Future Mineral Resources Inc. · TSX:FMR
Future Mineral Resources — Sulliden Gold — Investor Presentation (April 2014)
34 slides from Future Mineral Resources's investor presentation, April 2014

Slide 1: The Shahuindo Gold Project
TSX & BVL: SUE OTCQX: SDDDF The Shahuindo Gold Project Low-cost heap leach project in Peru with a clear path to production Investor Presentation, April 2014

Slide 2: Cautionary Statement
Cautionary Statement This presentation may include certain “forward-looking statements” within the meaning of applicable Canadian securities legislation. All statements, other than statements of historical fact, included herein, including, without limitation, statements regarding future plans and ob

Slide 3: Sulliden at a Glance
Sulliden at a Glance Near-term gold production in excellent mining jurisdiction Quick Facts The Shahuindo Project: a simple open-pit, heap leach mine Asset Shahuindo Project Located in a low cost gold-producing district in northern Peru Location Cajamarca, Peru Currently in advanced stages of pe

Slide 4: Project Location & Infrastructure
Project Location & Infrastructure 4

Slide 5: Peru: A Thriving Mining Country
Peru : A Thriving Mining Country 1. China 2. Australia 3. USA Peru is among 4. South Africa Gold producer the top 10 gold 5. Russia #1 in Latin America producers in the world: 6. Peru 7. Ghana Gold producer 8. Canada #6 in the world 9. Indonesia Silver producer 10. Mexico #2 in the world Copper prod

Slide 6: Shahuindo Gold & Silver Project
Shahuindo Gold & Silver Project Located in a low cost mining district Safe and friendly mining jurisdiction Stable and functioning democracy Located in a prolific gold belt Lagunas Norte and Yanacocha are two of the 10 lowest cost mines in the world¹ Access to trained and educated workforc

Slide 7: Shahuindo Infrastructure
Shahuindo Infrastructure Excellent location & accessibility 7

Slide 8: Current Mineral Resources & Exploration Potential
Current Mineral Resources & Exploration Potential 8

Slide 9: Gold Mineral Resource Growth
Gold Mineral Resource Growth Only approximately 150,000 m drilled on property Measured & Indicated (M&I) Mineral Resources Inferred Mineral Resources 3,000,000 2009 2011 2012 2,500,000 2.44 M 2,000,000 1.97 M 1.63 M M&I gold mineral resources: 1,500,000 1.44 M 2,438,000 ounces Inferred gold mineral

Slide 10: Silver Mineral Resource Growth
Silver Mineral Resource Growth Only approximately 150,000 m drilled on property Measured & Indicated (M&I) Mineral Resources Inferred Mineral Resources 60,000,000 2009 2011 2012 50,000,000 46.6 M 40,000,000 38.6 M 33.4 M M&I silver mineral resources: 30,000,000 29.8 M 28.0 M 33,370,000 ounces Inferr

Slide 11: Shahuindo Mineralization
Shahuindo Mineralization Continuous ore body outcropping on surface Section E1050 (featured on next slide) Easily accessible mineralization A single pit for Section centered on a 200 m thick base line Phase 1 & 2 of project Low strip ratio of 1.97: 1 (Feasibility Study, Sept 2012) UNDRILLED UN

Slide 12: Typical Cross Section (E1050)
Typical Cross Section (E1050) Large disseminated gold deposit at surface 12

Slide 13: Numerous Targets Remain Unexplored
Numerous Targets Remain Unexplored Excellent mineral growth potential Defined Mineral Resource Geochemical Footprint 13

Slide 14: Shahuindo Mine Overview
Shahuindo Mine Overview 14

Slide 15: Straightforward, Low-Risk Mining
Straightforward, Low-Risk Mining Open Pit 1 Mine 100 m - Conveying - Agglomerating - Stacking 3 ADR Plant Heap Leach 2 Processing Carbon in Column Gold Recovery Plant Preg Pond Barren Pond Carbon Stripping/Reactivation 15

Slide 16: Feasibility Study Results
Feasibility Study Results September 2012 Low Cost, Open Pit, Excellent production growth potential: Heap Leach Operation Near Term Tonnes per day mined 10,000 tpd Mineral Reserves represent only about 40% of gold ounces from total oxide mineral resource Gold Eq. Production +/- 90,000 oz/year Long Te

Slide 17: Mine Infrastructure Layout
Mine Infrastructure Layout Feasibility Study (September 2012) 10k tonne-per-day mine Small footprint Conveyor belts and ADR plant sized to accommodate future expansion Projected Mine Expansion Similar infrastructure footprint Easily expandable to accommodate a larger project and future min

Slide 18: Attractive Economics
Attractive Economics Comparable gold oxide projects Company, Technical Au IRR IRR Annual Mine Cash CAPEX Project & Location Report Price (Pre-Tax) (Post-Tax) Production Life Costs/oz. Sulliden Gold, Feasibility Study $1,300 45.6% 33.0% 87,700 oz. 10 yrs $541 $131.8 M Shahuindo, Peru (Sept. 26, 2012)

Slide 19: Low Cost Project vs. Major Gold Producers
Low Cost Project Shahuindo is located among some vs. Major Gold Producers of the lowest cost mines in the world Average all-in Sulliden’s Shahuindo Project: All-in costs*: costs in 2013*: $552/oz; 0.84 g/t (FS, Sept 2012) Buenaventura & Southern $826/oz $1,086/oz Peru Copper’s Tantahuatay: ~$360/oz;

Slide 20: Shahuindo Development Schedule
Shahuindo Development Schedule 20

Slide 21: Permitting Status
Permitting Status Completed EIA Document Construction Components 2nd round Completion of electrical Baseline Studies of official substation construction Feasibility Study community Final Public expected in H2 2014 Impact Analysis & workshops Audience EIA Approval Mine construction Manageme

Slide 22: Successful Final Audience
Successful Final Audience Important step in the EIA Process Completed on March 13, 2013 Over 2,500 attendees; Strong social support 22

Slide 23: Electrical Substation Progress
Electrical Substation Progress Electrical substation construction permit received in April 2013 Completion expected in 2014 23

Slide 24: Recent & Upcoming Milestones
Recent & Upcoming Milestones Recent Milestones The Path Forward… Strategic investment by Completion of land surface rights acquisitions Agnico Eagle Mines Ltd. (April 2013) Submission and receipt of remaining Environmental approval and process permits and authorizations construction permit f

Slide 25: Shahuindo Social Programs
Shahuindo Social Programs Sulliden plays an active role in the sustainable development of the communities surrounding its project 25

Slide 26: Local Training Programs
Local Training Programs In partnerships with: Initiated in October 2012 Sulliden has partnered with recognized Peruvian training institutions to provide training programs in: Masonry, Ironworks, Electrical Wiring & installations, Front end loader operation, Excavator Operator, Welding, Cooking a

Slide 27: Sembrando Oportunidades Locales (SOL)
Sembrando Oportunidades Locales (SOL) In partnerships with: Initiated in March 2014, as part of the training program The pilot Chef Training course if offered to the “Club de Madres” (Mother’s Club) of the nearby town of San Jose. 27

Slide 28: Agriculture Cooperative
Agriculture Cooperative Ex: ”COEVAC” Avocado Project Initiated in 2013, the aim of the COEVAC cooperative is to help improve farming practices The cooperative is composed of farmers and entrepreneurs in the nearby Condebamba Valley The pilot avocado project enabled the trade of avocados to the

Slide 29: Appendices
”n ® = a) = ® 2. 2. <x

Slide 30: Corporate Structure & Research
Corporate Structure & Research Toronto, Canada Lima, Peru United States Trading Symbols: TSX: SUE BVL: SUE OTCQX: SDDDF Capitalization Summary: Research Coverage Shares Outstanding 310.3M Warrants 18.9M Steve Parsons Options 26.5M Fully Diluted 355.7M Chris Thompson Andrew Kaip Stock Performance: Sh

Slide 31: Sulliden Management & Board
Sulliden Management & Board Proven Management Team Peter Tagliamonte, P.Eng. MBA, Chief Executive Officer & Chairman 30 yrs of experience in mine building and operations with particular focus in Central and South America Former CEO of Central Sun Mining and COO of Desert Sun Mining Justin Reid,

Slide 32: NI 43-101 Mineral Resources
NI 43-101 Mineral Resources September 2012 Gold Gold Silver Silver Gold Contained Grade Contained Grade Tonnes (t) Grade Ounces (g/t) Ounces (g/t) Eq.g/t Total Measured & Indicated 2,438,000 0.52 33,370,000 7.1 147,310,000 0.54 Mineral Resources Measured Mineral Resources Oxide (Reported at 0.2 g/t

Slide 33: NI 43-101 Mineral Reserves
NI 43-101 Mineral Reserves September 2012 Mineral Reserves represent only approximately 40% of the gold ounces from total oxide mineral resource Gold Gold Silver Silver Gold AuEq contained grade contained grade Tonnes (t) grade Ounces (ounces) (g/t) (ounces) (g/t) Eq.g/t Total P&P 1,022,000 0.84 11,

Slide 34: info@sulliden.com www.sulliden.com
Sulliden Gold Corporation Ltd. 65 Queen St W, Ste 800, Toronto, Ontario M5H 2M5 Investor Relations TSX (Toronto): SUE info@sulliden.com BVL (Lima): SUE +1 (416) 861-5805 OTCQX (US): SDDDF Stay connected for the latest developments: www.sulliden.com 34
Source: Internet Archive copy of sulliden.com
More decks from Future Mineral Resources Inc.
Investor Presentation (July 2026)18 slides · July 2026
Sulliden Mining Capital — Fact Sheet (June 2017)2 slides · June 2017
Sulliden Mining Capital — Investor Presentation (May 2016)27 slides · May 2016
Sulliden Mining Capital — Fact Sheet (April 2016)2 slides · April 2016
Sulliden Mining Capital — Investor Presentation (March 2016)24 slides · March 2016
Sulliden Mining Capital — Investor Presentation (September 2014)12 slides · September 2014