  1. Slide 1: AusPozz Project – Better Low-Carbon Concrete

    For personal use only AusPozz Project Better Low-Carbon Concrete Noosa Mining Conference 24 July 2025 ASX: ZEO www.zeotech.com.au 1

  2. Slide 2: Disclaimer

    Disclaimer These Presentation Materials are for information purposes only. They do not comprise a prospectus, product The Company confirms that it is not aware of any new information or data that materially affects the information disclosure statement, or other offering document under Australian law

  3. Slide 3: What is AusPozz?

    What is AusPozz ? High-Reactivity Metakaolin (HRM) For personal use only 700-750°C Toondoon AusPozz Low-Carbon High-Purity Metakaolin High Performance Kaolin Concrete AusPozz High Reactivity Metakaolin • Metakaolin is a Manufactured Pozzolan - the secret of 2000-year-old Roman concrete1 • Used in mo

  4. Slide 4: AusPozz offers multiple technical advantages

    AusPozz offers multiple technical advantages Significantly lower carbon footprint and multiple performance benefits1 For personal use only Increased Reduced Strength Durability Shrinkage Concrete Cancer • 79% reduction in embodied carbon vs cement • Almost double the strength – less concrete • Bette

  5. Slide 5: AusPozz Preliminary Feasibility Study

    AusPozz Preliminary Feasibility Study Strong business case validated by robust technical and financial characteristics For personal use only  Nameplate production of 300,000 tpa $406m NPV 42% IRR AusPozz from Train 1, and the manufacturing site offers scope for Train The Project has delivered a rob

  6. Slide 6: Cashflow and Capital Expenditure

    Cashflow and Capital Expenditure Early cash flows from DSO Kaolin operations reduce the capital requirement to approx. $95m For personal use only Project Cashflow (Y1-Y5) 150 150 Capital Cost Summary1 A$M 100 100 Direct Cost $62.3 Indirect Cost $43.7 $million $million 50 50 Contingency (11%) $10.5 T

  7. Slide 7: Bundaberg Port – Strategically Compelling

    Bundaberg Port – Strategically Compelling Bundaberg Port offers transport optionality, utilities, and future renewables access For personal use only • LOI signed with Gladstone Port Corporation for a 7.88ha site at Bundaberg Port1 • State Development Area zoning with access to infrastructure, utilit

  8. Slide 8: Compelling Financials Driven by Simplicity

    Compelling Financials Driven by Simplicity Conventional cost-effective flowsheet underpinned by ultra-high purity natural kaolin For personal use only • Australia’s highest-grade known raw ore kaolin resource offers a cost-effective approach to high-reactivity metakaolin production, AusPozz , and a

  9. Slide 9: Toondoon Kaolin Project

    Toondoon Kaolin Project Australia’s highest-grade known raw ore kaolin resource held under an approved Mining Lease For personal use only • Approved Mining Lease (ML 80126) • Huge tenements footprint covering 28,000ha¹ • Company ownership of 682ha of freehold land • 10.9Mt JORC (Measured 4.03Mt, Ind

  10. Slide 10: AusPozz Project Future Expansion

    AusPozz Project Future Expansion Potential scope for future Train 2 expansion, further improving economics and Net Zero impact For personal use only Train 1 Potential Train 2 Approximately 8 ha Bundaberg Port area site provides the potential for future expansion AusPozz production to 600,000 tpa wit

  11. Slide 11: Early Cashflow Opportunity – DSO and Cosmetic Kaolin

    Early Cashflow Opportunity DSO and Cosmetic Kaolin MOU with one of the world's leading independent kaolin trading companies For personal use only MSI presents a fast-track revenue opportunity • MOU establishes the framework to negotiate • MoU signed in May 20251 with Jiangsu Mineral Sources Internat

  12. Slide 12: Market Opportunity - AusPozz

    Market Opportunity - AusPozz Legislated emission reduction targets set to drive demand for low-carbon concrete solutions For personal use only The Size of the Target Sector Collaboration Partner • Cement production – 8% of global CO2 emissions1 • Holcim Australia – MoU signed Oct 2024, offering futu

  13. Slide 13: Significant Carbon Emissions Avoided

    Significant Carbon Emissions Avoided Nameplate AusPozz production has a huge decarbonisation impact on the built environment For personal use only The application of the nameplate annual AusPozz production in low-carbon concrete would avoid carbon emissions by an estimated 229,800 tonnes CO₂-e per y

  14. Slide 14: Commercial Pathways

    Commercial Pathways Immediate low-carbon concrete market and medium-term low-carbon cement potential For personal use only First Quarter 2026 Medium-Term Longer-Term Direct Shipping Ore (DSO) sales Produce and sell AusPozz Produce and sell AusPozz to blend with of kaolin raw ore for low-carbon concr

  15. Slide 15: Indicative Project Delivery Timetable

    Indicative Project Delivery Timetable1 Expansive Toondoon drilling program and forecast DSO Kaolin sales offer near-term value accretive milestones For personal use only Q4 2028 Q3 2028 AusPozzTM Stockpiling H1 2026 AusPozzTM and First Manufacturing Shipment Facility DFS Complete Constructed Q4 2025

  16. Slide 16: Corporate Overview

    Corporate Overview $120m $2.29m $0.065 1.85Bn 2.5c-10c For personal use only Market Cash at bank Share price Shares on issue 52-week range capitalisation (31 Mar 2025) Board & Management Sylvia Tulloch Peter Zardo Shane Graham Rob Downey James Marsh Non-Executive Chair Managing Director Executive Di

  17. Slide 17: For Further Information

    For Further Information James Marsh Chief Executive Officer For personal use only (+61) 7 3181 5523 james.marsh@zeotech.com.au Level 1, Brisbane Technology Park, 7 Clunies Ross Court, Eight Mile Plains, Queensland 4113, Australia Investor Relations Peter Taylor NWR Communications peter@nwrcommunicat