  1. Slide 1: Southern Natural Gas Company 2024 Outage Review

    Slide 1: Southern Natural Gas Company 2024 Outage Review

    Southern Natural Gas Company 2024 Outage Review April 17, 2024

  2. Slide 2: Welcome

    Slide 2: Welcome

    Welcome 2

  3. Slide 3: Agenda

    Slide 3: Agenda

    Agenda • Review of current and upcoming notable Outages • April/May/June/July • Unscheduled outages • North System • South System • South Louisiana System • EEC • The next outage meeting will be on May 22, at 1:30 CST • Contacts 3

  4. Slide 4: Disclaimers

    Slide 4: Disclaimers

    Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas

  5. Slide 5: Color Key for Maps

    Slide 5: Color Key for Maps

    Color Key for Maps • Yellow • Restrictions are possible • With extended duration, restrictions could be necessary from time to time • Lower than normal pressures may be experienced • Meter(s) affected are noted with (PIN #) • Red • Restrictions are probable 5

  6. Slide 6: Southern Natural Gas Pipeline

    Slide 6: Southern Natural Gas Pipeline

    Southern Natural Gas Pipeline Chattanooga Rome Hartwell SC Muldon North System GA MS Tarrant Bell Mills Aiken McConnells Atlanta Pell City DeArmanville Louisville Wrens Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Selma Elmore Holy Trinity Bie

  7. Slide 7: Unscheduled Outage Update

    Slide 7: Unscheduled Outage Update

    Southern Natural Gas Pipeline Unscheduled Outage Update Unscheduled Pipeline Chattanooga maintenance SMLL west of Hall Gate 2-13-24 to RTS-TBD Seg. 560 cap. 700 Mdth/d Rome impacted 95 Mdth/d Hartwell SC Muldon North System GA MS Tarrant Bell Mills Aiken McConnells Atlanta Pell City DeArmanville Lou

  8. Slide 8: SNG North System Pigging Review

    Slide 8: SNG North System Pigging Review

    SNG North System Pigging Review April/May/June/July Chattanooga Huntsville Pigging on Rome Calhoun line Pigging on NML Pigging on Logans Supply line 5-6-24 to 5-9-24 Rome 6-25-24 to 6-27-24 6-10-24 to 6-13-24 Pro.5454-east of Logansport Pro. 5663-west of Tarrant AL Pro.5978-north of Bell Mills Muldo

  9. Slide 9: SNG North System Maintenance Review

    Slide 9: SNG North System Maintenance Review

    SNG North System Maintenance Review April/May/June/July Chattanooga Huntsville Rome AL Muldon Storage Atlanta Bear Creek Shut-in test Tarrant Bell Mills 4-16-24 to 9 AM on 4-23-24 MS McConnells Pell City Restrictions first into ISS then Reform DeArmanville Providence CSS-not to exceed 64% of CSS Lou

  10. Slide 10: SNG North System Maintenance Review cont.

    Slide 10: SNG North System Maintenance Review cont.

    SNG North System Maintenance Review cont. April/May/June/July Chattanooga PL. remediation Gadsden Branch loop line Huntsville 5-6-24 to 8-2-24 Pro. 21261 north of Pell CityRome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA O

  11. Slide 11: SNG South System Pigging Review

    Slide 11: SNG South System Pigging Review

    SNG South System Pigging Review April/May/June/July MS Hartwell Pigging on SMLL Aiken 7-16-24 to 7-18-24 Atlanta Pro. 18931 west of Ellerslie Wrens Pigging on SML GA 5-14-24 to 5-16-24 Pro. 4701-east of Gallion Ocmulgee Pigging on Brunswick line AL Ellerslie Hallgate 5-27-24 to 6-13-24 Auburn Thomas

  12. Slide 12: SNG South System Maint. Review

    Slide 12: SNG South System Maint. Review

    SNG South System Maint. Review April/May/June/July MS Hartwell Aiken Pipeline remediation SM2ndLL Atlanta Hartwell unit outage 4-15-24 to 4-19-24 Wrens Pipeline maintenance SM2ndLL 3-27-24 to 4-17-24 4-12-24 to 4-19-24 Seg. 460 capacity of 2,273 Mdth/d impacted 240 Mdth/d GA 4-17-24 to 5-10-24 Seg.

  13. Slide 13: SNG South System Maint. Review cont.

    Slide 13: SNG South System Maint. Review cont.

    SNG South System Maint. Review cont. April/May/June/July Pipeline maintenance SMLL 4-20-24 to 5-20-24 Seg. 420 capacity of 1,675 MS Elmore station maintenance Mdth/d impacted up to 175 5-13-24 to 5-19-24 Hartwell Mdth/d Seg. 460 cap. Of 2,273 Mdth/d Aiken east of Bay Springs impacted 295 Mdth/d Atla

  14. Slide 14: SNG South System Maint. Review cont.

    Slide 14: SNG South System Maint. Review cont.

    SNG South System Maint. Review cont. April/May/June/July MS Pipeline maintenance SML PL. maintenance SM2ndLL Hartwell 5-21-24 to 6-20-24 4-18-24 to 5-10-24 Aiken Seg. 430 capacity of 2,283 Seg. 490 cap. Of 1,547 Mdth/dAtlanta Pipeline maintenance SML Mdth/d impacted up to 148 impacted 25 Mdth/d 5-21

  15. Slide 15: SNG South System Maint. Review cont.

    Slide 15: SNG South System Maint. Review cont.

    SNG South System Maint. Review cont. April/May/June/July SM2ndLL Pipeline remediation Pipeline remediation SML MS 6-3-24 to 6-7-24 6-24-24 to 6-28-24 Seg. 460 capacity of 2,140 Pro.17842/34908 Hartwell Mdth/d impacted 65 west of Thomaston Mdth/d Aiken Atlanta Pro. 21649 east of Elmore Wrens GA Ocmul

  16. Slide 16: SNG South Louisiana System Pigging Review

    Slide 16: SNG South Louisiana System Pigging Review

    SNG South Louisiana System Pigging Review April/May/June/July Gwinville Pearl River Pigging on FG2ndLL MS 4-22-24 to 4-25-24 LA Franklinton Pro. 16348-north of Franklinton Pigging on SS28 line 7-15-24 to 7-18-24 Pro. 28751-west of White Pigging on MPFLL Castle 7-15-24 to 7-19-24 Pro. 5942-south of F

  17. Slide 17: SNG South Louisiana System Maint. Review

    Slide 17: SNG South Louisiana System Maint. Review

    SNG South Louisiana System Maint. Review April/May/June/July SESH maintenance at Gwinville Pipeline maintenance 5-14-24 Cap. = 446 Mdth/d FGL 5-15-24 Cap. = 455 Mdth/d 7-8-24 to 8-8-24 5-16-24 Cap. = 476 Mdth/d Seg. 370 cap. 1,123 Sesh maintenance at Delhi Mdth/d impacted 20 5-20-24 Cap. = 432 Mdth/

  18. Slide 18: EEC Line

    Slide 18: EEC Line

    EEC Line April/May/June/July Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Elba Rankin Bay Springs Selma Elmore Gallion Holy Trin

  19. Slide 19: SNG North System Pigging Review

    Slide 19: SNG North System Pigging Review

    SNG North System Pigging Review Remainder of year Chattanooga Huntsville Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA Onward Pigging on NMLL Bear Creek Storage 10-8-24 to 10-9-24 AL Pro. 15346-east of Tarrant Loganspor

  20. Slide 20: SNG North System Maint. Review

    Slide 20: SNG North System Maint. Review

    SNG North System Maint. Review Remainder of year Pipeline maintenance Rome Muldon Shut-in test Calhoun loop line Huntsville 10-1-24 to 10-7-24 8-19-24 to 9-13-24 Restrictions first into ISS then Pro.15374 Rome CSS-not to exceed 36% of CSS north of Bell Mills AL DIQ /DWQ Muldon Storage Atlanta Tarran

  21. Slide 21: SNG South System Pigging Review

    Slide 21: SNG South System Pigging Review

    SNG South System Pigging Review April/May/June/July MS Hartwell Aiken Atlanta Wrens GA Pigging on SMLL Ocmulgee 8-5-24 to 8-8-24 Pro. 18926 east of Gallion AL Ellerslie Hallgate Auburn Thomaston Pigging on North Terrell line 6 Elba 8-12-24 to 8-15-24 Pro. 15224 south of Holy Riceboro Gallion Selma E

  22. Slide 22: SNG South System Maint. Review

    Slide 22: SNG South System Maint. Review

    SNG South System Maint. Review Remainder of year Thomaston Griffin 2nd loop MS line Pipeline maintenance 9-16-24 to 9-20-24 North of ThomastonHartwell Pro. 231009 Aiken Atlanta Wrens GA Ocmulgee Hallgate AL Ellerslie Auburn Thomaston Elba Gallion Selma Elmore PL. maintenance Riceboro SML York Holy T

  23. Slide 23: SNG South Louisiana System Pigging Review

    Slide 23: SNG South Louisiana System Pigging Review

    SNG South Louisiana System Pigging Review Remainder of year Gwinville Pearl River MS LA Franklinton West Leg White Castle Toca East Leg Shadyside Compressor Station Storage Field Southern will be conducting other general maintenance during this period 23

  24. Slide 24: SNG South Louisiana System Maint. Review

    Slide 24: SNG South Louisiana System Maint. Review

    SNG South Louisiana System Maint. Review Remainder of year Gwinville Pearl River MS LA Franklinton West Leg White Castle Toca East Leg Shadyside Compressor Station Storage Field Southern will be conducting other general maintenance during this period 24

  25. Slide 25: EEC Line

    Slide 25: EEC Line

    EEC Line Remainder of year Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Elba Rankin Bay Springs Selma Elmore Gallion

  26. Slide 26: Gas Control Contacts

    Slide 26: Gas Control Contacts

    Gas Control Contacts Skyler Spyker – Manager • (713) – 420 – 2386 (office) • (806)-470-7743 (cell) • skyler_spyker@kindermorgan.com • Kal Dankovich – Outage Coordinator • (205) – 533 – 4795 (cell) • kalman_dankovich@kindermorgan.com Jimmy Reese – Lead Controller • (205) – 577 – 3204 (cell) • jimmy_r

  27. Slide 27: Questions?

    Slide 27: Questions?

    Questions? 27

Source: Internet Archive copy of pipeline2.kindermorgan.com