEBT PROVISION INTEREST INTEREST INTEREST NET INTEREST CONTROLLED ENTITIES OWNERSHIP INTEREST FEES UNWIND CAPITALISATION ACCRUALS1 PAID PAID CityLink 100.00% (13) (3) 3 – – (13) (13) M2 100.00% (19)

  53. Slide 53: Maintenance expense and cash spend

    For personal use only MAINTENANCE MAINTENANCE 2 EXPENSE RECOGNISED CASH SPEND 1H17 ($M) 1H18 ($M) 1H17 ($M) 1H18 ($M) CityLink (7) (3) (5) (6) M2 (1) (3) (2) (1) LCT (4) (3) (3) (2) CCT (4) (3) (2) (3) ED (3) (4) (5) (2) M7 (6) (5) (2) (6) M5 (2) (2) – (2) Gateway Motorway (5) (5) (2) (3) Logan Moto

  54. Slide 54: Free cash calculation

    For personal use only FREE CASH CALCULATION SOURCE OF INFORMATION/EXPLANATION Cash flows from operating activities Statutory Transurban Holdings Limited operating cash flow (includes cash inflow from M5 TLNs). (refer Group Statutory accounts) Add back transaction and integration costs related to Tra

  55. Slide 55: Reconciliation of operating cash flow to free cash

    RECONCILIATION OF STATUTORY CASH FLOW FROM OPERATING ACTIVITIES TO FREE CASH For personal use only 1H17 ($M) 1H18 ($M) FREE CASH FLOW 1H17 1H18 % CHANGE Cash flows from operating activities 292 486 Free cash $680M $582M (14.4%) Add back transaction and integration costs related to Weighted average s

  56. Slide 56: Proportional EBITDA to free cash

    For personal use only 1H18 ($M) Comments Proportional EBITDA 911 Refer to slide 47 for further detail Proportional net finance (307) Refer to slides 50 and 51 for further detail costs paid (cash) Add back proportional maintenance 17 Refer to slide 52 for further detail expense (non-100% owned assets

  57. Slide 57: Treasury

    For personal use only Supplementary information Treasury

  58. Slide 58: Debt structure and ratings

    For personal use only Transurban3 BBB+/Baa1/A- Non- Corporate Recourse Sydney Brisbane GWA Working EMTN capital2 Airportlink 495 Express 95 Express €2.1B A$1.7B M2 LCT CCT ED3 M73 M53 TQ3 M7 Lanes Lanes3 Letter of Maple Credit -/A3/A- -/A3/A- -/A2/- BBB/-/- BBB/-/- BBB/-/BBB BBB-/-/BBB- C$0.3B A$0.5

  59. Slide 59: Debt facilities and drawn amounts

    For personal use only FACILITY FACILITY TOTAL FACILITY TOTAL DRAWN PROPORTIONAL STATUTORY (US$M)1 ($M)1 ($M) ($M) DRAWN ($M) DRAWN ($M) CORPORATE DEBT2 Working capital facilities3 – 1,650 1,650 36 36 36 USPP 162 774 982 982 982 939 EMTN (CAD, NOK and EUR Notes) 305 3,037 3,427 3,427 3,427 3,588 144A

  60. Slide 60: Proportional debt movement

    For personal use only 30 JUN 17 31 DEC 17 MOVEMENT AUD² ($M) ($M) ($M) EXPLANATION Corporate 4,330 4,613 283 Maturity of A$165 million USPP and A$300 million AMTN offset by A$749 million Euro MTN issuance Net A$5 million increase in proportional M7 debt as a result of USPP issuance and term bank rep

  61. Slide 61: Debt metrics and ratios

    For personal use only 30 JUNE 2017 31 DECEMBER 2017 TRANSURBAN NON- TRANSURBAN NON- GROUP CORPORATE RECOURSE GROUP CORPORATE RECOURSE Weighted average maturity (years)1,2 9.0 years 5.8 years 10.7 years3 9.3 years 6.4 years 10.8 years4 Weighted average cost of AUD debt1,5 4.9% 5.5% 4.5% 4.9% 5.5% 4.4

  62. Slide 62: Debt maturity profile

    For personal use only June 2017 maturity profile1,2,3 6,000 Existing debt refinanced $A MILLION 5,000 during 1H18 4,000 3,000 2,000 1,000 - FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY26 - 29 FY30 - 34 FY35+ December 2017 maturity profile1,2,3 6,000 New debt 5,000 $A MILLION raised 4,000 during 1

  63. Slide 63: Corporate debt maturity profile

    For personal use only Working capital facilities USPP AMTN EMTN 144A Letters of credit 2,000 1,800 1,600 225 1,400 A$ MILLION 1,200 711 1,000 790 800 600 321 206 208 915 733 400 833 866 233 706 200 360 375 254 219 94 - 1. Debt is shown in the financial year in which it matures. 2. Debt values are sh

  64. Slide 64: Non-recourse debt maturity profile

    For personal use only TQ (incl ALM7) ED M2 M7 CCT M5 LCT 495 95 2,000 1,800 80 1,600 467 278 1,400 179 A$ MILLION 1,200 288 1,000 350 160 800 79 85 98 535 108 609 1,307 600 225 300 90 408 200 400 845 400 40 225 60 100 100 495 475 116 440 100 200 406 250 279 302 293 277 200 200 203 200 - 37 1. The fu

  65. Slide 65: Interest rate hedging profile

    For personal use only • 99.1% of debt is interest rate TRANSURBAN INTEREST RATE HEDGING PROFILE1 hedged as at 31 December 2017 18,000 • Hedge tenor is matched to the tenor of the debt on 97%2 of drawn debt 16,000 • All foreign currency debt issued by GWA Sydney Brisbane Corporate Fixed amount Austra

  66. Slide 66: Debt funding activities

    For personal use only Debt funding activities JUN 17 GROUP DEBT1 DEC 17 GROUP DEBT1 BANK DEBT Major debt issuances during 1H18: AMTN • A$749 million corporate EUR notes AUD PRIVATE PLACEMENT • A$1,650 million corporate syndicated facility CAD NOTES • A$200 million M7 USPP notes EUR NOTES • US$45 mil

  67. Slide 67: Corporate overview

    For personal use only Supplementary information Corporate overview

  68. Slide 68: Group legal and entity structure

    For personal use only TRANSURBAN HOLDINGS LIMITED TRANSURBAN HOLDING TRUST TRANSURBAN INTERNATIONAL LIMITED CORPORATE ENTITIES ROAD/OPERATING ENTITIES OTHER ENTITIES ROAD/OPERATING ENTITIES CORPORATE ENTITIES Including: Companies operating and maintaining roads Trusts holding asset and financing Cor

  69. Slide 69: Asset overview: Melbourne and Sydney

    For personal use only MELBOURNE SYDNEY OVERVIEW CITYLINK WGT M5 M2 ED M7 NCX LCT CCT Under Under Opening date Dec 2000 Aug 1992 May 1997 Dec 1999 Dec 2005 Mar 2007 Aug 2005 construction construction Remaining concession period 17 years 22 years2 9 years 31 years 31 years 31 years 28 years3 31 years

  70. Slide 70: Asset overview: Brisbane and Greater Washington Area

    For personal use only BRISBANE GREATER WASHINGTON AREA GATEWAY LOGAN GO BETWEEN LEGACY AIRPORTLINK 495 EXPRESS 95 EXPRESS OVERVIEW CLEM7 MOTORWAY MOTORWAY BRIDGE WAY M7 LANES LANES4 Opening date Dec 1986 Dec 1988 Mar 2010 Jul 2010 Jun 2015 Jul 2012 Nov 2012 Dec 2014 Remaining concession period 34 ye

  71. Slide 71: Embedded inflation protection

    EMBEDDED INFLATION PROTECTION For personal use only MOTORWAY ESCALATION CityLink1 Escalated quarterly by the greater of quarterly CPI or 1.011065% per quarter for the first 16 years (until 31 December 2016), then quarterly by CPI. This is subject to a cap of annual CPI plus 2.5%, which cannot be exc

  72. Slide 72: Safety results

    For personal use only RESULTS TRANSURBAN RICI • RICI remains steady – this measures the number of serious injury road crashes (where an individual is transported from, or receives medical 7.0 treatment, at scene) per 100 million vehicle kilometres travelled on Transurban’s roads 6.0 • Tragically an

  73. Slide 73: Glossary

    For personal use only Supplementary information Glossary

  74. Slide 74: Glossary

    For personal use only TERM DEFINITION TERM DEFINITION 1776 Global incubator and seed fund for startups FX Foreign Exchange 1H/2H First or second half of a financial year FY Financial year 1 July to 30 June ADT Average Daily Traffic. ADT is calculated by dividing the total number of trips on each ass

  75. Slide 75: Glossary

    For personal use only TERM DEFINITION TERM DEFINITION PCP Prior Corresponding Period VB Virginia Beach PPP Public Private Partnership VDOT Virginia Department of Transportation PROP/ The proportional results are the aggregation of the results from each asset multiplied by VTIB Virginia Transport Inf

Transurban Group — H1 FY2018 Earnings Presentation on 6ix