  1. Slide 1: Q3 2026 Production Update

    Transforming resources into opportunity for all Q3 2026 Production Update 15 October 2026

  2. Slide 2: Disclaimer

    Disclaimer This Presentation (the “Presentation”) has been This Presentation does not constitute or form part statements in this Presentation relating to future prepared and issued by Kenmare Resources plc of, and should not be construed as, an offer, financials, results, plans and expectations (the

  3. Slide 3: Established producer, long mine life

    Established producer, long mine life Overview: Kenmare Resources plc Moma Titanium Minerals Mine in Mozambique • Track record of ~20 years of production • >100 years of Mineral Resources at current production rate Trusted corporate citizen • Meaningful contribution to Mozambique economy Moma • Const

  4. Slide 4: Materially stronger production in Q3

    Materially stronger production in Q3 Overview of Q3 2026 – operations, capital projects and markets Stronger production Rare earths opportunity Challenging markets • Materially increased production in Q3 • Pre-Feasibility Study (PFS) • Demand for all products remains vs Q2 2026 due to higher excavat

  5. Slide 5: Significant corporate initiatives in Q3

    Significant corporate initiatives in Q3 Overview of Q3 2026 – corporate IA renewal remains a priority Possible offer for Kenmare • The Implementation Agreement (IA) • As announced on 6 October 2026, governs the terms under which Kenmare received a non-binding Kenmare conducts its processing proposal

  6. Slide 6: ~60% increase in ilmenite production QoQ

    ~60% increase in ilmenite production QoQ Q3 2026 operations review Mining  Significant increase in Heavy Mineral Concentrate (HMC) production HMC Ilmenite due to higher excavated ore volumes (+22%) at all Wet Concentrator Plants (WCPs) 334,100t 233,600t  Lower ore grades (-12%), primarily at WCP A

  7. Slide 7: Improvements at WCP A realised in Q3

    Improvements at WCP A realised in Q3 Status update on the WCP A upgrade project New dredges at WCP A Solutions underway to resolve dredge performance issues  In H1, the key challenge impacting performance related to the dredges  Kenmare has been working with the dredge supplier on two primary issu

  8. Slide 8: Ilmenite weak but zircon continues to tighten

    Ilmenite weak but zircon continues to tighten Q3 2026 market review Stable demand for all products Concentrates production by region (Mt)1  Consistent demand but titanium feedstocks market remains challenging 5  Despite this, Kenmare achieved an increased average ilmenite 4 price received in Q3 vs

  9. Slide 9: Transforming resources into opportunity for all

    Transforming resources into opportunity for all Delivering Kenmare’s purpose Resilient long-term production profile Cashflow generation through the cycle • One of the world’s largest titanium minerals deposits • Solid record of operating cashflow generation • >100 years of Mineral Resources at curre