    Adex Mining Inc. – TSX-V: ADE • Adex is a Canadian mining company • Focus: to develop specialty metals at the Mount Pleasant Mine in New Brunswick, Canada • Total 12-year revenue: Cdn $1.5 billion • World’s largest indium resource • North America’s largest tin resource 2

  3. Slide 3: Forward-looking statements

    Slide 3: Forward-looking statements

    Forward-looking statements Certain statements in this Presentation may constitute “forward-looking” statements which involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Corporation, or the industry in which it operat

  4. Slide 4: Registered confirmation of resources

    Slide 4: Registered confirmation of resources

    Registered confirmation of resources Fire Tower Zone (FTZ) There is an NI 43-101-compliant indicated resource of 13,489,000 tonnes at 0.33% tungsten (WO3), 0.21% molybdenum (MoS2) and 0.06% bismuth (Bi) at the FTZ as outlined in the NI 43-101-compliant technical review of the Mount Pleasant Property

  5. Slide 5: Overview

    Slide 5: Overview

    Overview • Investment overview • Adex advantages – Strong demand – Low risk – Location and infrastructure • Ore deposit overview • Financials • Milestones 5

  6. Slide 6: Investment overview

    Slide 6: Investment overview

    Investment overview Property totals – from Preliminary Economic Assessment Pre-production capital Cdn $200 million Revenue – 12 years Cdn $1.5 billion Cash flow Cdn $802 million IRR (North Zone/ Fire Tower Zone) 28% 6

  7. Slide 7: Adex advantages

    Slide 7: Adex advantages

    Adex advantages • Strong metal demand • Low-risk operating and financial environment • Excellent location and infrastructure 7

  8. Slide 8: Strong demand

    Slide 8: Strong demand

    Strong demand • Flat-panel displays “Raw-material shortages – mobile phones, and higher prices are likely computers, TVs after the global recession spurred companies to delay • Next generation of or cancel projects. [We] photovoltaic cells favor molybdenum, titanium, indium, and rare-earth • Recent

  9. Slide 9: Strong demand – Indium

    Slide 9: Strong demand – Indium

    Strong demand Indium 1200 1000 800 600 Monthly Average Price US$ per KG 400 200 0 9

  10. Slide 10: Strong demand

    Slide 10: Strong demand

    Strong demand • Solder, tinplate, and other “Longer term outlook for tin industrial uses looks very encouraging [due • Organotin compounds in to] growing demand for electrical and electronic PVC plastics applications and growth in • Minable tin may run out in traditional uses.” 20 years Libertas Par

  11. Slide 11: Strong demand – Tin

    Slide 11: Strong demand – Tin

    Strong demand Tin 30 25 20 15 Monthly Average US$ 10 per KG 5 0 05-Apr-04 05-Apr-05 05-Apr-06 05-Apr-07 05-Apr-08 05-Apr-09 05-Apr-10 11

  12. Slide 12: Strong demand

    Slide 12: Strong demand

    Strong demand • Strong future Chinese “Demand for zinc will be led demand, attributable to by China, growing at an the automotive sector’s estimated 8% in 2010, to need for galvanized steel almost 4.5 million tonnes.” • Also used as a white pigment in paint, a fire VM Group research for Fortis Bank

  13. Slide 13: Strong demand – Zinc

    Slide 13: Strong demand – Zinc

    Strong demand Zinc 5 4.5 4 3.5 3 2.5 2 Monthly Average Price 1.5 US$ per KG 1 0.5 0 05-Apr-04 05-Apr-05 05-Apr-06 05-Apr-07 05-Apr-08 05-Apr-09 05-Apr-10 13

  14. Slide 14: Strong demand

    Slide 14: Strong demand

    Strong demand • Has the highest melting point of any metal “Projected growth in tungsten consumption over • Used in drill bits, saw the next five years [2009 to blades, ammunition, 2013] will require… a 32% chrome-plating substitute, increase in current production.” jewelry, incandescent Hayward Sec

  15. Slide 15: Strong demand – Tungsten

    Slide 15: Strong demand – Tungsten

    Strong demand Tungsten 300 250 200 150 Monthly Average Price 100 US$ per MTU 50 0 05-Apr-04 05-Apr-05 05-Apr-06 05-Apr-07 05-Apr-08 05-Apr-09 05-Apr-10 15

  16. Slide 16: Strong demand

    Slide 16: Strong demand

    Strong demand • Specialty steels “A robust auto market in • Moly-based lubricants for China is fueling some of the exploration drilling demand for steel. January saw an increase of • Nuclear reactor passenger car sales in condenser tubes (new China of 115.5%, while auto application) sales in India r

  17. Slide 17: Strong demand – Molybdenum

    Slide 17: Strong demand – Molybdenum

    Strong demand Molybdenum 100 90 80 70 60 50 40 Weekly 30 Average Price US$ per KG 20 10 0 28-Apr-00 28-Apr-01 28-Apr-02 28-Apr-03 28-Apr-04 28-Apr-05 28-Apr-06 28-Apr-07 28-Apr-08 28-Apr-09 28-Apr-10 17

  18. Slide 18: A rich metals inventory

    Slide 18: A rich metals inventory

    A rich metals inventory NNW SSE North Zone Fire Tower Zone (past-producer of tungsten: 1983-85) Indicated resource 10.9 Mt Sn, In, Zn Indicated resource 13.5 Mt W, Mo Inferred resource 7.6 Mt Sn, In, Zn Inferred resource 0.8 Mt W, Mo No. 1-5 Sn Lod oo Saddle Zone ce dj : Upper Deep N Tin Zone X Nort

  19. Slide 19: Resource summary

    Slide 19: Resource summary

    Resource summary Weight (%) NI 43-101 Resources: * 2 x “ 23 29 Mount Pleasant Property Sn In Z Mo Cu 13,489,000 tonnes 8, (Indicated, 2008) na nia n/a 0.21 0.33 0.06 n/a ae é 841,700 tonnes it , (Inferred, 2008) n/a n/a n/a 0.2 0.26 0.04 n/a 10,882,000 tonnes © 882, & (indicated, 2009) 0.43 67.8 g/t

  20. Slide 20: Low risk

    Slide 20: Low risk

    Low risk • Revenues from early mine production will make a significant capital contribution • Will mitigate much of the risk associated with future financing 20

  21. Slide 21: Location

    Slide 21: Location

    Location New \ Brunswick Québec Woodstock oe McAdam — USA @ ’ Mount ¥%&/ \ | \ Pleasant | Sy St. Lf Stephen

  22. Slide 22: Infrastructure

    Slide 22: Infrastructure

    Infrastructure • Fully developed mine workings (FTZ) • Crushing and processing complex • Administration building, maintenance shops, warehouse, ore storage etc. • On-site power and water distribution • Established tailings pond • Estimate replacement cost Cdn $84 million 22

  23. Slide 23: Infrastructure

    Slide 23: Infrastructure

    Infrastructure ‘i \\) Crushing and Engineering/ processing ore storage — complex Conve cones

  24. Slide 24: North Zone – Status

    Slide 24: North Zone – Status

    North Zone – Status Completed • Identified 18.5 million tonnes indicated and inferred (43-101 compliant estimate) • Finished preliminary economic assessment January 2010 Underway • Piloting tin and indium–zinc concentrate production – SGS • Piloting zinc metal and indium sponge production – Thibault

  25. Slide 25: North Zone – Status

    Slide 25: North Zone – Status

    North Zone – Status Mine plan • Decline access to underground • Open-stope mining with truck haul to surface • Mechanized trackless equipment • Multi-skilled workforce • 3.1 million tonnes over 10 years Mill production plan • Zinc–indium concentrate (flotation) • Hydromet circuit to make zinc metal

  26. Slide 26: NZ – Production stats

    Slide 26: NZ – Production stats

    NZ – Production stats From 2010 Tin Zinc Indium Preliminary Economic Assessment Concentrate Metal Sponge In the mill Feed grade 0.71% 1.82% 183 g/t Concentrate grade 46% 50% 4,900 g/t Metal recovery 75% 79% 75% Final products Total production 3,200 t/y 4,000 t/y 40 t/y Price - 2010 preliminary asses

  27. Slide 27: North Zone – Financials

    Slide 27: North Zone – Financials

    North Zone – Financials Mine life – current plan 10 years Production rate 850 t/d (Cdn $ Millions) Pre-production capital 71 Annual revenue 48 Annual operating cost 23 Annual cash flow 25 Pre-tax NPV @ 8% 80 Pre-tax IRR 29% 27

  28. Slide 28: Fire Tower Zone – Status

    Slide 28: Fire Tower Zone – Status

    Fire Tower Zone – Status Completed • Identified 14.3 million tonnes indicated and inferred (43-101 compliant estimate) • Finished preliminary economic assessment 2008 Underway • Bench-testing moly oxide hydromet – SGS (Lakefield) Upcoming • Pilot plant testwork – 2011 • Definitive feasibility – 2011

  29. Slide 29: Fire Tower Zone – Status

    Slide 29: Fire Tower Zone – Status

    Fire Tower Zone – Status Mine plan • Vertical crater retreat • Underground primary crushing • Conveyor to surface • 10 million tonnes over 12 years Mill production plan • Tungsten gravity/flotation • Tungsten concentrate into APT • Molybdenum flotation and impurity leach 29

  30. Slide 30: FTZ – Production stats

    Slide 30: FTZ – Production stats

    FTZ – Production stats From 2008 Tungsten Molybdenum Preliminary Economic Assessment Concentrate In the mill WO3 MoS2 Feed grade 0.33% 0.21% Concentrate grade 30% 80% Metal recovery 82% 76% Final products APT MoS2 Total production 1,900 t/y 1,100 t/y Price - 2008 preliminary assessment ($US/kg) 21.5

  31. Slide 31: Fire Tower Zone – Financials

    Slide 31: Fire Tower Zone – Financials

    Fire Tower Zone – Financials Mine life – current plan 12 years Production rate 2,400 t/d (Cdn $ Millions) Pre-production capital 130 Annual revenue 92 Annual operating cost 49 Annual cash flow 46 Pre-tax NPV @ 8% 164 Pre-tax IRR 27% 31

  32. Slide 32: Milestones

    Slide 32: Milestones

    Milestones 2008 2009 Completed 2008 drilling program, including Updated 43-101 compliant resource more than 13,000m of drilling estimate for NZ Completed preliminary assessment (scoping) on Sn-In-Zn at NZ Updated NI 43-101 compliant resource estimate for the Fire Tower Zone Developed a staged approa

  33. Slide 33: Milestones

    Slide 33: Milestones

    Milestones 2010-2011 Pilot plant program – production of indium sponge and zinc metal Pilot plant program – production of tin and indium-zinc concentrates Conclude concentrate and metal off-take sales contracts Confirmation drilling and upgrade of NZ inferred resources to indicated resources NZ defi

  34. Slide 34: Mount Pleasant development plan

    Slide 34: Mount Pleasant development plan

    Mount Pleasant development plan Activity 2010 2011 2012 2013 2014 Feasibility study North Zone Construction Commence production Metallurgical testwork Fire Tower Zone Feasibility study Construction Commence production Pre-production capital – North Zone: Cdn $71 million; Fire Tower Zone: Cdn $130 mi

  35. Slide 35: Leadership team

    Slide 35: Leadership team

    Leadership team J. Errol Farr, CMA President and Mr. Farr is a seasoned executive with over 15 years of CEO, Director experience in finance, accounting and operations with publicly listed junior mining companies. Mr. Farr has been involved with Adex Mining Inc. since its acquisition of Mount Pleasan

  36. Slide 36: Leadership team

    Slide 36: Leadership team

    Leadership team William (Bill) B. Technical Mr. W.B. Burton founded Adex in 1993 and was CEO Burton Advisor, from 1994 to 1998. He has worked extensively with a BSc (Hon.) Geology Director number of publicly traded mining and industrial companies and is currently President, CEO and a director of Mag

  37. Slide 37: Financial information

    Slide 37: Financial information

    Financial information Share structure Issued and outstanding shares 96,526,026 as of Fully diluted share structure 109,473,689 Oct. 4th, 2010 Fully diluted market $10,947,369 capitalization Current share price $ 0.10 52-week range Cdn $0.195–$ 0.08 Debt None Adex Share Price 0.2 0.15 0.1 0.05 0 Clos

  38. Slide 38: Summary of investment opportunity

    Slide 38: Summary of investment opportunity

    Summary of investment opportunity • Excellent location • Established infrastructure • Stable political environment • Low-risk strategies for staged development and financing • Predictable yields at target grade • Well-timed to take advantage of economic recovery and growth 38

  39. Slide 39: For more information

    Slide 39: For more information

    For more information Please contact: Errol Farr, President and CEO Adex Mining Inc. 67 Yonge Street, Suite 1402 Toronto, Ontario, M5E 1J8 efarr@adexmining.com 1-416-941-9663 Investor Relations 1-866-508-2339 investorrelations@adexmining.com www.adexmining.com 39

Source: Internet Archive copy of adexmining.com

More decks from Adex Mining Inc.

All 10 Adex Mining decks