  1. Slide 1: Aurubis AG Metals for Progress

    Aurubis AG Metals for Progress Twelfth German Corporate Conference 2023 Munich – Berenberg & Goldman Sachs September, 20th 2023

  2. Slide 2: Aurubis: We are experts for metals

    Aurubis: We are experts for metals. Successful in > 7,100 x passion and 157 years engagement 20 countries on of experience in the production of non- 3 continents ferrous metals about 1 million t One of the 20 worldwide leading of recycling materials different metals companies in are processed by Aur

  3. Slide 3: Aurubis production & sales footprint

    Aurubis production & sales footprint Headquarters Primary Copper Recycling/Precious Metals Copper Products Aurubis operates a closely linked network of 6 key plants in Europe with a focus on smelting and refining primary and recycling raw materials Furthermore, Aurubis operates a network of 8 plants

  4. Slide 4: Closing the loop is part of Aurubis' integrated business model

    Closing the loop is part of Aurubis’ integrated business model 28 30 34 45 46 47 Ni Zn Se Rh Pd Ag Copper cathodes Concentrates Smelting and Nickel sulfate refining Selenium Sulfuric acid 50 82 79 78 75 52 Sn Pb Au Pt Re Te Further processing Scrap/ intermediates Metals for progress Continuous cast

  5. Slide 5: Increased concentrate throughput and strong product demand

    Increased concentrate throughput and strong product demand Change vs. Change vs. FY 2021/22 prior year FY 2021/22 prior year Concentrate processing1 2,429,000 t +8 % Gold 47 t -8 % Copper scrap/ 540,000 t -1 % Silver 911 t -4 % blister copper input2 Other recycling materials2 524,000 t -3 % Lead 44,

  6. Slide 6: Aurubis' strong financial position enables our growth strategy

    Aurubis’ strong financial position enables our growth strategy 9M 9M 2022/23 2021/223 Target ROCE1 % 15.1 17.1 15.0 Equity ratio % 57.5 54.0 > 40.0 (equity/total assets) Debt coverage2 0.0 -0.2 < 3.0 9M 9M Additional KPIs 2022/23 2021/22 Capital expenditure €m 374 225 Capital employed €m 3,457 2,980

  7. Slide 7: Multimetal Recycling segment

    Multimetal Recycling segment Breakdown of income components in MMR segment 9M 2022/23 YTD (YTD prior-year figures) 9M 9M Operating results 2022/23 2021/222 47 % (43 %) RCs for recycling 45 % (53 %) EBIT €m 141 186 Metal result materials EBT €m 143 186 ROCE1 % 15.8 35.5 Quantities Copper scrap/bliste

  8. Slide 8: Custom Smelting & Products segment

    Custom Smelting & Products segment Breakdown of income components in CSP segment 9M 9M 9M 2022/23 YTD (YTD prior-year figures) Operating results 2022/23 2021/222 EBIT €m 314 294 48 % (48 %) EBT €m 322 290 28 % (33 %) Premiums + ROCE1 % 17.5 13.3 Metal result products Quantities Concentrates mt 1,705

  9. Slide 9: EBT between € 310 million and € 350 million

    Updated guidance for FY 2022/23 after suspension on August 31st, 2023 Our forecast range Operating EBT Operating ROCE between € 310 million between 8 % and € 350 million and 12 % Operating EBT Operating ROCE in € million in % Group 310 – 350 8–12 Multimetal Recycling – – Custom Smelting & Products –

  10. Slide 10: Our strategy builds on the sound mission of Aurubis

    Our strategy builds on the sound mission of Aurubis and covers all relevant aspects to drive sustainable growth Secure Strengthen Pursue Core Business Core Business Growth Options Industry Leadership in Sustainability Enablers − Digitalization, automation, and “Plant of the Future” − Strategic resou

  11. Slide 11: Growth strategy: CAPEX and EBITDA impact increase significantly

    Growth strategy: CAPEX and EBITDA impact increase significantly Short term Medium term Long term Currently approved Medium-term planning (next 4 years) Until 2030 Growth capex ~€ 1,150 million Growth capex ~€ 280 million is Ambition and scale of our long-term approved included in the medium-term pla

  12. Slide 12: Strong pipeline features advanced projects included in medium-term planning

    Strong pipeline features advanced projects included in medium-term planning, plus wealth of nascent concepts to drive sustainable growth Strategic projects from development to implementation Research & Concept Basic Without status Feasibility In implementation ideation development engineering Indust

  13. Slide 13: Expanding our flowsheet with additional smelting furnaces and processes

    Expanding our flowsheet with additional smelting furnaces and processes to drive multimetal growth strategy Input materials Smelting Refining Multimetal Cu concentrates HH HH » Cu ̶ Cu processing ̶ Ol Cu/CuNi Pir ̶ HH » Ag Primary HH CuNi electrolyte ̶ PM/Ni ̶ tankhouse Lue Pir » Au sites Pir ̶ repr

  14. Slide 14: Timeline of strategic projects in implementation

    Timeline of strategic projects in implementation Commissioning Blead treatment Olen Beerse (BOB) Start of construction Start of construction (BE Olen) Complex Recycling Solar Park (BG Pirdop) Industrial Heat (DE Hamburg) Commissioning Hamburg (CRH) Tankhouse Expansion Aurubis Richmond Module 1 Aurub

  15. Slide 15: Accumulated EBITDA to rapidly overcompensate investments

    Accumulated EBITDA to rapidly overcompensate investments Growth investments to be translated into profits Capex & EBITDA contribution from 8 strategic projects (in € million) − Investing around € 1.2 billion in strategic growth options ~1,340 − Rapid payback: accumulated EBITDA of € 1.3 billion Grow

  16. Slide 16: Growth options Aurubis Richmond, US – construction work is progressing

    Growth options Aurubis Richmond, US – construction work is progressing 08/23/2023 Aurubis Twelfth German Corporate Conference 2023

  17. Slide 17: Aurubis Richmond – the leading processor of electric and electronic recycling materials in the US

    Aurubis Richmond – the leading processor of electric and electronic recycling materials in the US EBITDA p.a. Pursue Growth Options Investment ~ € 80 million (by 2025/26) ~ € 640 million Aurubis Richmond complements and expands our international integrated smelter ~ € 170 million network with a high

  18. Slide 18: Secure core business: Complex Recycling Hamburg (CRH)

    Secure core business: Complex Recycling Hamburg (CRH) – further optimization of smelting process CRH Aurubis Twelfth German Corporate Conference 2023

  19. Slide 19: CRH: Further optimization of the smelting process in Hamburg

    Secure & strengthen core business CRH: Further optimization of the smelting process in Hamburg Secure Strengthen Core Business Core Business Investment EBITDA p.a. ~ € 190 million ~ € 40 million Aurubis is strengthening its core business and investing € 190 million for further (at full production) o

  20. Slide 20: Expanding the tankhouse in Pirdop

    Secure & strengthen core business Expanding the tankhouse in Pirdop Aurubis Twelfth German Corporate Conference 2023

  21. Slide 21: Expanding the tankhouse in Pirdop

    Secure & strengthen core business Expanding the tankhouse in Pirdop Secure Strengthen Core Business Core Business Investment EBITDA p.a. ~ € 120 million ~ € 30 million Aurubis is strengthening its core business and investing € 120 million in expanding the (at full production) tankhouse at its Bulgar

  22. Slide 22: Our KPIs underline our sustainability ambitions and demonstrate momentum

    Our KPIs underline our sustainability ambitions and demonstrate momentum Absolute Scope 1+2 CO2 emissions Scope 3 CO2 emissions Air emissions (dust) (in kt) (in kt)1 (in g per t of multimetal Cu equivalent)2 56.5 1,600 6,502 6,181 48.0 1,310* 4,942 40.1 1 2 3 800 2018 2022 2030 2018 2021 2030 2018 2

  23. Slide 23: Leading the way with life cycle assessments

    Leading the way with life cycle assessments – and substantially lower carbon footprints than industry averages CO2 footprint of Aurubis metals vs. global industry average 2020: 6,632 Copper cathodes Tin in kg CO2 eq./t Cu in kg CO2 eq./t 2021: 1,570 Global industry average Aurubis 2013: 4,027 2013:

  24. Slide 24: Thank you for your participation.

    Thank you for your participation. For further questions, contact: IR@aurubis.com

  25. Slide 25: Your IR contacts

    Your IR contacts Angela Seidler Elke Brinkmann Ferdinand von Oertzen VP Investor Relations & Head of Investor Relations Senior Manager Investor Relations Corporate Communications +49 40 7883-2379 +49 40 7883-3179 +49 40 7883-3178 e.brinkmann@aurubis.com f.vonoertzen@aurubis.com a.seidler@aurubis.com

  26. Slide 26: Financial calendar

    Financial calendar − 2022/23 Annual Report December 6, 2023 − AGM February 15, 2024 Aurubis Twelfth German Corporate Conference 2023

  27. Slide 27: Maintenance shutdowns in the next years

    Maintenance shutdowns in the next 3 years EBT effect from maintenance shutdowns (in € million) FY 2022/23 FY 2023/24 FY 2024/25 Smelter May/ maintenance ~36 June 2024 Hamburg Smelter May/ May/ maintenance ~20 ~35 June 2023 July 2025 Pirdop Anode Nov/ Nov/ Nov/ furnace ~7 ~8 ~8 Dec 2022 Dec 2023 Dec

  28. Slide 28: Aurubis at a glance

    Based in Hamburg, Aurubis AG The company’s main expertise Aurubis develops its leading market is in optimally processing position with a responsible concentrates and recycling at a glance approach to the environment, raw materials with people, and resources complex qualities The company, which was f

  29. Slide 29: Primary copper production process

    Primary copper production process Sulfuric acid plant Off-gas cleaning Copper scrap Copper concentrates Copper matte Blister copper (64 % Cu) (98 % Cu) Flash smelter Converter Anode furnace Copper Nickel sulfate (99.5 % Cu) Anode Cathode Anode slime Anode casting wheel Tankhouse Precious metal refin

  30. Slide 30: Disclaimer

    Disclaimer Forward-looking statements This document contains forward-looking statements that involve risks and uncertainties, including statements about Aurubis’ plans, objectives, expectations, and intentions. Readers are cautioned that forward-looking statements include known and unknown risks and