Ivanhoe Mines Ltd. Class A · TSX:IVN

Ivanhoe Mines Ltd. Class A — Q1 2024 Earnings Presentation

33 slides from Ivanhoe Mines Ltd. Class A's earnings presentation, Apr 30, 2024

  1. Slide 1: 2024 Q1 Financial Results

    www.ivanhoemines.com | TSX: IVN; OTCQX: IVPAF 2024 Q1 FINANCIAL RESULTS April 30, 2024

  2. Slide 2: Disclaimer and Forward-Looking Statements

    DISCLAIMER AND FORWARD-LOOKING STATEMENTS The information contained in this presentation and other information furnished by or on behalf of Ivanhoe Mines Ltd. (“Ivanhoe”) has been prepared to assist the reader in understanding the business and financial results of Ivanhoe for the periods indicated a

  3. Slide 3: Opening Remarks

    The Kamoa construction team, alongside our dedicated contractors, celebrate the first ore feed to the Phase 3 HPGR stockpile. OPENING REMARKS Robert Friedland, Founder & Executive Co-Chairman 3

  4. Slide 4: The green new deal is nothing without copper

    The green new ool, you have deal is... nothing without copper! 4 IVANHOE MINES

  5. Slide 5: Q1 2024 Highlights

    Pre-commissioning of Kamoa-Kakula’s new 5 million- tonne-per-annum Phase 3 concentrator underway well ahead of schedule, with first ore expected in May Q1 2024 HIGHLIGHTS Marna Cloete, President 5

  6. Slide 6: Q1 2024: Highlights of the First Quarter

    Q1 2024: HIGHLIGHTS OF THE FIRST QUARTER (Figures shown on 100% basis for Kamoa-Kakula) Kamoa-Kakula secures 15 MW of imported grid 86,203 tonnes power; significantly improved production in April Copper Produced (~32,000 tonnes of copper), a further 40 MW expected from tomorrow, May 1 85,155 tonnes

  7. Slide 7: Health & Safety: Striving for Continuous Improvement

    HEALTH & SAFETY: STRIVING FOR CONTINUOUS IMPROVEMENT Ivanhoe Mines’ TRIFR(1) by Project 5.15 4.23 2.66 Industry Average(2) 2.80 2.76 2.21 2.20 1.90 1.09 1.70 1.55 0.75 0.00 2022 2023 2024 Q124 2022 2023 2024 Q124 2022 2023 2024 Q124 Kamoa-Kakula Platreef Kipushi (1) Total recordable injury frequency

  8. Slide 8: Ivanhoe Mines' 7th Annual Sustainability Report

    IVANHOE MINES’ 7TH ANNUAL SUSTAINABILITY REPORT Kamoa-Kakula generated 6% of DRC GDP; $860 million paid government taxes and royalties $2.7 billion spent on domestic suppliers (YoY increase of 80%) 845 local enterprises supported group- wide (YoY 150% increase) 849 scholarships and bursaries distrib

  9. Slide 9: Sustainability: 2024 Strategic Drivers & Objectives

    SUSTAINABILITY: 2024 STRATEGIC DRIVERS & OBJECTIVES 1 Decarbonization strategy 2 Tailings storage management 3 Embedding human rights into business practice 4 Responsible sourcing best practice 5 Diversity and inclusion Agriculture is a major component of Kamoa's Sustainable Livelihoods initiative 9

  10. Slide 10: Q1 2024 Financial Overview

    Construction crews celebrate the lifting of Kamoa- Kakula’s second anode furnace into place at the direct-to-blister smelter construction site Q1 2024 FINANCIAL OVERVIEW David van Heerden, Chief Financial Officer 10

  11. Slide 11: Kamoa-Kakula: Quarterly Financial Results

    KAMOA-KAKULA: QUARTERLY FINANCIAL RESULTS (Figures shown on 100% basis for Kamoa-Kakula) Copper sold lower in Q1 2024 due to grid instability, offset marginally by higher copper price Copper Sold (kt) Quarterly Revenue(1) ($ million) / Realized Copper Price ($/lb.) $4.04/lb. $3.79/lb. $3.84/lb. $3.8

  12. Slide 12: Kamoa-Kakula: Quarterly Financial Results

    KAMOA-KAKULA: QUARTERLY FINANCIAL RESULTS (Figures shown on 100% basis for Kamoa-Kakula) C1 cash costs towards lower end of FY2024 guidance ($1.50 - $1.70/lb.) Q1 2024 EBITDA of $365 million with EBITDA margin of 59% C1 Cash Cost ($ per lb.) EBITDA ($ million) / EBITDA Margin (%) 66% 65% 61% 59% 56%

  13. Slide 13: Kamoa-Kakula: Q1 2024 EBITDA Waterfall

    KAMOA-KAKULA: Q1 2024 EBITDA WATERFALL (Figures shown on 100% basis for Kamoa-Kakula, US$ millions) Quarter-on-quarter increase in EBITDA from increase in remeasurement of contract receivables and improved copper prices; offset by decrease in tonnes sold and increase in cash costs Quarter-on-quarter

  14. Slide 14: Ivanhoe Mines Consolidated Financial Results

    IVANHOE MINES CONSOLIDATED FINANCIAL RESULTS Normalized profit of $70 million, excluding non-cash $139 million impact of convertible bond Share price of Ivanhoe Mines (C$) Net Profit / Normalized Net Profit(1) ($ million) Normalized Net Profit Net Profit 26% 14% 15% $113 $114 $95 Q1 2023 Q2 2023 Q3

  15. Slide 15: Strong Balance Sheet to Execute Five Major Projects

    STRONG BALANCE SHEET TO EXECUTE FIVE MAJOR PROJECTS (Figures shown on 100% basis, US$ millions) Q1 2024 2024 2025 Funding Ivanhoe moves to net cash Capital Expenditure position following redemption of Actuals Guidance Guidance Arrangements $575 million 2.50% convertible Kamoa-Kakula notes due 2026 P

  16. Slide 16: Operations & Project Update

    Kamoa-Kakula’s state-of-the-art 500,000 tonne-per-annum smelter under construction OPERATIONS & PROJECT UPDATE Mark Farren, Chief Operating Officer Alex Pickard, EVP, Corporate Development & IR 16

  17. Slide 17: Kamoa-Kakula: Quarterly Production

    KAMOA-KAKULA: QUARTERLY PRODUCTION (Figures shown on 100% basis for Kamoa-Kakula) 86,203 tonnes of copper in concentrate Ore tonnes milled (‘000’s tonnes) / produced in Q1 2024; tonnes and grade Copper ore grade processed (%) were impacted by intermittent grid 5.21% 5.37% 4.95% 4.80% power instabili

  18. Slide 18: Power Stability Initiatives in Progress

    POWER STABILITY INITIATIVES IN PROGRESS Long-term DRC grid improvement projects underway, in conjunction with SNEL; completion targeted for mid-2025 15 MW of imported power secured from Zambian grid since mid-March Agreement signed to secure additional 40 MW of imported power sourced from Mozambique

  19. Slide 19: Phase 3 Concentrator Ahead of Schedule

    PHASE 3 CONCENTRATOR AHEAD OF SCHEDULE Phase 3 concentrator 94% complete, ahead of schedule for first production in May 2024 Pre-commissioning of Phase 3 concentrator underway Kamoa-Kakula Phase 3 concentrator construction site 19

  20. Slide 20: Smelter Construction on Schedule for Q4 2024

    SMELTER CONSTRUCTION ON SCHEDULE FOR Q4 2024 Construction of the direct-to-blister copper smelter project is 82% complete and on target for completion by the end of 2024 Aerial view of the 100-hectare smelter construction site, with Phase 1 & 2 concentrators in the background 20

  21. Slide 21: Kamoa-Kakula Phase 3: Inga Refurbishment

    KAMOA-KAKULA PHASE 3: INGA REFURBISHMENT Refurbishment of hydropower at Inga II approximately 62% complete for Q1 2025 Wet commissioning and synchronization to the grid is delayed until mid Q1 2025 due to late delivery in the first quarter of the turbine runner and shaft All critical-path equipment

  22. Slide 22: Growth Beyond Phase 3 – Targeting >20 Mtpa

    GROWTH BEYOND PHASE 3 – TARGETING >20 MTPA Optimization of Phase 3: targeting increased throughput beyond 5 Mtpa; work starting immediately Project 95: targeting increased recoveries to ~95%; engineering complete in May Tailings recovery from existing tailings (~0.7% copper) Studies underway to acce

  23. Slide 23: Western Forelands Exploration, DRC

    WESTERN FORELANDS EXPLORATION, DRC ~17,000m of drilling completed as at quarter end Drilling at high-grade Kitoko discovery continued to define the extent of mineralization Nearly 5 million contained tonnes of copper already delineated across Makoko and Kiala discoveries 23

  24. Slide 24: Kitoko Strike Remains Open

    KITOKO STRIKE REMAINS OPEN MAKOKO KAKULA WEST KITOKO Open in all directions 24

  25. Slide 25: Kipushi: Ahead of Schedule for Q2 2024

    KIPUSHI: AHEAD OF SCHEDULE FOR Q2 2024 Stoping of ultra-high grade Big Zinc orebody started ahead of schedule; approximately 260,000 tonnes of development ore stockpiled on surface Kipushi concentrator pre-commissioning commenced ahead of schedule, with first feed expected in June Aerial view of the

  26. Slide 26: Kipushi: Development Ahead of Schedule

    KIPUSHI: DEVELOPMENT AHEAD OF SCHEDULE Underground development continues ahead of schedule, with over 5,500 metres completed to date Stoping of Kipushi’s ultra-high-grade Big Zinc orebody commenced in December 2023, ahead of schedule Underground development of Kipushi’s Big Zinc orebody 26

  27. Slide 27: Platreef: Optimization of Shaft 3 in Progress

    PLATREEF: OPTIMIZATION OF SHAFT 3 IN PROGRESS Ramp-up of Phase 1 deferred until mid-2025 to accommodate Shaft #3 development Phase 2 expansion will be accelerated by re- purposing ventilation Shaft #3 for hoisting Shaft #3 will generate additional hoisting capacity of approx. 4 Mtpa, bringing total

  28. Slide 28: Q1 Financial Results: Management Q&A

    www.ivanhoemines.com | TSX: IVN; OTCQX: IVPAF Q1 FINANCIAL RESULTS MANAGEMENT Q&A 28

  29. Slide 29: Appendices

    Q1 FINANCIAL RESULTS APPENDICES www.ivanhoemines.com | TSX: IVN; OTCQX: IVPAF

  30. Slide 30: 2024 Cash Cost Guidance

    2024 CASH COST GUIDANCE $3.50 2024 guidance range: $3.00 $1.50/lb. –$1.70/lb. C1 Cash Cost ($/lb.) $2.50 Reflects the early commissioning of the Phase 3 concentrator in Guidance range: $2.00 late June 2024, requiring $1.50 - $1.70 additional backup generation $1.50 2024 Guidance Backup power may inc

  31. Slide 31: Significant Cash Flow Attributable to Ivanhoe

    SIGNIFICANT CASH FLOW ATTRIBUTABLE TO IVANHOE As at Shareholder Loan Balances March 31, 2024 ($ million) Kamoa-Kakula (39.6% equity interest) Ivanhoe will receive Total shareholder loans payable by Kamoa Holding $3,611 distributions (once Portion of shareholder loan receivable by Ivanhoe $1,787 paya

  32. Slide 32: Ivanhoe Mines' Adjusted EBITDA

    IVANHOE MINES’ ADJUSTED EBITDA (All values in US$ million) Reconciliation of profit after tax to Ivanhoe’s EBITDA and Ivanhoe Mines Adjusted EBITDA (US$ million) adjusted EBITDA: Ivanhoe’s profit (loss) after taxes ($ 69) Finance income ($ 62) Current and deferred tax recovery ($ 3) Finance costs $9

  33. Slide 33: Strong Balance Sheet Supports Ivanhoe's Growth

    STRONG BALANCE SHEET SUPPORTS IVANHOE’S GROWTH Below figures as at March 31, 2024 (All values in $ million) Net Debt(1) ($ million) / Net Debt to LTM EBITDA Cash and cash equivalents of $411 million 0.6x 1.2x nmf Redemption of $575 million 2.50% convertible notes due 2026 – reduces total debt to $69

Ivanhoe Mines — Q1 2024 Earnings Presentation on 6ix