Paladin Energy Ltd · ASX:PDN

Paladin Energy — Shareholder Meeting (November 2023)

22 slides from Paladin Energy's shareholder meeting presentation, Nov 15, 2023

  1. Slide 1: Annual General Meeting Presentation

    Annual General Meeting Presentation Clean energy. Clear future. 15 November 2023 IAN PURDY CHIEF EXECUTIVE OFFICER

  2. Slide 2: Disclaimer and Competent Person's Statement

    Disclaimer and Competent Disclaimer This presentation contains summary information about the Company’s activities current Except for statutory liability which cannot be excluded, the Company, its officers, Person’s Statement as at the date of this presentation. The information in this presentation i

  3. Slide 3: Market Cap, Share Price and Langer Heinrich Mine Returning to Production

    Market Cap1 A$2.9B Share price1 A$0.975/share Available Cash2 US$99.8M Index ASX200 Research Coverage Namibia Langer Heinrich Mine Returning to Production 1. As at 14 November 2023 2. As at 30 September 2023 3

  4. Slide 4: Strong demand growth for nuclear energy driven by global decarbonisation

    Strong demand growth for nuclear energy driven by global decarbonisation Global reactor fleet set to grow significantly Second largest source of Bipartisan political support 321 global clean energy with​ proposed reactors in the US & IRA4 tax credits almost zero carbon in for clean energy emissions​

  5. Slide 5: Uranium structural supply shortage

    Uranium structural supply shortage Western Market (Mlb U3O8 p.a.) 200 Average • Demand is exceeding supply deficit of market expectations ~35Mlb p.a. over 150 the next • Primary supply decade1 shortage • Secondary supplies are shrinking 100 • Window of opportunity for incumbent producers 50 2023 202

  6. Slide 6: Uranium inventory levels are rapidly reducing

    Uranium inventory levels are rapidly reducing Secondary Supplies1 90,000 2 Underfeeding Net Utility Inventory Drawdowns Other Russian Supplies 80,000 70,000 • Sustained inventory drawdowns are no longer 60,000 a viable option for utilities Thousand Pounds (U3O8) • Western enrichers to 50,000 switch

  7. Slide 7: Uranium contracting has returned to fundamentals

    Uranium contracting has returned to fundamentals • Term contracting has returned to the uranium market, driven by Term Contracting Activity (Mlb U3O8 p.a.) mid-term supply / demand fundamentals • Increased term market activity coincides with vastly reduced “carry- 275 Evaluating/Potential trade” act

  8. Slide 8: Langer Heinrich Mine overview

    Langer Heinrich Mine overview 75% owned by Paladin 10 years of production history with over 43Mlb of U3O8 produced and sold Excellent local infrastructure (port, road, rail, water & power) with proximity to the Walvis Bay industrial hub Strong Government and community support for uranium mining in N

  9. Slide 9: Project on track and on budget (~85% complete)

    Project on track and on budget (~85% complete) Decision to Long lead Early works All equipment orders Detailed Progression of Senior Operations Introduction of Repairs & restart LHM orders completed completed structural & Repair & Operations workforce stockpile ore Refurbishment completed mechanical

  10. Slide 10: A return to operations is imminent

    A return to operations is imminent LHM successfully operated for 10 years providing a straightforward pathway to commercial production Ore feed for Year 1 of operations will come from previously mined stockpiled material (mining expected to commence in Year 2) Plant operations team now in place with

  11. Slide 11: Over 440Mlbs of high-grade mineral resources in key global uranium jurisdictions

    Over 440Mlbs of high-grade mineral resources in key global uranium jurisdictions1,2 Paladin Mineral Resources1,2 Total Mass of U3O8 = 445.6Mlb Langer Heinrich Mine2 Michelin3 • Ore Reserves: 84.8Mt at 448 ppm U3O8 for 83.8Mlb • The most uranium prospective tenement holding in a • Mineral Resources (

  12. Slide 12: Canada: Michelin Uranium Project

    Canada: Michelin Uranium Project (100% Paladin ownership1) Secured 100% Control Ownership Completed extensive exploration Development pathway • Paladin now holds 100% of the advanced work packages over past 12 months • Workstream commenced to determine Michelin exploration project • Key work program

  13. Slide 13: Paladin's strategy for value creation

    Paladin’s strategy for value creation Paladin is on a clear pathway to becoming a globally significant independent uranium producer, helping the transition to a low-carbon global economy 1 2 3 Execute at the Define Development Embed Langer Heinrich Mine and Exploration Potential Sustainable Returns

  14. Slide 14: About Paladin

    About Paladin 14

  15. Slide 15: Paladin Board

    Paladin Board Cliff Lawrenson Lesley Adams Melissa Holzberger Jon Hronsky OAM Peter Main Joanne Palmer Peter Watson Non-Executive Chairman Non-Executive Director Non-Executive Director Non-Executive Director Non-Executive Director Non-Executive Director Non-Executive Director Mining executive with d

  16. Slide 16: Paladin Executive Team

    Paladin Executive Team Ian Purdy Anna Sudlow Paul Hemburrow Alex Rybak Jess Oram Johan Roux Johan Coetzee Chief Executive Officer Chief Financial Officer Chief Operating Officer Chief Commercial Officer General Manager General Manager Project Director Exploration Langer Heinrich Mine Langer Heinrich

  17. Slide 17: Our mission: resourcing a global carbon-free future

    Our mission: resourcing a global carbon-free future Nuclear energy is playing a critical role in Emissions Intensity by Energy Source 2 the transition to a decarbonised (g/kWh) economy 820 Today nuclear energy accounts for 47% of carbon-free electricity generation in the US1 and is recognised as a g

  18. Slide 18: Paladin is committed to implementing leading ESG reporting frameworks

    Paladin is committed to implementing leading ESG reporting frameworks As Paladin moves towards production, the structured implementation of three reporting frameworks (SASB, GRI and TCFD) and compliance with the IFRS Sustainability Disclosure Standards will increase the level of detail reported and

  19. Slide 19: Mineral Resources and Ore Reserves – Langer Heinrich

    Mineral Resources and Ore Reserves – Langer Heinrich Summary Mineral Resources1 Millions of Tonnes Grade U3O8 Grade V2O5 Location Classification (Mt) (ppm) Contained U3O8 (Mlb) (ppm) Contained V2O5 (Mlb) In situ -open pit Measured 79.1 450 78.6 145 25.5 In situ -open pit Indicated 23.5 375 19.5 120

  20. Slide 20: Mineral Resources table – Canadian exploration portfolio

    Mineral Resources table – Canadian exploration portfolio Mineral Resources Mt Grade ppm U3O8 Mlb U3O8 (100% basis) Paladin Ownership (%)3 Canada Measured Michelin1 17.6 965 37.6 100 Rainbow2 0.2 920 0.4 100 Indicated Gear2 0.4 770 0.6 100 Inda2 1.2 690 1.8 100 Jacques Lake1 13.0 630 18.0 100 Micheli

  21. Slide 21: Mineral Resources table – Australian exploration portfolio

    Mineral Resources table – Australian exploration portfolio Mineral Resources Mt Grade ppm U3O8 Mlb U3O8 (100% basis) Paladin Ownership (%) Australia Measured Valhalla1 16.0 820 28.9 100 2 Indicated Andersons 1.4 1,450 4.6 100 Bikini3 5.8 495 6.3 100 Duke Batman4 0.5 1,370 1.6 100 Odin5 8.2 555 10.0

  22. Slide 22: Investor Enquiries

    Investor Enquiries: Paula Raffo paladin@paladinenergy.com.au Level 8 191 St Georges Terrace, WA 6000 +61 8 9423 8100 paladin@paladinenergy.com.au paladinenergy.com.au