Tungsten Mining NL — Technical Presentation (November 2026)
37 slides from Tungsten Mining NL's technical presentation, Nov 17, 2026
Slide 1: Watershed Project Definitive Feasibility Study Executive Summary
rsonal use only Tungsten Mining NL · ASX: TGN Watershed Project Definitive Feasibility Study Executive Summary 17th November 2026
Slide 2: Important Notices and Disclaimers
Important Notices and Disclaimers Competent Person Statements “expect”, “project”, “estimate”, “target”, “schedule”, “may”, “will”, “intend”, “indicative”, “anticipate”, “believe”, “potential” and “could”, and similar expressions. The information in this presentation that relates to metallurgy, proc
Slide 3: Watershed DFS Key Outcomes
DFS Highlights · Key Metrics Watershed DFS Key Outcomes Pre-tax NPV8% (Valuation from 1 November 2026) A$1,569 M rsonal use only Pre-tax IRR Payback (Pre-tax, From First Revenue) 70% 18 Months Go-forward Pre- Total Pre-production Life-of-Mine (LoM) LoM Operating Production CAPEX1 Capital WO₃ OPEX2 M
Slide 4: Global Tungsten Market – Supply and Demand Forecast
Tungsten Market · Global Forecast Global Tungsten Market – Supply and Demand Forecast Tungsten demand Tungsten supply Structural deficit rsonal use only 220 • Chinese export controls exacerbating commodity risk and supply chain security • Global demand growth is concentrated in key sectors that diss
Slide 5: Global Tungsten Market – Future Demand by Sector
Tungsten Market · Sector Demand Forecast Global Tungsten Market – Future Demand by Sector 2025 demand Growth to 2035 2035 demand 154.07 kt +60.65 kt 214.73 kt rsonal use only Base year 3.4% CAGR p.a. Forecast 2025 demand Growth to 2035 Growth (kt) Principal drivers Flat to negative: EV powertrains e
Slide 6: APT mid price has averaged US$2,996/mtu for 7 months
Tungsten Market · APT Price APT mid price has averaged US$2,996/mtu for 7 months, up from US$674/mtu rsonal use only US$3,140/mtu 3,500 Peak 3,000 APT mid price (US$/mtu WO₃) 2,500 US$674/mtu US$2,996/mtu 7 month average 2,000 1,500 1,000 500 0 Nov 25 Jan 26 Mar 26 May 26 Jul 26 Sep 26 Source: Fastm
Slide 7: Project Location & Tenure
Introduction · Project Location & Tenure Highway or main road Town N The Watershed Project in Far North Railway Mine access road Other mine Port and airport Queensland is 100% Owned by 0 10 20 km Tungsten Mining NL rsonal use only Watershed Lease Type Lease Number Status Ownership Coral Sea Mining L
Slide 8: Speed-to-Market Strategy with First Production Aimed for H1 2027
Introduction · Project Strategy The Project Development is Centred Around a Speed-to-Market Strategy with First Production Aimed for H1 2027 Tungsten Mining NL (TGN) has completed a Definitive Feasibility Study (DFS) for the rsonal use only Watershed Tungsten Project in Far North Queensland to suppo
Slide 9: Mineral Resource and Ore Reserve
Resource · Mineral Resource Estimate & Ore Reserves Mineral Resource and Ore Reserve 69.7 Mt 0.11% 76.0 kt Mineral Resource(1)(3) WO₃ grade Contained WO₃ rsonal use only Category Tonnes (Mt) WO₃ (%) Contained WO₃ (kt) Measured 12.5 0.13 15.7 Indicated 41.9 0.10 43.5 Inferred 15.3 0.11 17.1 Total 69.
Slide 10: Additional Resource Drilling Underway
Geology · Resource Drilling Additional Resource Drilling Underway to Increase Confidence in Initial Mining Areas Program Commenced Expected Completion rsonal use only 21,000 m RC July 2026 Dec 2026 Phase 2 drills 40 m × 20 m first, then infills to 20 m × 20 m Broad spacing first allows more targeted
Slide 11: Mining 141.8 Mt over 10.2 years to recover 31,279 t WO₃
Production · Mine Plan & Production Profile Mining 141.8 Mt over 10.2 years to recover 31,279 t WO₃ Ore mined Waste mined Strip ratio 18 3.6 rsonal use only Total material mined 15 3.0 Strip ratio (t:t) 12 2.4 (Mt) 9 1.8 6 1.2 3 0.6 0 0.0 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2
Slide 12: Bulk Sample Processing
Bulk Sample Fines Bulk Sample Excavation Metallurgy and Processing · Bulk sample Preconcentration Spiral Bulk Sample Processing Bulk sample 135t rsonal use only Crushing and Screening ~52t −10 mm −40+10 mm ~83t 1.24% WO3 @0.60% WO3 Fines Dense Media Pre- Ore sorting Separation (DMS) concentration an
Slide 13: Bulk Sample: +50% WO₃ Concentrate at 68.9% Net Recovery
Metallurgy and Processing · Flowsheet Confirmation Bulk Sample: +50% WO₃ Concentrate at 68.9% Net Recovery Ore sorting1 Feed (%) Product (%) Sample Grade Grade Mass WO₃ Rec. Mass WO₃ Rec. WO₃ WO₃ rsonal use only Bulk Sample 100 0.60 100 9.7 5.58 90.9 Fines pre-concentration Feed (%) Product (%) Samp
Slide 14: Conventional Process Flowsheet Confirmed
Metallurgy and Processing · Process Flowsheet Conventional Process Flowsheet Confirmed Crushing & 1 3 High Grade Ore sorting Scheelite Product Screening Beneficiation plant rsonal use only Ore feed RoM Ore −40+10 mm Sorter Accepts Scheelite con 2 Fines pre-concentration −10 mm Pre-concentrate 1 Ore
Slide 15: Project Infrastructure Site Layout
Maitland track Project Infrastructure · Site layout Accommodation village The Project Consists of Infrastructure Helipad Components to Support the Mining Operation Village road rsonal use only Lease boundary Mine pit Waste rock dumps Communications trailer Process plant Process plant Water dams Runo
Slide 16: Bulk Earthworks, Roadworks and Drainage
Civil Works · Project Wide Civils Plan Bulk Earthworks, Roadworks and Drainage 0 1 2 km N 28% existing grade reduced to 17.5% rsonal use only Ch 20000 Ch 5000 Ch 15000 Ch 0 Ch 10000 Magazine pad and SSAN pad Floodway A (100 m) Floodway C (50 m) Floodway B (100 m) Mine pits Mulligan Highway Ch 24000
Slide 17: Plant Infrastructure Consists of Conventional Processing Facilities
Project Infrastructure · Processing Area The Plant Infrastructure Consists of Conventional Processing Facilities High Grade Beneficiation Plant rsonal use only Fines Pre-Concentration Plant Plant Primary and Services Secondary Area (PSA) Crushing & Screening Ore Sorting Plant Tertiary and Quaternary
Slide 18: Power, Water, Communications and Non-Process Infrastructure
Project Infrastructure · Overview Power, Water, Communications and Non-Process Infrastructure Power Water Strategy Source Groundwater bores rsonal use only Diesel powered generators Storage Station Dam (~54 ML capacity) 3.2 MW 2.7 MW Demand Maximum demand Average demand 2 ML/day ~300 ML/yr Demand Pe
Slide 19: Accommodation Village
Project Infrastructure · Accommodation Village 260 Permanent and 100 Temporary Rooms to meet Construction Peak of 336 Hired modules Permanent Accommodation Power station 60 rooms 65 buildings, 260 rooms Gymnasium rsonal use only Rapid deployment camp Wet mess 40 rooms Dry mess Wastewater treatment p
Slide 20: Mine Services Area
Project Infrastructure · MSA Mine Services Area N 0 25 50 m Administration area MSA admin building, TGN office, Refuelling and diesel LV workshop Heavy Mobile Equipment (HME) With Mobile Equipment rsonal use only crib, ablution and ice room and LV refuelling, Maintenance (MEM) diesel storage and unl
Slide 21: Groundwater Supply from Eight Production Bores
Project Infrastructure · Water Supply Accommodation village Groundwater Supply of up to 36 L/s from Eight PDS54 5 l/s Production Bores to meet Project Needs PDS53 10 l/s rsonal use only Water demand by Year (ML) Construction Process Mining Potable Stage 1 bore location Future bore location Village r
Slide 22: Comprehensive Communications Network to Service Entire Site
Project Infrastructure · Communications Equipment Comprehensive Accommodation village ~80 CB handsets for Communications Network to Starlink backhaul Full Wi-Fi coverage construction DMR handsets for mine Service Entire Site ~20 operations CB and DMR radio trailer 3 rsonal use only Full radio covera
Slide 23: Co-disposed Tailings Strategy
Project Infrastructure · Tailings Co-disposed Tailings Project Utilises a Co-disposal Tailings Strategy 141.8 Mt 76.1 Mm³ rsonal use only placed in the Waste Rock combined WRD capacity Dumps (WRDs) (LoM) 71.5% 18.9% 9.6% Waste rock 101.3 Mt Sorter rejects 26.8 Mt Tailings 13.7 Mt FY28–29 Waste and t
Slide 24: Project Delivered through a Lead EPCM and Integrated Owner’s Team
Project Execution · Execution Strategy Project Delivered through a Lead EPCM and Integrated Owner’s Team Civils & NPI Process plant Area Integrated owner’s team with ESP Integrated owner’s team with Lead EPCM rsonal use only Minor civils & Non-process Fines pre- High-grade Package Bulk civils Ore so
Slide 25: Accommodation Strategy Caters for Peak Project Manning
Project Execution · Indicative Manning & Accommodation Strategy Accommodation Strategy Caters for Peak Project Manning Projects Mining Civils Project Construction Operations Bed Limit 400 Construction Peak: 336 rsonal use only 350 300 Steady State: 260 rooms ROOMS 250 200 150 100 50 - Oct-26 Nov-26
Slide 26: Townsville and Cairns used as Primary Ports for Logistics
Project Execution · Logistics Watershed Townsville and Cairns used as the Mine access road Primary Ports for Logistics Mount Carbine Mount Molloy Cairns rsonal use only Mareeba Cairns route Townsville route Cairns route 330 km, 533 km, Atherton 330 km, about 4 h 12 min about 4 h 12 min about 6 h 36
Slide 27: Project Schedule has FID in Dec-26 and First Production in Jun-27
Project Execution · Indicative Schedule Project Schedule has FID in Dec-26 and First Production in Jun-27 The dates in this schedule are forward-looking estimates based on the assumptions determined through the Study, including the timing of project funding and regulatory approvals. Actual timing ma
Slide 28: Go-forward Pre-production Capital Requirement
Project Financials · CAPEX Go-forward Pre-production Capital Requirement A$206.6 M A$264.4 M Go-forward, from November 2026 Total pre-production capital, April 2026 rsonal use only Pre-production capital by area, A$M Pre-commitment funding 22.4 spent 35.3 committed 57.8 Process infrastructure 52.8 O
Slide 29: LoM C1 cash cost of US$440/mtu WO₃
Project Financials · OPEX LoM C1 cash cost of US$440/mtu WO₃ LOM C1 cash cost: US$440/mtu A$629/mtu WO₃ over 31,279 tonnes WO3 produced. rsonal use only C1 cost component A$/mtu US$/mtu Mining 346 242 Site G&A 193 135 Processing 77 54 Concentrate transport 10 7 Environment, heritage, approvals 3 2 C
Slide 30: APT Forecast Supporting Positive Project Economics
Project Financials · Tungsten Price Forecast The APT Forecast is Expected to Maintain High Pricing Supporting Positive Project Economics 3,500 US$2,675/mtu rsonal use only A$3,821/mtu 3,000 Spot Price 2,500 APT price (US$/mtu) 2,000 Average LOM 1,500 US$1,500/mtu 1,000 A$2,143/mtu Average LoM Price
Slide 31: Project has Robust Financial Metrics
Project Financials · Financial Evaluation Project has Robust A$6,769 M Financial Metrics Spot, cumulative by 2039 7,000 Cumulative cash flow pre-tax (A$ M) Base case NPV8 pre-tax · Fastmarkets APT forecast rsonal use only A$1,569 M 5,000 Spot Case (illustrative only) Spot NPV8 pre-tax · APT US$2,675
Slide 32: Watershed Holds its Primary Approvals
Environment & Community · Approvals & Environment Watershed Holds its Primary Approvals Granted mining leases, an approved environmental authority and a rsonal use only Commonwealth decision provide the regulatory basis for the currently approved project. Mining leases Environmental EPBC Act Seven g
Slide 33: Community – Managing Social Responsibilities
Environment & Community · Social Governance Community – Managing Social Responsibilities People and partnerships Maintaining constructive relationships with Traditional Owners, landholders rsonal use only and regional stakeholders. • Ongoing engagement with Western Yalanji representatives and local
Slide 34: Tungsten Mining is Progressing Offtake Agreements ahead of FID
Offtake · Offtake Strategy Tungsten Mining is Progressing Offtake Agreements ahead of FID Europe Target counterparties rsonal use only Japan Refiners and Strategic Partners Metals Traders Processors Channel into refiners, Flexible volumes, Foundation of the carbide and tooling logistics and offtake:
Slide 35: Funding Strategy: Project finance progressing
Project Funding · Funding Strategy Project finance progressing Targeting up to 70% senior debt ~A$277 M rsonal use only Peak unlevered funding requirement, including ~A$22 M invoiced to date, leaving ~A$255 M remaining. Excludes financing costs. Timeline to financial close and FID June 2026 Senior d
Slide 36: Contact us
rsonal use only Tungsten Mining NL · ASX: TGN Contact us Telephone +61 8 9486 8492 E-mail info@tungstenmining.com Website www.tungstenmining.com Address Level 10, 905 Hay Street, Perth 6000, Western Australia
Slide 37: Appendix: MRE and Ore Reserve
Appendix: MRE and ORE Reserve rsonal use only Refer ASX Announcements dated 18th June 2026, “Watershed Updated Mineral Resource Estimate”, The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and
Tungsten Mining NL — Technical Presentation (November 2026) on 6ix