  1. Slide 1: Silverton Wind Farm Community Consultative Committee

    Silverton Wind Farm Community Consultative Committee Meeting No.CCC-032 Thursday, 23 May 2019

  2. Slide 2: Agenda

    Agenda 1 2 3 4 5 6 Welcome Previous Project update Community Topics of interest Other minutes • Overview relations • Weekly Generation business Performance • Wind Farm Works update • Silverton Wind • Commissioning Forecast • Rehabilitation Works • Daydream Mine Road • WTG40 gearbox oil spill Silvert

  3. Slide 3: 1. Welcome

    co) = fe) 2) O® =

  4. Slide 4: 2. Previous minutes

    2. Previous minutes

  5. Slide 5: Action items

    2. Previous minutes Action items Item Action Status Who 3.23.16 AGL to contact Rod Grenfell in relation to erecting a fence along Daydream Mine Road near the Open AGL – 3/19 Umberumberka pipeline access. 4.25.07 AGL to progress the 20m monopole with Telstra and Crown as part of the mobile reception

  6. Slide 6: 3. Project update

    • Overview • Wind Farm Works • Connection Works 3. Project update

  7. Slide 7: Silverton Wind Farm

    3. Project update Silverton Wind Farm Silverton Wind Farm • Located in the Barrier Ranges approximately 5km north of the Silverton township • Owned by the Powering Australian Renewable Fund (PARF) • Generation capacity of 200 MW • Wind turbines: 58 x GE 3.43-130 • Annual Energy Production (AEP) - ~7

  8. Slide 8: Scope of works

    3. Project update Silverton Wind Farm Scope of works • Silverton Wind Farm consists of two main scope of work: - Wind Farm Works (GE-CATCON) - Connection Works (TransGrid) • AGL has prepared an Overview Environmental Management Strategy (OEMS) in accordance with the project approval • Overview activ

  9. Slide 9: GE-CATCON wind farm works

    3. Project update Silverton Wind Farm Wind Farm Works • GE-CATCON (joint venture) has been engaged to deliver the wind farm works - Engineer, Procure, Construct (EPC) Contract • Scope of works, includes - 58 x GE 3.43-130 wind turbines - 33kV electrical reticulation (underground and overhead) and 33

  10. Slide 10: Connection Works

    3. Project update Silverton Wind Farm Connection Works • TransGrid has achieved Practical Completion on 20 February 2018 - Existing Broken Hill 220kV substation (connection point) - 220kV transmission line - Wind farm 220kV substation • Connection works were successfully energised on 23 Feb 2018. •

  11. Slide 11: Construction works

    3. Project update Wind Farm Works Construction works • Wind turbines erection: - WTG erection complete: 58/58 (100%) - WTG mechanical completion: 58/58 (100%) • Wind turbines commissioning: - WTG commissioned: 58/58 (100%) Installation of the final blade to WTG48 on Wednesday afternoon, 27 February

  12. Slide 12: Construction works – Progress photos

    3. Project update Wind Farm Works Construction works – Progress photos Silverton Wind Farm | 23 May 2019 12

  13. Slide 13: Wind Turbine Commissioning

    3. Project update Wind Farm Works Wind Turbine Commissioning • The wind farm is currently being commissioned in accordance with the AEMO commissioning plan which involves coordination with AEMO and TransGrid (NSP). - AEMO – Australian Energy Market Operator - NSP – Network Service Provider • Commiss

  14. Slide 14: Wind Turbine GE 3.43-130

    3. Project update Wind Farm Works Wind Turbine GE 3.43-130 • GE 3.43-130 Power Curve - Cut in wind speed – 3 m/s - Rated wind speed – 13 m/s - Cut out wind speed – 25 m/s Silverton Wind Farm | 23 May 2019 14

  15. Slide 15: First Generation

    3. Project update Wind Farm Works First Generation • First generation occurred from the Silverton Wind Farm (STWF) on Saturday, 12 May 2018 at 23:30 hrs • Generation from the Silverton Wind Farm (STWF) as at Tuesday, 19 February 2019. - 208,000 MWh - Already powering approximately 36,500 average Aus

  16. Slide 16: Local Industry Participation

    3. Project update Wind Farm Works Local Industry Participation • Currently ~30 construction workers with approximately 40% from the local area. - Continued reduction in the number of construction workers. - Local component mainly associated with the operation and maintenance of the wind turbines. Si

  17. Slide 17: Local suppliers

    3. Project update Wind Farm Works Local suppliers • Delivery of the Silverton Wind Farm to date has involved the following local suppliers / contractors - Attards Transport - Interhealth Broken Hill - Barrier Daily Truth - Judd Plumbing - Boss Construction - Lawrence Engineering - Broken Hill City C

  18. Slide 18: 4. Community relations update

    4. Community relations update

  19. Slide 19: Community enhancement program

    4. Community relations update Community enhancement program Community Enhancement Program The Community Enhancement Program for the Silverton Wind Farm is progressing, in accordance with condition 18 (schedule 2) of the project approval. We are implementing the program to give effect to the commitme

  20. Slide 20: Silverton Solar Program

    4. Community relations update Community enhancement program Silverton Solar Program • To date, AGL has provided solar panels to 30 property owners and 23 of these properties have received their smart meters and are “operational”. • Origin, Red Energy and Acumen are generally the energy retailer and

  21. Slide 21: Water Tank Program

    4. Community relations update Community enhancement program Water Tank Program • AGL is progressing supply, installation and connection of a domestic sized water tank (10,000L) - Water tank supply  Landmark - Installation and connection  Broken Hill Plumbing Services • Rolling installations starte

  22. Slide 22: Mobile Reception Program – Black Spot Funding

    4. Community relations update Community enhancement program Mobile Reception Program – Black Spot Funding • On 18 March 2019, the Minister for Regional Services, Senator the Hon Bridget McKenzie, announced the results of the Round 4 competitive assessment process, including the Silverton small cell.

  23. Slide 23: Visual Impact Mitigation

    4. Community relations update Visual impact mitigation Visual Impact Mitigation AGL issued notification to the Silverton residents in accordance with condition 2 (schedule 3) of the project approval in relation to the visual impact mitigation measures outlined in condition 1 (schedule 3). • Owners w

  24. Slide 24: Silverton Sunsets Music Festival

    4. Community relations update Silverton Sunsets Music Festival Silverton Wind Farm | 23 May 2019 24

  25. Slide 25: Community engagement

    4. Community relations update Community engagement Community information AGL contact details for community and project information are shown below: • P: 1800-039-600 • E: community@agl.com.au • W: agl.com.au/silverton Construction information GE-CATCON will provide contact details on the project sig

  26. Slide 26: 5. Topics of interest

    • Weekly Generation Performance • Silverton Wind Forecast • Rehabilitation Works • Daydream Mine Road • WTG40 Gearbox Oil Spill 5. Topics of interest

  27. Slide 27: Weekly Generation Performance

    5. Topics of interest Weekly Generation Performance Generation Performance • Weekly graph for Tuesday, 14 May to 22 May 2019 Silverton Wind Farm | 23 May 2019 27

  28. Slide 28: Silverton Wind Forecast

    5. Topics of interest Silverton Wind Forecast Silverton Wind Forecast • Monitoring night-time wind forecast for staging tests at 48 WTGs and +50 WTGs. Silverton Wind Farm | 23 May 2019 28

  29. Slide 29: Rehabilitation Works

    5. Topics of interest Rehabilitation Works Wind Farm Works • GE-CATCON is progressing rehabilitation works across the site in accordance with the construction phase rehabilitation management plan specific to the Silverton Wind Farm site. • Rain events from April and May 2019 have seen striking of ex

  30. Slide 30: Daydream Mine Road Maintenance Works

    5. Topics of interest Daydream Mine Road Maintenance Works • GE-CATCON has undertaken maintenance works to Daydream Mine Road and is progressing handover to Roads and Maritime Services (RMS). Silverton Wind Farm | 23 May 2019 30

  31. Slide 31: WTG40 Gearbox Oil Spill

    5. Topics of interest WTG40 Gearbox Oil Spill Minor incident • GE 3.43-130 wind turbine gearbox has an oil capacity of 560l • Nacelle contains built in bunding • Approximately 400-500l of oil leaked from the gearbox at WTG40 on 28 April 2019 • About 1.5l of oil made it to the base of the wind turbin

  32. Slide 32: 6. Other business

    6. Other business

  33. Slide 33: Next meeting

    Silverton Wind Farm Community Consultative Committee (CCC) • Next meeting (TBC) - Thursday, 19 September 2019 - Time: 6:00pm - Silverton Municipal Chambers, Silverton Next meeting