Slide 3: Operational and financial highlights
Operational and financial highlights Record financial ⚫ Record half-year revenues, adjusted EBITDAX and profit after tax driven by higher production and realisations results ⚫ Cash as of 30 June 2022 of US$161.6 million, up 37% on end-2021, no debt on balance sheet ⚫ Montara Venture FPSO hull and ta
Slide 4: H1 2022 – record interim results
H1 2022 – record interim results Production Revenue Operating cashflow pre w/c Net (debt)/cash boe/d US$ million US$ million US$ million 16,000 250 140 180 15,008 126 162 226 225 +37% 120 150 14,000 13,188 +51% +63% +133% 200 96 118 100 120 12,116 172 12,000 175 80 90 82 150 9,934 138 10,000 60 57 6
Slide 5: Realised oil prices and premiums
Realised oil prices and premiums Strong Dated Brent pricing and premiums in H1 2022 Tapis and Stag premiums2,3 have strengthened significantly US$/bbl Tapis - US$/bbl Stag- US$/bbl 120 12 25 7.0 23.7 22.5 100 10 20 9.78 80 3.4 1.6 8 5.0 13.9 12.7 7.84 15 60 6 10.2 102.5 5.98 4.2 8.3 10 40 69.6 70.9
Slide 6: Financial Results – H1 2022 cash bridge
Financial Results – H1 2022 cash bridge Reconciliation from cash on 1 January 2022 to 30 June 2022 US$ million 350 Cash balance Operating cash flows 300 Other cash flows 250 200 150 100 50 0 Cash Revenue Opex Other Staff costs G&A and Capex Leases Tax Dividend Working Cash Value of Cash at 30 1 Jan
Slide 7: Shareholder returns update
Shareholder returns update Total shareholder return since admission to AIM Shareholder returns profile (June 2022-June 2023) US$ million Company A 100 20% 350% Dividends + buyback Company B 177% 90 18% Jadestone 109% 80 16% Cash returned to shareholders Brent 44% 70 14% Company C 5% 2022 cash yield
Slide 8: Montara field update
Montara field update 2022 timeline Montara Venture FPSO ⚫ Release of oil to sea from 2C crude oil tank ⚫ Production shut-in June ⚫ Oil dispersed within 48 hours ⚫ Temporary repair to hull/2C tank ⚫ Production restart July ⚫ Cofferdam engineering and testing onshore ⚫ Defect between 4S ballast and 5C
Slide 9: Montara Venture FPSO – current workstreams
Montara Venture FPSO – current workstreams Internal Investigation Organisational & Outcomes Actions Independent procedural review review Hull inspection and repair programme Assurance workstream Independent Operational Internal review Production restart review readiness Hull risk-based inspection as
Slide 10: 2C crude oil tank – cofferdam installed
2C crude oil tank – cofferdam installed Cofferdam illustration Cofferdam installation September 2022 Source: Hydrex Underwater Technology ⚫ 2C crude oil tank leak was quickly plugged at time of original incident in June 2022 ⚫ Permanent repair involves the design, manufacture and installation of a c
Slide 11: Montara Venture FPSO – 5C tank inspection and steel renewal
Montara Venture FPSO – 5C tank inspection and steel renewal 5C crude oil tank inspection 5C tank steel renewal - before 5C tank steel renewal - after Maintenance philosophy – no shortcuts, aim for life-of-field repair 11 | H1 2022 results review 20 September 2022
Slide 12: Montara investment since acquisition
Montara investment since acquisition Cumulative Montara investment since acquisition Montara investment highlights US$ million US$ million 60 300 ⚫ US$10 million fabric maintenance Refurbishment US$84 ⚫ US$14 million tank inspection & repairs 50 250 and repairs million ⚫ US$6 million topsides & subs
Slide 13: Montara – cash generation and value creation since acquisition
Montara – cash generation and value creation since acquisition Montara value and cash generation – at acquisition and today US$ million 700 600 500 Consensus Montara analyst valuation 400 300 Montara NPV10 at time of 200 acquisition Montara free cash flow since acquisition 100 Montara acquisition co
Slide 14: Peninsular Malaysia update
Peninsular Malaysia update Peninsular Malaysia operated assets Peninsular Malaysia non-operated assets ⚫ Year-to-date production of c.4,900 boe/d from PM323 and PM329 ⚫ Shut–in since February due to hull integrity issues on above expectations the Bunga Kertas FPSO, which resulted in a class - Well r
Slide 15: North West Shelf Oil – establishing a strategic presence in a material asset
North West Shelf Oil – establishing a strategic presence in a material asset STOIIP estimates (mmstb)1 Cum. Oil Production (mmstb)2 186 97 270 415 136 291 Cossack Lambert-Hermes Wanaea Gross production bbls/d +30% 15,000 +10% 12,500 10,000 Active oil 7,500 producer Source: Wood Mackenzie 5,000 1 Jad
Slide 16: Akatara update – good progress at site since FID
Akatara update – good progress at site since FID Akatara gas development – central processing facility – site preparation on peatland 1. “Corduroy” installation 2. Lay Geotextile and Geogrid 3. Soil fill 16 | H1 2022 results review 20 September 2022
Slide 17: Akatara update
Akatara update Well pad A – 4 wells Well pad B – 4 wells Well pad C – 2 wells Well pad D -1 well ⚫ As part of the Akatara gas development plan, a well operation program is currently planned for H2 2023 consisting of: - Intervention work on four wells for reactivation, integrity restoration and flow
Slide 18: Portfolio update
Portfolio update Stag Vietnam gas Maari ⚫ Valaris-107 rig on contract in August ⚫ Early-stage negotiations in recent months with ⚫ Legislative changes to New Zealand’s upstream the end-user of gas from Nam Du and U Minh regulatory framework implemented at the end ⚫ Initial activity focused on abando
Slide 19: 2022 guidance
2022 guidance 2022 guidance Comments ⚫ Pending finalisation on work programme at Montara prior to Group production 11,000—13,000 boe/d restart ⚫ Increased opex/bbl guidance is solely a reflection of the Opex US$31.00—37.00/boe recently reduced production guidance above ⚫ Stag infill drilling Capex U
Slide 20: Q&A
Q&A H1 2022 results review, 20 September 2022
Slide 21: Appendix
Appendix Jadestone @ Energy
Slide 22: Montara tank inspection by drone
Montara tank inspection by drone - provides detailed condition record 22 | H1 2022 results review 20 September 2022
Slide 23: Montara FPSO deckplate corrosion – before and after
Montara FPSO deckplate corrosion – before and after 23 | H1 2022 results review 20 September 2022
Slide 24: Montara FPSO pump room roof remediation – before and after
Montara FPSO pump room roof remediation – before and after 24 | H1 2022 results review 20 September 2022
Slide 25: Montara FPSO – remediation of corrosion to structural frames
Montara FPSO – remediation of corrosion to structural frames 25 | H1 2022 results review 20 September 2022
Slide 26: Montara FPSO – remediation of helideck stairway
Montara FPSO – remediation of helideck stairway 26 | H1 2022 results review 20 September 2022
Slide 27: Montara FPSO – remediation of hose hangoff platform
Montara FPSO – remediation of hose hangoff platform 27 | H1 2022 results review 20 September 2022
Slide 28: Montara FPSO – remediation of corrosion in high-pressure systems
Montara FPSO – remediation of corrosion in high-pressure systems 28 | H1 2022 results review 20 September 2022