  1. Slide 1: Interruptible Load Program (ILP)

    Interruptible Load Program (ILP) APRIL 19, 2024

  2. Slide 2: About the Interruptible Load Program (ILP)

    About the Interruptible Load Program (ILP) ILP was promulgated under ERC Resolution No. 8 Series of 2010 and amended by Resolution No. 8 Series of 2013, No. 5 Series of 2015, and No. 3 Series of 2019. ILP was first implemented in Visayas and Mindanao to ration limited power supply and avert prolonge

  3. Slide 3: About the Interruptible Load Program (ILP)

    About the Interruptible Load Program (ILP) ILP is a voluntary, demand-side management program that allows customers to collectively reduce electricity drawn from the grid when power interruptions are imminent to ration limited power supply. • Open to non-contestable customers, contestable customers,

  4. Slide 4: About the Interruptible Load Program (ILP)

    About the Interruptible Load Program (ILP) • The ILP Agreement, protocol, as well as the compensation and recovery mechanism, are part of ERC Resolution No. 5 Series of 2015 • For captive customers, the ILP Agreement is between the customer and the DU • For contestable customers, the ILP Agreement i

  5. Slide 5: About the Interruptible Load Program (ILP)

    About the Interruptible Load Program (ILP) As of April 2024, the total capacity available for de-loading in MERALCO’s area is 529.67 MW from 103 companies representing 239 participating services. MERALCO ILP DE-LOADING CAPACITY (MW) WITH SIGNED AGREEMENTS Signed Potential Contestable Potential Capti

  6. Slide 6: About the Interruptible Load Program (ILP)

    About the Interruptible Load Program (ILP) Since its implementation in 2014, MERALCO ILP has spared as many as 1.8 million households from rotating power interruptions. 6

  7. Slide 7: 5 Steps to Implementing ILP

    Notification Activation Determination of Compensable kWh 5 Steps to Implementing ILP Billing Settlement

  8. Slide 8: Steps to Implementing ILP: Notification

    5 Steps to Implementing ILP Notification 1 Activation NOTIFICATION: MERALCO’s Customer Care Group directly notifies ILP Participants Determination of through their contact Compensable kWh persons of grid conditions and possible ILP activation Billing Settlement 8

  9. Slide 9: ILP Notification Process

    ILP Notification Process 1st Notification: 5pm of prior day Only with Yellow and Red System Alerts from NGCP NGCP advice Immediately 2nd Notification: 7am of current day confirm to Yellow and Red System Alerts updates from NGCP Customer Care: (1) receipt of notification/ Red Alert confirmation, stat

  10. Slide 10: Notification Reminders

    Notification Reminders Make sure to provide the correct landline number, mobile number and email address Depending on the level of reserves, the final confirmation notice may also be the first and only notice for de-loading should a large power plant unexpectedly breaks down. This will be an emergen

  11. Slide 11: Steps to Implementing ILP: Activation

    5 Steps to Implementing ILP Notification 2 : Participants choose between 2 de- loading windows that capture morning and afternoon Activation peaks: Determination of Compensable kWh Billing Participants can also choose the “flexible” option for Settlement possible de-loading in the morning and/or aft

  12. Slide 12: Activation Reminders

    Activation Reminders If you are unable to continue de-loading Always ensure ample fuel supply during the prescribed de-loading hours, please notify MERALCO’s ILP hotline (1622-8118) immediately and indicate: De-load immediately once instructed (1)reason for inability to continue de- by MERALCO loadi

  13. Slide 13: Steps to Implementing ILP: Determination of Compensable kWh

    5 Steps to Implementing ILP Notification 3 DETERMINATION OF COMPENSABLE KWH: MERALCO will read consumption meters of participating accounts at Activation the same time as the usual reading for billing & tag hours of ILP activation Determination of Compensable kWh Billing Settlement 13

  14. Slide 14: BCQ Re-declaration Timeline

    BCQ Re-declaration Timeline Computation of Confirmation or BCQ Re- ILP Activation [D] Compensable kWh Compensable kWh Declaration [D+7] [D+4] [D+6] • At the end of each • MERALCO shall: (i) read • RES shall: (i) validate with • GenCo shall re-declare its activation, MERALCO consumption meters at its

  15. Slide 15: Steps to Implementing ILP: Billing

    5 Steps to Implementing ILP Notification 4 : MERALCO will compute Activation the De-loading Compensation based on the ERC-prescribed formula and send to the Participating Captive Customer for verification within 7 Determination of business days from the regular Compensable kWh reading date. For the

  16. Slide 16: Billing and Compensation (Amendments)

    Billing and Compensation (Amendments) E J@@& [Incremental = De-loading Rate x + Maintenance Cost Compensable kWh] De-loading Compensationyesos Where: incremental De-loading _ [Generation Cost ofFuelx _ PC Average rate Rate Fuel Consumption Rate] Average price of diesel fuel from Petron, Shell and Ca

  17. Slide 17: Sample Computation

    Sample Computation Captive RES / Contestable Generation Cost of Fuel, PhP/kWh 22.10 22.10 Average diesel pump price, PhP65/L 3.10 10.10 DWS: includes transmission, system loss, Average Rate, PhP/kWh All-in Rate distribution, supply, metering and other non-bypassable charges Incremental De-loading Ra

  18. Slide 18: Steps to Implementing ILP: Settlement

    5 Steps to Implementing ILP Notification 5 Activation : The signed conforme letter must be returned by the Participating Captive Customer to MERALCO within 3 business days from receipt, and by the RES to Determination of MERALCO within 2 business days from receipt. Compensable kWh Upon receipt of th

  19. Slide 19: Billing & Settlement Reminders

    Billing & Settlement Reminders • For Participating Captive Customers, submit necessary documents (e.g., BIR Certificate of Registration) upon enrollment to avoid delays in processing of payment. Upon MERALCO’s payment of the De-loading Compensation, the Participating Captive Customer shall issue to

  20. Slide 20: Join the ILP! Update your participation details!

    Join the ILP! Update your participation details! 20

  21. Slide 21: Switching?

    Switching? Finalize the tripartite ILP agreement with your Retail Electricity Supplier (RES) to participate! 21

  22. Slide 22: Thank you!

    Thank you!