AGL Energy Limited · ASX:AGL

AGL Energy — Corporate Update (September 2019)

32 slides from AGL Energy's corporate update, Sep 19, 2019

  1. Slide 1: Silverton Wind Farm Community Consultative Committee Meeting CCC-033

    Slide 1: Silverton Wind Farm Community Consultative Committee Meeting CCC-033

    Silverton Wind Farm Community Consultative Committee Meeting No.CCC-033 Thursday, 19 September 2019 Click icon to add picture

  2. Slide 2: Agenda

    Slide 2: Agenda

    Agenda 1 2 3 4 5 6 Welcome Previous Project update Community Topics of interest Other minutes • Overview relations • Generation business Performance • Wind Farm Works update • WTG Performance GE • Commissioning 3.43-130 • WTG34 Gearbox Oil Spill • AGL Group Operations Silverton Wind Farm | 19 Septem

  3. Slide 3: 1. Welcome

    Slide 3: 1. Welcome

    1. Welcome

  4. Slide 4: Introduction

    Slide 4: Introduction

    1. Welcome Silverton Wind Farm Introduction • With all the wind turbines constructed and commissioned, AGL’s Construction Team and Wind & Solar Team is preparing for the transition from construction to operations. - Jo Stone, Head of Wind & Solar - Richard Armstrong, Asset Leader - Colin Hill, Asset

  5. Slide 5: 2. Previous minutes

    Slide 5: 2. Previous minutes

    2. Previous minutes

  6. Slide 6: Action items

    Slide 6: Action items

    2. Previous minutes Action items Item Action Status Who 3.23.16 AGL to contact Rod Grenfell in relation to erecting a fence along Daydream Mine Road near the Open AGL – 9/19 Umberumberka pipeline access. 4.25.07 AGL to progress the 20m monopole with Telstra and Crown as part of the mobile reception

  7. Slide 7: 3. Project update

    Slide 7: 3. Project update

    • Overview • Wind Farm Works • Connection Works 3. Project update

  8. Slide 8: Silverton Wind Farm

    Slide 8: Silverton Wind Farm

    3. Project update Silverton Wind Farm Silverton Wind Farm • Located in the Barrier Ranges approximately 5km north of the Silverton township • Owned by the Powering Australian Renewable Fund (PARF) • Generation capacity of 200 MW • Wind turbines: 58 x GE 3.43-130 • Annual Energy Production (AEP) - ~7

  9. Slide 9: Scope of works

    Slide 9: Scope of works

    3. Project update Silverton Wind Farm Scope of works • Silverton Wind Farm consists of two main scope of work: - Wind Farm Works (GE-CATCON) - Connection Works (TransGrid) • AGL has prepared an Overview Environmental Management Strategy (OEMS) in accordance with the project approval • Overview activ

  10. Slide 10: Wind Farm Works

    Slide 10: Wind Farm Works

    3. Project update Silverton Wind Farm Wind Farm Works • GE-CATCON (joint venture) has been engaged to deliver the wind farm works - Engineer, Procure, Construct (EPC) Contract • Scope of works, includes - 58 x GE 3.43-130 wind turbines - 33kV electrical reticulation (underground and overhead) and 33

  11. Slide 11: Connection Works

    Slide 11: Connection Works

    3. Project update Silverton Wind Farm Connection Works • TransGrid has achieved Practical Completion on 20 February 2018 - Existing Broken Hill 220kV substation (connection point) - 220kV transmission line - Wind farm 220kV substation • Connection works were successfully energised on 23 Feb 2018. •

  12. Slide 12: Construction works

    Slide 12: Construction works

    3. Project update Wind Farm Works Construction works • Following the previous CCC meeting, GE- CATCON has focused on the following activities: - WTG troubleshooting to maintain availability - Site access road finalisation - Site rehabilitation - Construction demobilisation - WTG maintenance activiti

  13. Slide 13: Construction works – Progress photos

    Slide 13: Construction works – Progress photos

    3. Project update Wind Farm Works Construction works – Progress photos Silverton Wind Farm | 19 September 2019 13

  14. Slide 14: Wind Turbine Commissioning

    Slide 14: Wind Turbine Commissioning

    3. Project update Wind Farm Works Wind Turbine Commissioning • The wind farm is currently being commissioned in accordance with the AEMO commissioning plan which involves coordination with AEMO and TransGrid (NSP). - AEMO – Australian Energy Market Operator - NSP – Network Service Provider • Commiss

  15. Slide 15: 4. Community relations update

    Slide 15: 4. Community relations update

    4. Community relations update

  16. Slide 16: Community enhancement program

    Slide 16: Community enhancement program

    4. Community relations update Community enhancement program Community Enhancement Program The Community Enhancement Program for the Silverton Wind Farm is progressing, in accordance with condition 18 (schedule 2) of the project approval. We are implementing the program to give effect to the commitme

  17. Slide 17: Silverton Solar Program

    Slide 17: Silverton Solar Program

    4. Community relations update Community enhancement program Silverton Solar Program • To date, AGL has provided solar panels to 30 property owners and 25 of these properties have received their smart meters and are “operational”. • Some properties received panels from AGL as their property was under

  18. Slide 18: Water Tank Program

    Slide 18: Water Tank Program

    4. Community relations update Community enhancement program Water Tank Program • AGL is progressing supply, installation and connection of a domestic sized water tank (10,000L) - Water tank supply  Landmark - Installation and connection  Broken Hill Plumbing Services • Rolling installations starte

  19. Slide 19: Mobile Reception Program – Black Spot Funding

    Slide 19: Mobile Reception Program – Black Spot Funding

    4. Community relations update Community enhancement program Mobile Reception Program – Black Spot Funding • On 18 March 2019, the Minister for Regional Services, Senator the Hon Bridget McKenzie, announced the results of the Round 4 competitive assessment process, including the Silverton small cell.

  20. Slide 20: Visual Impact Mitigation

    Slide 20: Visual Impact Mitigation

    4. Community relations update Visual impact mitigation Visual Impact Mitigation AGL issued notification to the Silverton residents in accordance with condition 2 (schedule 3) of the project approval in relation to the visual impact mitigation measures outlined in condition 1 (schedule 3). • Owners w

  21. Slide 21: Silverton Hotel Broken Heel Festival 2019

    Slide 21: Silverton Hotel Broken Heel Festival 2019

    4. Community relations update Silverton Hotel Broken Heel Festival 2019 Silverton Wind Farm | 19 September 2019 21

  22. Slide 22: Community information

    Slide 22: Community information

    4. Community relations update Community engagement Community information AGL contact details for community and project information are shown below: • P: 1800-039-600 • E: community@agl.com.au • W: agl.com.au/silverton Construction information GE-CATCON will provide contact details on the project sig

  23. Slide 23: 5. Topics of interest

    Slide 23: 5. Topics of interest

    • Generation Performance • WTG Performance GE 3.43-130 • WTG34 Gearbox Oil Spill • AGL Group Operations 5. Topics of interest

  24. Slide 24: Generation Profile

    Slide 24: Generation Profile

    5. Topics of interest Generation Performance Generation Profile • First generation occurred from the Silverton Wind Farm (STWF) on Saturday, 12 May 2018 at 23:30 hrs • Generation from the Silverton Wind Farm (STWF) as at Sunday, 15 September 2019. - 380,265 MWh - Already powering approximately 70,50

  25. Slide 25: Wind Turbine GE 3.43-130

    Slide 25: Wind Turbine GE 3.43-130

    5. Topics of interest Wind Farm Works Wind Turbine GE 3.43-130 • GE 3.43-130 Power Curve - Cut in wind speed – 3 m/s - Rated wind speed – 13 m/s - Cut out wind speed – 25 m/s Silverton Wind Farm | 19 September 2019 25

  26. Slide 26: WTG34 Gearbox Oil Spill

    Slide 26: WTG34 Gearbox Oil Spill

    5. Topics of interest WTG34 Gearbox Oil Spill Minor incident • GE 3.43-130 wind turbine gearbox has an oil capacity of 560l • Nacelle contains built in bunding • Approximately 200l of oil leaked from the gearbox at WTG34 on 29 May 2019 • The oil was contained in the tower bunding. No environmental i

  27. Slide 27: AGL Wind & Solar team

    Slide 27: AGL Wind & Solar team

    5. Topics of interest AGL Group Operations AGL Wind & Solar team • Silverton Wind Farm will be managed by the AGL Wind & Solar team. • Responsible for asset management and operations for: - Nyngan Solar Plant - Broken Hill Solar Plant - Silverton Wind Farm - Coopers Gap Wind Farm* (under constructio

  28. Slide 28: AGL's Generation Portfolio

    Slide 28: AGL's Generation Portfolio

    5. Topics of interest AGL Group Operations AGL’s Generation Portfolio AGL Gas and Renewables • Torrens Island • Gas Operations • Renewables • Wind and Solar • Hydro • Operations Silverton Wind Farm | 19 September 2019 28

  29. Slide 29: AGL's Generation Portfolio

    Slide 29: AGL's Generation Portfolio

    5. Topics of interest AGL Group Operations AGL’s Generation Portfolio AGL Gas and Renewables • Torrens Island • Gas Operations • Renewables • Wind and Solar • Hydro • Operations Silverton Wind Farm | 19 September 2019 29

  30. Slide 30: 6. Other business

    Slide 30: 6. Other business

    6. Other business

  31. Slide 31: Next meeting

    Slide 31: Next meeting

    Silverton Wind Farm Community Consultative Committee (CCC) • Next meeting (TBC) - Thursday, 19 March 2020 - Time: 6:00pm - Silverton Municipal Chambers, Silverton Next meeting

  32. Slide 32: Contact

    Slide 32: Contact

    Click icon to add picture Contact AGL Energy Silverton Wind Farm 1800-039-600 AGLcommunity@agl.com.au

Source: Internet Archive copy of agl.com.au