CCC Presentation Hera-Federation Complex Project Update 5 September 2023 ASX Code: AMI
Slide 2: Acknowledgement of Country
Acknowledgement of Country • Aurelia Metals Ltd respectfully acknowledges the Ngiyampaa Nation as the Traditional Custodians of this land – both past and present. • We know this land has history, custodians and stories, spanning tens of thousands of years, that endure to this day. • We pay our respe
Slide 3: Aurelia FY23 Performance
Aurelia FY 23 Performance FY23 KEY TAKE-AWAYS Business turnaround provides a strong foundation for increased profitability Y 86koz Au at AISC of $2,315/oz Y Peak H2 unit costs lower Y Peak JunQ development metres 53% above DecQ Y Continued operational stability at Darques: Y Federation development c
Slide 4: Federation Hera Complex Progress
4 Federation Hera Complex Progress Tracking Key Dates of Interest (as of 13 June 2023): • Redpath Mining Contractors remobilisation recommence Mid- July 2023 Restart decline early - August 2023 • Hera to Peak and Burthong Road Upgrades late August 2023 Starting - September 2023 • Relocation of Minin
Slide 5: Federation Hera Complex Overview
Federation Hera Complex Overview
Slide 6: Federation Mine Development
6 Federation Mine Development FIRST 3 MONTHS OF WORK PROGRAM: • Decline, sumps and stockpile development • Single heading development, ventilated and power down decline from surface Federation development @ end Oct 2023 Note: Assumes 1 Aug 2023 Decline resumption
Slide 7: Road Upgrade Works - Priory Tank Road Intersection
7 Federation Hera Complex Overview Road Upgrade Works – Priory Tank Road Intersection
Slide 8: Road Upgrade Works - Burthong Road Northern End
8 Federation Hera Complex Overview Road Upgrade Works - Burthong Road Northern End
Slide 9: Road Upgrade Works - Burthong Road Southern End
9 Federation Hera Complex Overview Road Upgrade Works - Burthong Road Southern End
Slide 10: Federation Site Access Road/Burthong Road Intersection
Environment and Community 5 September 2023 ASX Code: AMI
Slide 13: Environment and Community
13 Environment and Community Environmental Priorities and Objectives. Priorities and improvement initiatives • Continue to provide input to the drafting of new Federation management plans to ensure the outcomes are practical and feasible. This activity is critical to the timely commencement of const
Slide 14: Location on dust monitor
14 Environment and Community Location on dust monitor
Slide 15: Exploration
Exploration 5 September 2023 ASX Code: AMI
Slide 16: Exploration around Federation to recommence
16 Exploration Exploration around Federation to recommence • New coming rig coming to site 6/9/23, will result in less disturbance being required. • Heavy rubber matting used instead of road base to reduce set up and rehabilitation requirements
Source: Internet Archive copy of aureliametals.com