  1. Slide 1: Operations Update (April'14 – Dec'14)

    OPERATIONS UPDATE (April’14 – Dec’14)

  2. Slide 2: Sales Bookings (Apr'14 – Dec'14)

    SALES BOOKINGS (Apr’ 14 – Dec’ 14) AREA LAUNCHED AREA SOLD SALES VALUE CITY (MN SQ FT) (MN SQ FT) (INR CR) Gurgaon 0.00 0.25 283 Noida & G Noida 0.00 0.18 172 Chennai 0.16 0.13 42 Kolkata 0.00 0.08 53 Other Cities 0.48 0.47 113 Total 0.64 1.11 663 AREA SOLD BOOKED VALUE AVG. REALISATION SEGMENT (MN

  3. Slide 3: Regionwise Sales Bookings (Value) (Apr'14 – Dec'14)

    REGIONWISE SALES BOOKINGS (VALUE) (Apr’14 – Dec’14)

  4. Slide 4: Sales Bookings During Last 6 Quarters

    SALES BOOKINGS DURING LAST 6 QUARTERS

  5. Slide 5: Average Realization per Sq.Ft. During Last 6 Quarters

    AVERAGE REALIZATION PER SQ.FT. DURING LAST 6 QUARTERS

  6. Slide 6: Delivery Status of Projects

    DELIVERY STATUS OF PROJECTS BALANCE AREA TOTAL AREA DELIVERED AREA DELIVERED UNDER S NO. PARTICULARS AREA* DURING TILL 31ST DEC 2014 DEVELOPMENT (IN MN SQ FT) APR – DEC 2014 (MN SQ FT) (IN MN SQ FT.) 1 Sold Area 56.70 1.78 19.27 37.43 2 Leased Area - 1.26 - - Total 56.70 3.04 19.27 37.43 * This is t

  7. Slide 7: Possession Status of Projects for Last 6 Quarters

    POSSESSION STATUS OF PROJECTS FOR LAST 6 QUARTERS

  8. Slide 8: Construction Status of Projects

    CONSTRUCTION STATUS OF PROJECTS Construction Number of Area % age Projects Stage projects (mn sq ft) of total Gurgaon: The Close (South),The Close (North), World Spa, Fresco, Escape, Harmony, Espace, Nirvana Floors, The Residences, Signature Tower II, South City Floors, Nirvana Courtyard, Arcadia, B

  9. Slide 9: Construction Status of Projects

    CONSTRUCTION STATUS OF PROJECTS

  10. Slide 10: 2) = (eh iq) — ©) oO = {e) < (ox jd) = 7)

    2) = (eh iq) — ©) oO = {e) < (ox jd) = 7) (= = <2) O _ = Oo i)

  11. Slide 11: Residences Dehradun, GIP Dehradun

    Residences Dehradun GIP Dehradun Structure work in progress Structure work in progress

  12. Slide 12: Slide 12

  13. Slide 13: Unihomes – Handover / Internal work / Structure

    UNIHOMES – Handover/ Internal work/ Structure in progress

  14. Slide 14: GIP – Piling / Structure work in progress

    GIP – Piling/ Structure work in progress

  15. Slide 15: Slide 15

  16. Slide 16: Harmony, Kolkata – Structure complete, internal work in progress

    HARMONY, KOLKATA – Structure complete, internal work in progress

  17. Slide 17: Air, Kolkata; Vistas, Kolkata

    AIR, KOLKATA VISTAS, KOLKATA Structure Complete, Internal work in progress Handover / Finishing in Progress

  18. Slide 18: Fresco, Kolkata – Structure work in progress

    FRESCO, KOLKATA - Structure work in progress

  19. Slide 19: Cascades, Kolkata – Internal work in progress

    CASCADES, KOLKATA – Internal work in progress

  20. Slide 20: Heights, Kolkata – Internal work in progress

    HEIGHTS, KOLKATA – Internal work in progress

  21. Slide 21: Downtown, Kolkata – Internal work in progress

    DOWNTOWN, KOLKATA – Internal work in progress

  22. Slide 22: Slide 22

  23. Slide 23: Uniworld Resorts, Bengaluru – Internal / External work in progress

    UNIWORLD RESORTS, BENGALURU – Internal / External work in progress