  1. Slide 1: Copper, Nickel & Precious Metal Production Growth in Sudbury

    www.magnamining.com TSXV: NICU OTC: MGMNF c COPPER, NICKEL & PRECIOUS METAL PRODUCTION GROWTH IN SUDBURY, NORTH AMERICA’S PREMIER MINING DISTRICT January 2026

  2. Slide 2: Cautionary Statements

    CAUTIONARY STATEMENTS Cautionary Statement Regarding Forward-Looking Information This presentation contains forward-looking information and forward-looking statements (collectively, "forward-looking statements") within the meaning of applicable securities laws. All statements, other than statements

  3. Slide 3: The Sudbury Advantage

    THE SUDBURY ADVANTAGE OVER 100 YEARS OF MINING WORLD CLASS MINERAL ENDOWMENT INFRASTRUCTURE & PROCESSING FACILITIES LOW-COST ACCESS TO EXPLORATION & DEVELOPMENT SOCIAL LICENSE TO OPERATE

  4. Slide 4: Magna Mining – Pillars of Growth

    MAGNA MINING – PILLARS OF GROWTH PRODUCTION SYNERGISTIC EXPLORATION 0 ACQUISITIONS • Currently one producing copper mine (McCreedy West) • Experienced Sudbury exploration team • Track record of acquiring accretive projects in Sudbury • Four permitted, past producing mines • Track record of making si

  5. Slide 5: Capital Structure and Equity Performance

    CA P ITA L S T R U C T U R E EQUITY PERFORMANCE C U R R E N T CA P I TA L ST R U CT U R E (TSXV: NICU ) $4.00 Retail 7 Issued & Outstanding 249,858,803 ~37% $3.50 6 $3.00 5 Volume (Millions) $2.50 Options, RSUs & DSUs 13,485,570 4 Price (C$) $2.00 3 $1.50 2 Warrants 0 $1.00 $0.50 1 $-- -- Jan-23 Aug

  6. Slide 6: Sudbury – A World Class Mining District

    SUDBURY – A WORLD CLASS MINING DISTRICT ~200km to Timmins PODOLSKY LEVACK Glencore McCREEDY WEST Strathcona Mill Glencore Levack Falconbridge Smelter Chelmsford Vale Clarabelle Mill Vale Copper Cliff Smelter SHAKESPEARE City of Sudbury Whitefish Wanup Nairn CREAN HILL Magna Property Massey ~400km to

  7. Slide 7: Magna Mining's Production Pipeline

    MAGNA MINING’S P R O D U C T I O N PIPELINE Pipeline of projects: Magna now has a portfolio of low capex, brownfield or past producing assets that can provide a platform for Production McCREEDY WEST significant production growth for the next 5 years LEVACK Bootstrapped production plan: Staggered pro

  8. Slide 8: McCreedy West & Levack Properties

    McCREEDY WEST & LEVACK PROPERTIES Vale Coleman Mine Glencore Strathcona Mill Glencore Fraser Mine Levack #2 Shaft McCreedy West Portal Glencore Levack Hardy Mine Townsite Glencore Craig Mine (Onaping Depth Project) Glencore Onaping Mine

  9. Slide 9: McCreedy West Mine

    McCREEDY WEST MINE Administrative Complex Security Portal Ore Sorter Crusher, Sample Tower, Shipping

  10. Slide 10: McCreedy West Mine

    McCREEDY WEST MINE Current production is from the 700 FW Cu Zone Optionality to restart nickel production from the Intermain Nickel Zone Development and exploration initiatives will focus on the area to the west of the 700 FW Zone towards the historical Hardy mine (Glencore)

  11. Slide 11: McCreedy West – 2026 Production Plans

    McCREEDY WEST – 2026 PRODUCTION PLANS Isometric Looking North Portal Scale 300 Ft Green – Planned Development 930 West Area Orange – Planned Cu Stopes 930 – 1250 Area 1250 West Area Recent high-grade intercepts drilled by Magna (highlighted above) outside of the stopes designed by prior operators su

  12. Slide 12: Levack Mine

    L E VA C K MINE Administration Security Levack #2 Shaft Building Vale Coleman Core Shack Mine Proposed Portal Glencore Strathcona Mill Sample Tower Backfill Plant Glencore Onaping Depth Project

  13. Slide 13: Levack Mine

    LEVACK MINE Conceptual MLV-25-21 2.3% Ni, 0.7% Cu over 28.0m Including Ramp From 6.6% Ni, 0.7% Cu, over 2.4m And 3.3% Ni, 1.0 % Cu over 12.4 m Surface MLV-25-22 2.4% Ni, 0.8% Cu, over 15.5m And 3.2% Ni, 2.2% Cu over 2.4 m Main Ni- Keel Cu-PGE Cu Zone Footwall No. 1 & No. 2 Zone Ni-Cu Zones No. 3 Ni-

  14. Slide 14: Levack Mineral Resource Estimate

    LEVACK MINERAL R E S O U R C E ESTIMATE1 Cu Ni Co Pt Pd Au Ag CuEq Deposit Type Category Cut-off Grade Short Tons Metric Tonnes % % % (g/tonne) (g/tonne) (g/tonne) (g/tonne) % Contact Indicated 2.00% CuEq 6,535,000 5,928,000 0.89 1.41 0.05 0.46 0.56 0.07 0.99 3.18 Footwall Indicated 2.50% CuEq 197,0

  15. Slide 15: Morrison Footwall Deposit at Levack

    MORISSON FOOTWALL DEPOSIT AT LEVACK Magna Mining COO Jeff Huffman in a CEO Jason Jessup and COO Jeff Huffman in Morrison Deposit mechanized cut & fill stope footwall copper stope at McCreedy West in a captive cut & fill stope in the Morrison circa 2010 2010 Deposit in 2011 15 Photo credits: Steve Cl

  16. Slide 16: Levack Footwall – Exploration Target Areas

    LEVACK FOOTWALL – EXPLORATION TARGET AREAS The “R2” target area exhibits many mineral and metallurgical similarities to the top of the adjacent Morrison deposit High nickel and PGE grades seem to be transitioning into very high-grade copper and precious metals Exploration is ongoing with two surface

  17. Slide 17: Crean Hill Mine

    C R E A N H I L L M ICNREE A N H I L L M I N E Water Victoria Mine Treatment Plant (KGHM) (500m) Outcrop of 109 FW Main Access Road Waste Rock Proposed Portal Stockpile Location 2024 109 FW Bulk Sample Location Historical Main Pit (Filled)

  18. Slide 18: Crean Hill Mine

    CREAN HILL MINE 2024 PEA outlined a 13 year, 2,200 tonne per day operation with LOM mineable resource sales of 195.5 million pounds nickel, 169.5 million pounds copper, 313,000 oz platinum, 359,000 oz palladium, and 117,000 oz gold Pre-Feasibility Study underway with completion in Q3 of 2026

  19. Slide 19: Podolsky Mine

    P O D O L S K Y MINE Administration Building Security 2000 Deposit Shaft Waste Water Treatment Plant North Zone Portal

  20. Slide 20: Podolsky North Zone

    PODOLSKY NORTH ZONE SW NE Main Shaft Portal Whistle Pit North Zone Contact Ni Zones FNX4199 17.8 % Cu, 1.4% Ni, FNX4400 10.2 g/t Pt+Pd+Au 1.0 Ni, 0.2% Cu, over 7.0 m over 103.7 m Gabbro FNX4205 Zone 21.0 % Cu, 0.7% Ni, 15.9 g/t Pt+Pd+Au FNX40238 over 6.6 m 23.4 % Cu, 1.2% Ni, 12.9 g/t Pt+Pd+Au over

  21. Slide 21: Upcoming Catalysts

    UC UP PC OOMM I NI N GGCCAAT TAALLYYSSTTSS NEAR TERM LEVACK EXPLORATION RESULTS - FOOTWALL TARGETS NI 43-101 MINE RESERVES - McCREEDY WEST Q4 PRODUCTION RESULTS FROM McCREEDY WEST POTENTIAL SYNERGISTIC ACQUISITIONS

  22. Slide 22: Mining for Our Future

    MINING FOR OUR FUTURE TSXV: NICU OTCQX: MGMNF Jason Jessup, CEO Paul Fowler, Executive Vice President www.magnamining.com Jason.Jessup@magnamining.com Paul.Fowler@magnamining.com

  23. Slide 23: Management

    MANAGEMENT Jason Jessup, MBA – Chief Executive Officer & Director Jason has over 25 years of experience in the mining industry comprising operations management, corporate development and project evaluation. Formerly FNX Mining, Sandstorm Gold, Premier Royalty, and INCO. Paul Fowler, CFA – Executive

  24. Slide 24: Directors and Strategic Advisors

    DIRECTORS AND STRATEGIC ADVISORS V e r n B a k e r , P .E n g . , M B A C h a i r m a n Vern has +30 years of experience in the mining sector. He was most recently the CEO of Jaguar Mining (TSX: JAG) and previously served as General Manager of Goldcorp’s Cerro Negro Mine, as well as VP Operations at

  25. Slide 25: McCreedy West – Q3 2025 Summary

    McCREEDY WEST – Q3 2025 S U M M A R Y Q3 2025 Operating & Financial Results July – September 2025 (“Q3”) was the second full quarter of production from the McCreedy West copper mine under Magna’s operation. During the quarter 75,215 tons of ore were processed from the 700 Footwall Copper Zone at an

  26. Slide 26: H2 Operational Guidance

    H2 O P E R AT I O N A L GUIDANCE H2 2025 OPERATIONAL GUIDANCE 1 Prices are in CAD unless otherwise stated Q3 2025 Q4 2025 700 Copper Zone Ore Tons Sold 80,000 - 92,000 80,000 - 92,000 Copper Equivalent Grade Contained 2.90% - 3.40% 3.80% - 4.40% Copper Equivalent Payable Pounds (000s) 3,500 - 4,200

  27. Slide 27: Sudbury Property Portfolio

    SUDBURY PROPERTY PORTFOLIO ~200km to Timmins RAND PARKIN NORTHWEST FOY NORTH RANGE PODOLSKY FROST LAKE LEVACK Capreol BLEZARD Glencore Strathcona Mill KIRKWOOD McCREEDY WEST Levack Glencore Falconbridge Smelter Chelmsford FALCONBRIDGE FOOTWALL TRILL Vale Clarabelle Mill Vale Copper Cliff Smelter SHA

  28. Slide 28: Sudbury Geology – Impact Structure

    SUDBURY GEOLOGY – IMPACT STRUCTURE Source: https://craterexplorer.ca/sudbury-impact-structure-geomorphology/

  29. Slide 29: Sudbury Geology – Composite Cross Section

    SUDBURY GEOLOGY – C O M P O S I T E CROSS SECTION SUDBURY BRECCIA Contact-type NICKEL-COPPER deposit Footwall-type Sudbury Igneous Complex COPPER-PRECIOUS METALS (SIC) deposit Source: https://www.researchgate.net/figure/Composite-cross-section-showing-the-geological-settings-for-North-and-East-Range

  30. Slide 30: FNX Historical Share Price

    FNX H I S T O R I C A L SHARE PRICE Source: Bloomberg & Company Filings

  31. Slide 31: Mineral Resource Estimates

    MINERAL R E S O U R C E ESTIMATES • 935 million lbs of copper Total Contained Metal in NI 43-101 Compliant • 936 million lbs of nickel Resources (Measured & Indicated) • 3.1 million ounces of precious metals (Pt, Pd + Au) • 3.4 billion lbs of copper equivalent (Cu Eq) Additional Contained Metal in H

  32. Slide 32: Historical Resources

    H I S T O R I C A L RESOURCES Historical Resources1 Ni Cu Co Pt Pd Au Ag Property Deposit Type Tonnes (%) (%) (%) (gpt) (gpt) (gpt) (gpt) Measured and Indicated Podolsky Contact 6,058,000 0.75 0.21 Podolsky Footwall 1,099,000 0.27 2.35 0 1.01 1.01 0.42 13.56 Kirkwood Contact 565,000 1.17 0.49 Total

  33. Slide 33: Notes on McCreedy West Resource Estimate and Historical Resources

    NOTES ON McCREEDY WEST RESOURCE ESTIMATE AND HISTORICAL RESOURCES McCreedy West Property Mineral Resource Estimate Notes: 1. The effective date of the McCreedy West Property Mineral Resource Estimate (MRE) is December 31, 2023. This is the close out date for the final mineral resource models and min

  34. Slide 34: Notes on Levack Resource Estimate

    NOTES ON LEVACK RESOURCE ESTIMATE Levack Mineral Resource Estimate Notes: 1. The effective date of the Levack Mine Mineral Resource Estimate (MRE) is August 31, 2025. This is the close out date for the final mineral resource models and mine out models (as-builts). 2. The mineral resources are report