Sunrise Energy Metals Limited · ASX:SRL
Sunrise Energy Metals — Corporate Update (April 2021)
27 slides from Sunrise Energy Metals's corporate update, April 2021
Slide 1: Project Execution Plan Modification
Project Execution Plan Modification Community Consultative Committee April 2021
Slide 2: Contents
Contents 01 02 Company Name Change Sunrise Regional Update 03 Project Execution Plan Modification – Overview 04 Project Execution Plan Modification – Environmental Assessment 05 Project Execution Plan Modification – Timing 06 CCC Member Questions 2 Powering innovation | April 21
Slide 3: Company Name Change
01 Company Name Change 3 Powering innovation | April 21
Slide 4: Company Name Change
Company Name Change › Sunrise Energy Metals Limited (SEM) ▪ Following shareholder approval in March, Clean TeQ Holdings Limited (ASX:CLQ) has now been renamed SUNRISE ENERGY METALS LIMITED ▪ Trading commenced on 12th April on the ASX with the ticker “SRL” ▪ A number of other subsidiary companies wit
Slide 5: Regional Sunrise Update
02 Regional Sunrise Update 5 Powering innovation | April 21
Slide 6: Regional Sunrise Update
Regional Sunrise Update Key Personnel Changes › Tim Kindred, Sunrise Project and Startup Director finished with the project in February. › Sunrise Regional Manager, Mike Wood has assumed overall management of the Sunrise project. Power Supply › Biodiversity assessments undertaken along the easement
Slide 7: Regional Sunrise Update: Oversized Transport Route
Regional Sunrise Update Oversized Transport Route › Approximately 150 oversized loads will be required to be delivered to Sunrise › SEM will establish an oversized / overmass transport route between Pt Pirie (SA) and Sunrise › Route survey completed › Planning underway to scope civil & electrical in
Slide 8: PEP Modification - Overview
03 PEP Modification - Overview 8 Powering innovation | April 21
Slide 9: PEP Modification - Overview: Background
PEP Modification - Overview Background › SEM has continued to review and optimise the Project design as part of preparations for the Project execution. The outcomes of this review are outlined in the Project Execution Plan. › The Project Execution Plan identified a number of changes to the approved
Slide 10: Mine Site and Processing Facility
PEP Modification - Overview Mine Site and Processing Facility 10 Powering innovation | April 21
Slide 11: PEP Modification - Rail Siding
PEP Modification - Overview Rail Siding › Relocation of the rail siding approximately 500 m south of the approved location to minimise rail and road traffic interactions at the rail level crossing on Scotson Lane. › Approximate 675 m extension of the approved Scotson Lane upgrade (8 m wide sealed pa
Slide 12: PEP Modification - Rail Siding
PEP Modification - Overview Rail Siding › New ammonium sulphate storage and distribution facility – would supply broadacre cropping/other agricultural operations in the region by road. › Waste would be disposed of at an appropriately licensed landfill consistent with the Development Consent. 12 Powe
Slide 13: PEP Modification - Road Transport Activities
PEP Modification - Overview Road Transport Activities › Changes to vehicle movements associated with the increased construction phase accommodation camp capacity and changes to heavy vehicle delivery requirements. › Changes to operational phase heavy vehicle movements to and from the rail siding ass
Slide 14: Project Components - No Changes
PEP Modification - Overview Project Components - No Changes › Other mine and processing facility components (e.g. surface development area, mining method, waste rock management, processing method and rate, tailings management, mine facilities, water management concepts, rehabilitation strategy and o
Slide 15: PEP Modification – Environmental Assessment
04 PEP Modification – Environmental Assessment 15 Powering innovation | April 21
Slide 16: Specialist Studies
PEP Modification – Environmental Assessment Specialist Studies The Modification Report will be supported by the following specialist studies: › Aboriginal Cultural Heritage Assessment › Biodiversity Review › Noise and Air Quality Assessment › Surface Water Assessment › Social Impact Review › Road Tr
Slide 17: Aboriginal Cultural Heritage (Rail Siding Only)
PEP Modification – Environmental Assessment Aboriginal Cultural Heritage (Rail Siding Only) › Aboriginal Cultural Heritage Assessment (ACHA) being prepared by Landskape in accordance with the relevant Heritage NSW guidelines. › Survey of modified rail siding undertaken on 23 February 2021 in consult
Slide 18: Biodiversity (Rail Siding Only)
PEP Modification – Environmental Assessment Biodiversity (Rail Siding Only) › Surveys by Biodiversity Australia (BA) found rail siding areas mostly comprised of cleared land/derived native grassland, with patches of Poplar Box Woodland. › BA concluded the Modification would not increase impacts on b
Slide 19: Noise and Air Quality
PEP Modification – Environmental Assessment Noise and Air Quality › Noise and Air Quality Assessments being prepared by Renzo Tonin and Jacobs in accordance with contemporary NSW Government guidelines. › Maximum case construction and operational scenarios will be considered for both the modified min
Slide 20: Surface Water
PEP Modification – Environmental Assessment Surface Water › The Modification would not change the site water management performance measures (e.g. separation between clean and mine water, TSF and Evaporation Pond seepage controls, water storage design capacity, erosion and sediment controls). › No c
Slide 21: Social
PEP Modification – Environmental Assessment Social › The scope of the Social Impact Review is based on consultation with DPIE and includes a desktop study and consultation with the Lachlan, Parkes and Forbes Shire Councils. › Review will take into consideration potential incremental social impacts a
Slide 22: Road Transport
PEP Modification – Environmental Assessment Road Transport › Road Transport Assessment is being prepared by TTPP which considers: ▪ Changes to vehicle movements associated with the increased construction phase accommodation camp capacity and changes to heavy vehicle delivery requirements. ▪ Changes
Slide 23: Land Contamination Assessment (Rail Siding Only)
PEP Modification – Environmental Assessment Land Contamination Assessment (Rail Siding Only) › Land Contamination Assessment has been prepared by Ground Doctor in accordance with the relevant NSW Government Guidelines. › Inspection of modified rail siding footprint conducted on 25 February 2021. › G
Slide 24: PEP Modification - Timing
05 PEP Modification - Timing 24 Powering innovation | April 21
Slide 25: Key Modification Milestones
PEP Modification – Timing Key Modification Milestones › Meet with DPIE [complete] › Undertake specialist environmental assessments and consultation [underway] › Prepare Modification Report [underway] › Submit Modification Report to DPIE [mid 2021] › Public exhibition [three weeks after submission] ›
Slide 26: CCC Member Questions
06 CCC Member Questions 26 Powering innovation | April 21
Slide 27: Thank you
Thank you 0. sunrise energy metals
Sunrise Energy Metals — Corporate Update (April 2021) on 6ix