Stora Enso Oyj Class A · OMXHEX:STEAV
Stora Enso Oyj Class A — Forest field trip (June 2024)
8 slides from Stora Enso Oyj Class A's conference presentation, Jun 5, 2024
Slide 1: Stora Enso Wind power
5 June 2024 Stora Enso Wind power Emil Thalin Director, Energy Development
Slide 2: Why wind power?
Why wind power? Stora Enso Demand for electricity in Sweden will grow First turbine rapidly. Forecasts point at a 100% increase to installed in 2007 ~300 TWh/year by 2040. Onshore wind power will play a crucial role in ~90 turbines meeting this demand. Access to suitable land is a key success factor
Slide 3: Emerging wind power opportunities
Emerging wind power opportunities Our ambition is to 20 TWh potential Aiming for develop and for wind power 5–10 TWh significantly production on Stora wind power increase our Enso’s land in production ramping involvement in wind Sweden up from 2030→ energy
Slide 4: We are developing wind power through three project types
We are developing wind power through three project types Land-lease projects Project development Partner projects Project developers lease Stora Develop and sell our own Develop and sell projects with Enso land to develop projects projects with our own personnel partners. Risk, cost and profit thems
Slide 5: Wind power process
Wind power process – from identification of potential areas to running operations 5–10 years Due to legal processes related to permits 2 years Permit Permit Detailed Investment Investigations Consultation application appeal Procurement Construction Operation engineering decision and EIA process Our
Slide 6: The future is built on renewable energy
The future is built on renewable energy • Onshore wind power is the only available power production to be built in the short term. • Onshore wind power always requires access to large land areas. • Current land-lease contracts continue to generate stable rental income • By focusing on new permits to
Slide 7: The renewable materials company
The renewable materials company
Slide 8: sal
sal StoraEnso,