  1. Slide 1: Allied Gold 2024 Guidance and Outlook

    Slide 1: Allied Gold 2024 Guidance and Outlook

    ALLIED GOLD 2024 GUIDANCE AND OUTLOOK FEBRUARY 21, 2024 TSX: AAUC

  2. Slide 2: Disclaimers

    Slide 2: Disclaimers

    DISCLAIMERS Certain information, statements, beliefs and opinions in this presentation are forward-looking statements or forward-looking information, within the meaning of applicable Canadian securities legislation. All statements other than those of historical facts included in this presentation ar

  3. Slide 3: Value Creation Strategy: Focused on Optimizations and Growth

    Slide 3: Value Creation Strategy: Focused on Optimizations and Growth

    VALUE CREATION STRATEGY FOCUSED ON OPTIMIZATIONS AND GROWTH Established • Production increased in Q4 and H2 compared to H1 Sustainable • Produced 94,755 ounces of gold in Q4, contributing to a total of 343,817 ounces in 2023 Production Platform(1) • 2023 mine-site all-in sustaining cost (“AISC”) exp

  4. Slide 4: Value Creation Strategy: 2024 Production and Cost Guidance

    Slide 4: Value Creation Strategy: 2024 Production and Cost Guidance

    VALUE CREATION STRATEGY FOCUSED ON OPTIMIZATIONS AND GROWTH 2024 Production • Guiding for 2024 gold production of 375,000-405,000 ounces and Cost Guidance(1) • Mine-site AISC(2) expected to see year-over-year improvement of ~$185/oz • Areas of focus for 2024: - Delivering Improvements at Sadiola: An

  5. Slide 5: Value Creation Strategy: 2025 and 2026 Outlook

    Slide 5: Value Creation Strategy: 2025 and 2026 Outlook

    VALUE CREATION STRATEGY FOCUSED ON OPTIMIZATIONS AND GROWTH(1) 2025 and 2026 • Gold production to sequentially increase in 2025 with a further step-change in 2026 to >600,000 ounces, all Outlook at improving costs driven by: o Sadiola: Increase in production expected from additional oxide ore and Ph

  6. Slide 6: 2024 Guidance

    Slide 6: 2024 Guidance

    2024 GUIDANCE(1) Gold Production Cash Costs(2) Mine-Site All-in Sustaining Costs(2) 375,000 – $1,250/oz $1,400/oz 405,000 ounces Total Sustaining Expansionary Exploration Capital(3) Capital $32.0 million $29.5 million $198.5 million 2024 is set to deliver increased production at lower costs, while m

  7. Slide 7: 2024 Guidance by Mine

    Slide 7: 2024 Guidance by Mine

    2024 GUIDANCE BY MINE(1) Au Production (Au oz) Cash Costs (US$/oz)(2,3) Mine-Site AISC (US$/oz) (2,3) Sadiola 195,000 – 205,000 1,075 1,150 Bonikro 95,000 – 105,000 1,275 1,650 Agbaou 85,000 – 95,000 1,595 1,675 Total 375,000 – 405,000 1,250 1,400 (US$ millions) Sustaining Capital Expansionary Capit

  8. Slide 8: 2024 Guidance Insights

    Slide 8: 2024 Guidance Insights

    2024 GUIDANCE INSIGHTS(1) Insights • Increase in production driven by additional oxide ore feed at Sadiola and improved feed grades at Agbaou from the inclusion of Agbalé o High-end of guidance largely dependent on contractor transition at Agbaou • Mine-site AISC(2) reflects significant savings vers

  9. Slide 9: 2025 and 2026 Outlook

    Slide 9: 2025 and 2026 Outlook

    2025 AND 2026 OUTLOOK(1) EXPECTED OPERATING TRENDS THROUGH 2026 While not currently included in Allied's official one-year guidance, the operating outlook, based on our Mineral Reserves and which has upside through the drill bit, aligns with our strategic vision to deliver significant growth at subs

  10. Slide 10: Value Creation by Exploration

    Slide 10: Value Creation by Exploration

    VALUE CREATION BY EXPLORATION(1,2) • Allied's outlook and long-term strategy is underpinned by highly prolific geology and the company's track record of value creation through exploration • In 2023, we achieved significant milestones, generally and across these focus areas: o Added over 300koz to Mi

  11. Slide 11: 2023 Mineral Reserves and Mineral Resources Update

    Slide 11: 2023 Mineral Reserves and Mineral Resources Update

    2023 MINERAL RESERVES AND MINERAL RESOURCES UPDATE(1,2) • Grew Mineral Reserves by >300koz Au, or 2.8%, to 11.2Moz Au o Represents approximately 190% replacement of depletion o Reflects meaningful growth at Sadiola, Agbaou and Kurmuk, with partial replacement of mining depletion at Bonikro • Increas

  12. Slide 12: 2023 Mineral Reserves and Mineral Resources Update

    Slide 12: 2023 Mineral Reserves and Mineral Resources Update

    2023 MINERAL RESERVES AND MINERAL RESOURCES UPDATE(1,2) Change in Consolidated Mineral Reserves (Koz Au) Consolidated Mineral Reserves and Mineral Resources (December 31, 2023) Resources shown inclusive of Reserves (on a 100% basis) Tonnage Grade Content (Mt) (Au g/t) (Koz Au) Proven Reserves 47.1 1

  13. Slide 13: Sadiola Exploration Update

    Slide 13: Sadiola Exploration Update

    SADIOLA EXPLORATION UPDATE(1) Sadiola • Objective to support phased expansion, looking to improve upon of the base plan adding low-cost oxide ounces in the short term to increase cashflows • 2023 achievements • Identified Mineral Reserves and Mineral Resources at Diba • Replaced 187% of 2023 mining

  14. Slide 14: Côte d'Ivoire Exploration Update

    Slide 14: Côte d'Ivoire Exploration Update

    CÔTE D’IVOIRE EXPLORATION UPDATE(1) 2023 achievements • 25% increase in Mineral Reserves at Agbaou, representing 229% of 2023 depletion • Increased Measured & Indicated Mineral Resources at Bonikro by 28% Bonikro • Oume (Dougbafla prospects) • Established exploration camp to allow night shift operat

  15. Slide 15: Agbaou Updated Life of Mine Plan

    Slide 15: Agbaou Updated Life of Mine Plan

    AGBAOU UPDATED LIFE OF MINE PLAN(1,2) Average LOM mine-site AISC <$1,450/oz 95 - 105 95 - 105 ~110 85 - 95 100 100 65 2024E 2025E 2026E 2027E 2028E 2029E Reserve Based Production (koz Au) Conversion of Inferred & Exploration Targets (koz Au) • The 2024 LOM plan has increased the mine life from 2026

  16. Slide 16: Kurmuk Exploration Update

    Slide 16: Kurmuk Exploration Update

    KURMUK EXPLORATION UPDATE(1) • Dish Mountain Infill Drilling • Target upgrading Dish Mountain Inferred to Indicated within pit design • Access and rig deployment to Tsenge and field camp • Tsenge • Tsenge completed detailed mapping and targeting • 5,500 mapping observations • Detailed interpretation

  17. Slide 17: Kurmuk Project Update

    Slide 17: Kurmuk Project Update

    KURMUK PROJECT UPDATE(1) • Completed FEED optimization study a ten-year mine life based on Mineral Reserves, with production levels averaging 290,000 oz per year in the first five years and life of mine AISC(2) below $950 per ounce • Increased throughput from 4.4MT per year (2022 DFS) to 6.0Mt per y

  18. Slide 18: Maintaining Financial Flexibility

    Slide 18: Maintaining Financial Flexibility

    MAINTAINING FINANCIAL FLEXIBILITY(1) Allied plans to execute on a select number of non-dilutive alternatives to enhance the Company's financial flexibility as it advances its growth initiatives, including streams on producing assets and a gold prepay facility Given that equity markets, in our view,

  19. Slide 19: Significant Near-Term Growth with Longer-Term Upside

    Slide 19: Significant Near-Term Growth with Longer-Term Upside

    SIGNIFICANT NEAR-TERM GROWTH WITH LONGER-TERM UPSIDE(1) Mine-Site AISC Strategic Outlook (US$/oz)(2): Guidance Strategic Vision <1,585 1,400 <1,375 <1,225 <1,000 >700-800 >600 400-450 Meaningful growth expected from world 375-405 344 class assets with globally significant scale 2023A 2024E 2025E 202

  20. Slide 20: Closing Remarks

    Slide 20: Closing Remarks

    CLOSING REMARKS Arclies 19

  21. Slide 21: Appendix

    Slide 21: Appendix

    APPENDIX Arclies 20

  22. Slide 22: Appendix A: Mineral Reserves and Mineral Resources

    Slide 22: Appendix A: Mineral Reserves and Mineral Resources

    APPENDIX A MINERAL RESERVES AND MINERAL RESOURCES As of December 31, 2023 Proven Mineral Reserves Probable Mineral Reserves Total Mineral Reserves Mineral Property Tonnes (kt) Grade (g/t) Content (koz) Tonnes (kt) Grade (g/t) Content (koz) Tonnes (kt) Grade (g/t) Content (koz) Sadiola Mine 18,612 0.

  23. Slide 23: Year-End 2023 Mineral Reserves and Resources

    Slide 23: Year-End 2023 Mineral Reserves and Resources

    YEAR-END 2023 MINERAL RESERVES AND RESOURCES Reporting Notes SADIOLA KURMUK Mineral Resources: Mineral Resources: • The Sadiola Mineral Resource Estimate is listed at 0.5 g/t Au cut-off grade, • The Kurmuk Mineral Resource Estimate is listed at 0.5 g/t Au cut-off grade and constrained within an US$1

  24. Slide 24: Year-End 2023 Mineral Reserves and Resources

    Slide 24: Year-End 2023 Mineral Reserves and Resources

    YEAR-END 2023 MINERAL RESERVES AND RESOURCES Reporting Notes BONIKRO AGBAOU Mineral Resources: Mineral Resources: • The Mineral Resource estimate for Bonikro and Agbalé are listed at 0.5 g/t Au cut-off • The Agbaou Mineral Resource Estimate is listed at 0.5 g/t Au cut-off grade, grade, constrained w

  25. Slide 25: Appendix B: Non-GAAP Financial Measures

    Slide 25: Appendix B: Non-GAAP Financial Measures

    APPENDIX B NON-GAAP FINANCIAL MEASURES NON-GAAP FINANCIAL PERFORMANCE MEASURES The Company has included certain non-GAAP financial performance measures to supplement its Consolidated Financial Statements, which are presented in accordance with IFRS, including the following: (i) Cash costs per gold o

  26. Slide 26: Investor Relations

    Slide 26: Investor Relations

    Investor Relations 200 Bay Street Suite 2200, Royal Bank Plaza – North Tower Toronto, Ontario M5J 2J3 ir@alliedgold.com www.alliedgold.com

Source: Internet Archive copy of s203.q4cdn.com

More decks from Allied Gold Corporation

All 30 Allied Gold decks