Knr Constructions Limited · NSE:KNRCON
Knr Constructions — Investor Presentation (November 2019)
42 slides from Knr Constructions's investor presentation, Nov 14, 2019
Slide 1: Cover letter to stock exchanges: Investors presentation November 2019
I \ Rd KNR Constructions Limited. Datc: 14d' November 2019 Ref: KNRCL/SD / 201,9 / 1,86 & "187 To To Dept. of Corporate Serviccs, National Stock Exchange of India Limited BSE Limited "Exchange Plaza", P J Towers, Dalal Street, Bandra Kurla Complex, Fort, MUMBAI - 400001 Bandra (E), MUMBAI - 400051 B
Slide 2: KNR Constructions Limited Investor Presentation November 2019
KNR Constructions Limited Investor Presentation November 2019 Positioned To Build A New India
Slide 3: Disclaimer
Disclaimer This presentation and the accompanying slides (the “Presentation”), which have been prepared by KNR Constructions Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any secu
Slide 4: Key Highlights & Result Update
Key Highlights & Result Update
Slide 5: Standalone Financial Highlights
Standalone Financial Highlights (Rs. Million) Revenue EBITDA EBITDA Margins PAT +31% +51% +300 bps +56% 5,462 1,258 23.0% 701 20.0% 4,163 831 450 Q2 FY20 Q2 FY19 Q2 FY20 Q2 FY19 Q2 FY20 Q2 FY19 Q2 FY20 Q2 FY19 Q2 FY20 Revenue EBITDA EBITDA Margins PAT +4% +12% +150 bps -1% 9,726 10,108 2,158 21.3% 1
Slide 6: Standalone Financial Results
Standalone Financial Results Standalone Rs. Million Q2 FY20 Q2 FY19 YoY H1 FY20 H1 FY19 YoY Total Revenue 5,462.0 4,162.9 31% 10,108.0 9,726.5 4% Operating Expenses 3,157.0 2,630.0 6,210.2 6,215.2 Employees Expenses 362.8 249.3 634.2 445.2 Other Expenditure 684.4 452.2 1,105.6 1,136.1 EBITDA 1,257.8
Slide 7: Standalone Balance Sheet
Standalone Balance Sheet ASSETS (Rs. Million) Sep-19 Mar-19 EQUITY & LIABILITIES (Rs. Million) Sep-19 Mar-19 Non-Current Assets Equity Property, plant and equipment 4,257.0 3,709.2 Equity Share capital 281.2 281.2 Capital work-in-progress 56.0 0.1 Other equity 14,972.1 13,861.9 Right of Use Asset 18
Slide 8: Consolidated Financial Results
Consolidated Financial Results Consolidated Rs. Million Q2 FY20 Q2 FY19 YoY H1 FY20 H1 FY19 YoY Total Revenue 5,870.7 4,504.2 30% 11,177.9 10,423.0 7% Operating Expenses 3,179.5 2,698.9 6,573.0 6,327.5 Employees Expenses 367.3 253.9 642.7 454.4 Other Expenditure 741.5 518.2 1,221.6 1,256.3 EBITDA 1,
Slide 9: Consolidated Balance Sheet
Consolidated Balance Sheet ASSETS (Rs. Million) Sep-19 Mar-19 EQUITY & LIABILITIES (Rs. Million) Sep-19 Mar-19 Non-Current Assets Equity Property, plant and equipment 4,290.2 3,746.0 Equity Share capital 281.2 281.2 Capital work-in-progress 56.0 0.1 Instruments entirely equity in nature 85.0 85.0 Ri
Slide 10: Cash Flow Statement
Cash Flow Statement Standalone Consolidated Particulars (Rs. Million) Sep-19 Sep-18 Sep-19 Sep-18 Net Profit Before Tax 1,489.4 1,296.9 1,588.4 1,187.9 Adjustments for: Non-Cash Items / Other Investment or Financial Items 763.3 769.3 1,255.3 1,418.3 Operating profit before working capital changes 2,
Slide 11: Key Updates
Key Updates ❑ Company has a Portfolio of 5 HAM Projects worth of Rs.60,491.7 Million (BPC) ❑ The concession agreement between KNR Chidambaram Infra Private Limited and NHAI is deemed terminated with effect from 11th April 2019 as per the Clause 4.5 of the concession agreement ❑ During Q2 FY20, the c
Slide 12: Business Overview
Business Overview
Slide 13: Business Overview
Business Overview ❑ One of the leading companies providing Engineering, Procurement and Construction (EPC) services ▪ Major Projects in Roads & Highways – one of the fast-growing sectors ▪ Established presence in Irrigation and Urban Water Infrastructure Management Vision ❑ 20 years of experience of
Slide 14: Transformation
Transformation 1995 2006 2007 2008 ▪ Incorporated & Commenced EPC ▪ Bagged 1st BOT Project in Karnataka ▪ Bagged 2nd BOT project worth ▪ IPO & Listed on BSE and NSE Business worth Rs. 4,420 mn; Entry into Urban Rs.5,920mn in Telangana water Infrastructure with contract in Bangalore 2013 2013 2012 20
Slide 15: Top Management
Top Management Mr. K. Narasimha Reddy – Mr. K. Jalandhar Reddy – Founder Promoter & Managing Director Promoter & Executive Director ▪ Over 50 years of experience in the Highway sector ▪ Over 25 years of experience in the Highway and ▪ Started career in 1968 and engaged in the business of infrastruct
Slide 16: Supported by Professional Team
Supported by Professional Team ▪ A Bachelor of Engineering (BE) from MITS Gwalior (MP) with Over 35 years of total experience with ~20 years of Mr. T.L. Verma experience in Highway sector (Sr. Vice President - Projects) ▪ Working with the company since 2006 on various projects i.e. Bridges and Highw
Slide 17: Key Business Strengths
Key Business Strengths
Slide 18: Project Execution Capabilities
1. Project Execution Capabilities ❑ Top management’s active involvement at all stages of Project execution ▪ Selection of Major Raw Material ▪ Selection of construction Camp location ❑ Faster Decision making to ensure project completion on schedule ❑ Received Bonus for completion of construction ahe
Slide 19: Pan India Project Execution Capability
Pan India Project Execution Capability* Bihar Arunachal Pradesh No of Projects 1 No of Projects 1 Uttar Pradesh Value of Projects Rs. 1,411 mn Value of Projects Rs. 920 mn No of Projects 4 Value of Projects Rs. 1,704 mn Assam No of Projects 2 Madhya Pradesh Value of Projects Rs. 1,913 mn No of Proje
Slide 20: Project Execution Highlights
Project Execution Highlights Cement Concrete Road ▪ Completed Widening to 4/6 lanes and Strengthening of Existing two lane carriageway of NH – 5 in the State of Orissa for a length of 56.0 Kms with total contract value of work is Rs 2,310 mn ▪ Existing road was widened & strengthened with flexible p
Slide 21: In-house Construction Equipment
2. In-house Construction Equipment Sr. No. Machinery Quantity Sr. No. Machinery Quantity 1 Tippers & Tankers 1,075 14 Rollers 32 2 Excavators 314 15 Crushers 27 3 Generators 199 16 Light Soures 25 4 Concrete Mixers And Pumps 131 17 Trailers 24 5 Compactors 128 18 Dozers 28 6 Loaders 75 19 Compressor
Slide 22: In-house Execution Team
3. In-house Execution Team 5% Total Employees* Project Engineering 1,655 32% Site Supervision 35% Site Engineers Equipment Operators 8% Admin & Office Staff 20% IN-HOUSE TEAM OF QUALIFIED AND EXPERIENCED EMPLOYEES LED BY PROVEN MANAGEMENT TEAM * as on September 30, 2019 21
Slide 23: Host of Marque Clients
4. Host of Marque Clients National Andhra Pradesh Ministry of Hyderabad Karnataka Karnataka Road Highways Road Development Road Transport Growth State Highway Development Authority of Corporation & Highways Corridor Improvement Corporation India (NHAI) (APRDC) (MoRTH) Limited (HGCL) Project (KSHIP)
Slide 24: BOT Portfolio
BOT Portfolio
Slide 25: BOT Portfolio – Annuity Projects
BOT Portfolio – Annuity Projects Particulars Patel KNR Infrastructures limited (PKIL) Patel KNR Heavy Infrastructures Limited (PKHIL) Stake 40% 40% Project Details Project Type Road-Annuity Road-Annuity State Karnataka Telangana JV Partner PEL PEIL Client NHAI NHAI Length (KM) 60.0 53.0 Concession S
Slide 26: BOT Portfolio – Toll Projects
BOT Portfolio – Toll Projects Particulars KNR Walayar Tollways Private Limited KNR Muzaffarpur Barauni Tollway Private Limited Stake 100% 51% Project Details Project Type Road-Toll Road-Toll State Kerala Bihar JV Partner - JKM Infra Project Ltd Client NHAI NHAI No of Lanes Two to Four Two Length(KM)
Slide 27: HAM Portfolio
HAM Portfolio Trichy to Chittor to Ramsanpalle to Magadi to Oddanchatram to Particulars Kallagam Mallavaram Mangloor Somwarpeth Madathukulam* KNR Srirangam Infra KNR Tirumala Infra KNR Shankarampet Projects KNR Somwarpeth Infra KNR Palani Infra SPV Name Private Limited Private Limited Private Limite
Slide 28: Details of SPA with Cube
Details of SPA with Cube^ Total Equity Cube’s Equity Share KNR’s Equity Share Consideration for KNR’s Particulars (Rs. mn) (49%) (Rs. mn) (51%) (Rs. mn) 51% stake (Rs. mn)* KNR Sriranagm Infra Pvt Ltd 471.5 490.8 736.1 (SPA Signed: 28th Jan’19) 962.3 1.50 times KNR Tirumala Infra Pvt Ltd 701.9 730.6
Slide 29: Order Book & Business Strategy
Order Book & Business Strategy
Slide 30: Order-book Highlights
Order-book Highlights Order Book Break-up Key Projects Rs. Mn Chittor to Mallavarm Project (HAM) 8,749 46% Non- Ramsanpalle to Mangloor Project (HAM) 7,279 43% Captive 57% Trichy to Kallagam Project (HAM) 6,305 11% Hubli – Hospet Section of NH - 63 3,070 Captive (HAM Projects) State Govt. Central Go
Slide 31: HAM Projects Won
HAM Projects Won Rs. million 15,350^ 66,818 Bid Project Cost HAM Projects Not Included in Order Book (Rs. mn) 51,468 Two laning with paved shoulders of Magadi to near Somwarpeth In 11,445.0 the State of Karnataka Four Laning of Oddanchatram – Madathukulam section of NH - 209 (New NH-83) under Bharat
Slide 32: Order-book: State-wise
Order-book: State-wise Arunachal Pradesh No of Projects 1 Balance Value Rs. 1,092 mn Karnataka No of Projects 5 Balance Value Rs. 4,920 mn AP & Telangana No of Projects 10 Balance Value Rs. 34,611 mn Kerala No of Projects 3 Balance Value Rs. 712 mn Tamil Nadu No of Projects 11 Balance Value Rs. 10,1
Slide 33: Business Strategy
Business Strategy Focus on Projects involving Higher degree of engineering skills 03 Focus on securing EPC Continuously explores contracts from reputed growth opportunities by Clients and forming strategic Joint Concessionaire Ventures (JVs) 02 04 Capitalise on Opportunity Execute all the projects o
Slide 34: Financial Highlights
Financial Highlights
Slide 35: Standalone Financial Highlights
Standalone Financial Highlights* Financial Year 2010 2011 2012 2013 2014 2015 2016^ 2017^ 2018^ 2019^ Rs. 7,125 Rs. 7,930 Rs. 7,505 Rs. 6,921 Rs. 8,348 Rs. 8,761 Rs. 9,025 Rs. 15,411 Rs. 19,317 Rs.21,373 Turnover $118.6 $132.0 $125.0 $115.2 $139.0 $140.0 $136.1 $238.3 $296.9 $306.8 Rs. 1,121 Rs. 1,3
Slide 36: Standalone Financial Highlights
Standalone Financial Highlights Revenue & EBITDA (Margin %) EBITDA Margin (%) 15.7% 17.1% 17.8% 16.8% 15.1% 14.4% 16.9% 14.9% 19.9% 20.0% 21,373 19,317 15,411 7,930 8,348 8,761 9,026 EBITDA 7,125 7,505 6,921 Revenue 3,839 4,270 1,121 1,356 1,338 1,164 1,258 1,261 1,529 2,296 2010 2011 2012 2013 2014
Slide 37: Standalone Net Working Capital Days
Standalone Net Working Capital Days 79 69 53 52 48 52 42 40 42 43 41 36 36 28 30 26 23 18 20 19 20 20 19 16 16 15 15 15 17 16 13 14 12 14 7 98 10 66 45 64 51 74 53 39 45 40 58 53 Mar-10 Mar-11 Mar-12 Mar-13 Mar-14 Mar-15 Mar-16 Mar-17 Mar-18 Mar-19 Jun-19 Sep-19 Inventory Debtors Creditors Net Worki
Slide 38: Shareholding Pattern as on 30th September 2019
Shareholding Pattern as on 30th September 2019 Shareholders Holding more than 1% of the Equity % to Equity (Other than Promoters) 11.51% ICICI Prudential Mutual Fund 6.75% HDFC Mutual Fund 6.40% DSP Blackrock Mutual Fund 6.24% 30.17% 55.17% L&T Mutual Fund 2.16% Franklin Mutual Fund 2.00% UTI Mutual
Slide 39: Completed Projects
Completed Projects Walayar Road Project MP Road Site MP Road Site Eturunagaram Bridge over river Muzaffarpur-Barauni Road Walayar Toll plaza Godavari Project 38
Slide 40: Under Construction Projects
Under Construction Projects Salem Flyover River Bridge KP Sagar Irrigation Flyover in Madurai - Coimbatore Flyover Salem Flyover Ramanathpuram Section 39
Slide 41: Equipments & Others
Equipments & Others Concrete Paver Gantry Tippers at Irrigation Site Tippers Workers on Site Excavator 40
Slide 42: For further information, please contact
For further information, please contact Company : Investor Relations Advisors : KNR Constructions Ltd. CIN: L74210TG1995PLC130199 Strategic Growth Advisors Pvt. Ltd. Mr. K. Venkata Ram Rao CIN: U74140MH2010PTC204285 (GM - Finance & Accounts) Mr. Jigar Kavaiya / Mr. Rohan Adhiya venkatram@knrcl.com +
KNR Constructions — Investor Presentation (November 2019) on 6ix