Manila Electric — Investor Presentation (2025)

47 slides from Manila Electric's investor presentation, Nov 28, 2025

  1. Slide 1: Customer Choice Programs (CCP)

    Slide 1: Customer Choice Programs (CCP)

    CUSTOMER CHOICE PROGRAMS (CCP)

  2. Slide 2: Customer Choice Programs (CCP)

    Slide 2: Customer Choice Programs (CCP)

    Customer Choice Programs (CCP) The Electric Power Industry Reform Act (EPIRA) or RA 9136 mandates the government to promote retail competition, ensure customer choice, advocate the use of Renewable Energy (RE) resources, and institutionalize energy efficiency and conservation. Through the Customer C

  3. Slide 3: Customer Choice Programs (CCP)

    Slide 3: Customer Choice Programs (CCP)

    Customer Choice Programs (CCP) CCP is composed of three (3) main programs: Competitive Retail Electricity Market Green Energy Option Program Retail Aggregation Program Program Allows eligible customers to choose their Allows consumers to choose 100% renewable Allows two or more end-users, or all end

  4. Slide 4: Customer Choice Programs eligibility criteria

    Slide 4: Customer Choice Programs eligibility criteria

    Customer Choice Programs (CCP) Customers must meet the following criteria to be eligible to switch to the Customer Choice Programs: Competitive Retail Electricity Market Green Energy Option Program Retail Aggregation Program Program • Existing end-users with an average • Existing end-users with a mo

  5. Slide 5: Benefits of CCP

    Slide 5: Benefits of CCP

    Benefits of CCP CCP empowers consumers with “The Power of Choice” with the freedom to select their preferred electricity supplier. COMPETITIVE RETAIL GREEN ENERGY RETAIL AGGREGATION ELECTRICITY MARKET OPTION PROGRAM PROGRAM Encourages higher efficiency and Supplies energy that is from 100% Ensures t

  6. Slide 6: Industry players

    Slide 6: Industry players

    Industry players POLICY MAKERS/REGULATORS POWER INDUSTRY END-USERS Department of Energy Regulatory Eligible end-user Energy Commission Generation Companies The most important player in the retail market ▪ Supervises restructuring of ▪ Promotes competition, the electricity industry among others ▪ For

  7. Slide 7: Electricity Supply Chain

    Slide 7: Electricity Supply Chain

    Electricity Supply Chain Captive End-User The DU is my power provider. GENERATION TRANSMISSION DISTRIBUTION (DU) Generation Companies or The DU procures energy from the GenCos NGCP transfers power from GenCos supply power via and/or Wholesale Electricity Spot Market GenCos to the DU Transmission Lin

  8. Slide 8: Switching to the Retail Market: CREM & GEOP

    Slide 8: Switching to the Retail Market: CREM & GEOP

  9. Slide 9: STEP 1: Check if you are qualified

    Slide 9: STEP 1: Check if you are qualified

    STEP 1: Check if you are qualified CRITERIA CREM GEOP • Existing end-users with an average monthly peak • Existing end-user with a monthly average peak demand of ≥ demand of 500 kW for the past twelve (12) months. 100 kW for the past twelve (12) months. • New end-users with forecasted monthly peak •

  10. Slide 10: STEP 2: Choose a Retail Electricity Supplier

    Slide 10: STEP 2: Choose a Retail Electricity Supplier

    STEP 2: Choose a Retail Electricity Supplier Eligible End-Users may choose from different Retail Suppliers in the market; however, make sure to contact only ERC-licensed Retail Suppliers. For GEOP, with DOE-issued Operating Permit. For the list of Retail Electricity Suppliers, visit: CREM GEOP https

  11. Slide 11: CREM and GEOP Switching Timeline

    Slide 11: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 90 Calendar Days 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days Days from Days Prior Days Prior Days Prior TARGET Before Target Switch Prior Target Submission of Target Switch Target Switch Target Switch SWITCH DATE Date Switch Date Letter of Intent D

  12. Slide 12: CREM and GEOP Switching Timeline

    Slide 12: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 90 Calendar Days 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days Days from Days Prior Days Prior Days Prior TARGET Before Target Switch Prior Target Submission of Target Switch Target Switch Target Switch SWITCH DATE Date Switch Date Letter of Intent D

  13. Slide 13: CREM and GEOP Switching Timeline

    Slide 13: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days 90 Calendar Days Before Days from Days Prior Days Prior Days Prior TARGET Prior Target Target Switch Date Submission of Target Switch Target Switch Target Switch SWITCH DATE Switch Date Letter of Intent D

  14. Slide 14: CREM and GEOP Switching Timeline

    Slide 14: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days 90 Calendar Days Before Days from Days Prior Days Prior Days Prior TARGET Prior Target Target Switch Date Submission of Target Switch Target Switch Target Switch SWITCH DATE Switch Date Letter of Intent D

  15. Slide 15: CREM and GEOP Switching Timeline

    Slide 15: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days 90 Calendar Days Before Days from Days Prior Days Prior Days Prior TARGET Prior Target Target Switch Date Submission of Target Switch Target Switch Target Switch SWITCH DATE Switch Date Letter of Intent D

  16. Slide 16: CREM and GEOP Switching Timeline

    Slide 16: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days 90 Calendar Days Before Days from Days Prior Days Prior Days Prior TARGET Prior Target Target Switch Date Submission of Target Switch Target Switch Target Switch SWITCH DATE Switch Date Letter of Intent D

  17. Slide 17: CREM and GEOP Switching Timeline

    Slide 17: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days 90 Calendar Days Before Days from Days Prior Days Prior Days Prior TARGET Prior Target Target Switch Date Submission of Target Switch Target Switch Target Switch SWITCH DATE Switch Date Letter of Intent D

  18. Slide 18: CREM and GEOP Switching Timeline

    Slide 18: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days 90 Calendar Days Before Days from Days Prior Days Prior Days Prior TARGET Prior Target Target Switch Date Submission of Target Switch Target Switch Target Switch SWITCH DATE Switch Date Letter of Intent D

  19. Slide 19: CREM and GEOP Switching Timeline

    Slide 19: CREM and GEOP Switching Timeline

    CREM and GEOP Switching Timeline 30 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days 90 Calendar Days Before Days from Days Prior Days Prior Days Prior TARGET Prior Target Target Switch Date Submission of Target Switch Target Switch Target Switch SWITCH DATE Switch Date Letter of Intent D

  20. Slide 20: 7 Working Days Switching Timeline

    Slide 20: 7 Working Days Switching Timeline

    7 Working Days Switching Timeline • Carefully plan your switch to any Customer Choice Programs prior to completing submissions • Supplier shall submit switch notification to CRB not later than seven (7) working days prior to the proposed effectivity date Switch notification Supplier to comply CRB in

  21. Slide 21: Switching to the Retail Market: RAP

    Slide 21: Switching to the Retail Market: RAP

  22. Slide 22: STEP 1: Check if you are qualified

    Slide 22: STEP 1: Check if you are qualified

    STEP 1: Check if you are qualified End-users not yet meeting the prevailing threshold set by the ERC for the CREM may form an Aggregated Group and participate in the RAP, subject to the following: • Aggregated average monthly peak demand of the Aggregated Members, for the preceding three (3) months

  23. Slide 23: STEP 1: Sample computation of aggregated peak demand

    Slide 23: STEP 1: Sample computation of aggregated peak demand

    STEP 1: Check if you are qualified S A M P L E C O M P U TAT I O N How to find your Aggregated Average Monthly Peak Demand Sample Computation Service ID Average KW Oct-24 Nov-24 Dec-24 Number from Oct-Dec (SIN) (kW) (kW) (kW) (kW) A 200 250 300 250 B 200 300 400 300 Aggregated average monthly peak d

  24. Slide 24: STEP 2: Choose a Retail Aggregator

    Slide 24: STEP 2: Choose a Retail Aggregator

    STEP 2: Choose a Retail Aggregator Eligible End-Users may choose from different Retail Aggregators in the market. Make sure to contact only ERC-licensed Retail Suppliers, and Retail Aggregators with Authority to Aggregate from ERC. For the list of Retail Electricity Suppliers, visit: RAP: Retail Ele

  25. Slide 25: RAP Switching Timeline

    Slide 25: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  26. Slide 26: RAP Switching Timeline

    Slide 26: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  27. Slide 27: RAP Switching Timeline

    Slide 27: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  28. Slide 28: RAP Switching Timeline

    Slide 28: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  29. Slide 29: RAP Switching Timeline

    Slide 29: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  30. Slide 30: RAP Switching Timeline

    Slide 30: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  31. Slide 31: RAP Switching Timeline

    Slide 31: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  32. Slide 32: RAP Switching Timeline

    Slide 32: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  33. Slide 33: RAP Switching Timeline

    Slide 33: RAP Switching Timeline

    RAP Switching Timeline 90 Calendar Days 30 Calendar 60 Calendar 30 Calendar 16 Calendar 10 Calendar 7 Working Days from Days Prior Days Prior Days Prior Days Prior TARGET Before Target Switch Days from Submission of Submission of Target Switch Target Switch Target Switch Target Switch SWITCH DATE Da

  34. Slide 34: 7 Working Days Switching Timeline

    Slide 34: 7 Working Days Switching Timeline

    7 Working Days Switching Timeline • Carefully plan your switch to any Customer Choice Programs prior to completing submissions • Supplier shall submit switch notification to CRB not later than seven (7) working days prior to the proposed effectivity date Switch notification Supplier to comply CRB in

  35. Slide 35: After Switching to the Retail Market

    Slide 35: After Switching to the Retail Market

    - 47) MERALCO ~

  36. Slide 36: Knowing Your Load Requirement

    Slide 36: Knowing Your Load Requirement

    Knowing Your Load Requirement Consider the following to get the best supplier that fits you and your business’ needs and gives you the best value for money: 1. Learn about your power usage information 2. Know your consumption forecast 3. Know your Load Profile. You may request this from your DU, as

  37. Slide 37: Load profile data request fees

    Slide 37: Load profile data request fees

    • Requests for load profile data shall be subject to a fee amounting to P5,000, exclusive of 12% VAT. • Table 1 presents the schedule of applicable fees for load profile data requests. SCHEDULE OF APPLICABLE FEES FOR LOAD PROFILE DATA REQUESTS Load Profile Data Request Fee Load Profile Data Request

  38. Slide 38: After Switching to the Retail Market

    Slide 38: After Switching to the Retail Market

  39. Slide 39: Meralco's roles after you have switched

    Slide 39: Meralco's roles after you have switched

    Meralco’s roles after you have switched Distribution Utility (DU) / Network Service Provider (NSP) Metering Service Provider (MSP) Supplier of Last Resort (SoLR)

  40. Slide 40: Keeping You Connected: Billing, Payments, Service Modifications

    Slide 40: Keeping You Connected: Billing, Payments, Service Modifications

    KEEPING YOUConnected Keeping You CONNECTED Billing Payments Service Modifications • The Retail Customer shall receive one • Settle your electric bill in full to your • You may course your request for consolidated bill from the Retail Supplier or Retail Supplier. In cases of non- change in load and o

  41. Slide 41: Keeping You Connected: Concerns and Power Interruption

    Slide 41: Keeping You Connected: Concerns and Power Interruption

    KEEPING YOUConnected Keeping You CONNECTED Electricity Concerns Power Interruption • You may get in touch with the DU and the Retail • The DU will advise both Retail Customer and the Supplier/ Aggregator for your electricity concerns or Retail Supplier/ Aggregator of any pre-arranged issues. power i

  42. Slide 42: Reversion to the Captive Market

    Slide 42: Reversion to the Captive Market

    (I) MERALCO Reversion to ~ = the Captive - — Market

  43. Slide 43: Reversion to the Captive Market

    Slide 43: Reversion to the Captive Market

    Reversion to the Captive Market The Omnibus Rules allow Retail Customers to revert to the Captive Market only upon meeting the demand threshold requirements: PROGRAM DEMAND THRESHOLD REQUIREMENT Competitive Retail Average peak demand has decreased to less than 25% of prevailing CREM threshold for th

  44. Slide 44: MERALCO as Supplier of Last Resort

    Slide 44: MERALCO as Supplier of Last Resort

  45. Slide 45: Supplier of Last Resort (SoLR)

    Slide 45: Supplier of Last Resort (SoLR)

    Supplier of Last Resort ( SoLR) • As a Distribution Utility, MERALCO is designated by the ERC as the SoLR in its franchise area. • SoLR service is not a service provided to the captive market and is not a Retail Supplier service provided by the DU. Who is my • It is intended to be a temporary servic

  46. Slide 46: Supplier of Last Resort (SoLR)

    Slide 46: Supplier of Last Resort (SoLR)

    Supplier of Last Resort ( SoLR) As a SoLR customer of MERALCO, generation rates shall be based on Wholesale Electricity Spot Market (WESM) nodal energy price or bilateral contract price, whichever is applicable, and a 5% premium to cover for the incremental administrative and overhead expenses relat

  47. Slide 47: Contact Us

    Slide 47: Contact Us

    Contact Us To learn more about Customer Choice Programs and switch-related procedures, get in touch with us via the following: CUSTOMER SEGMENT EMAIL HOTLINE Residential customercare@meralco.com.ph (02) 16110 Biz biz@meralco.com.ph (02) 16211 enterprise@ meralco.com.ph Enterprise & Nat Gov (02) 1621