Wesizwe Platinum Limited · JSE:WEZ

Wesizwe Platinum — Shareholder Meeting (July 2012)

27 slides from Wesizwe Platinum's shareholder meeting presentation, Jul 19, 2012

  1. Slide 1: Full Steam Ahead

    FULL STEAM AHEAD ANNUAL GENERAL MEETING - 19 July 2012 CEO – MR. JIANKE GAO

  2. Slide 2: Introduction

    INTRODUCTION • Wesizwe is forging ahead with the development of the Bakubung Platinum Mine. • Very Significant Milestones achieved to date. • Strategic equity partner and funder still committed to ensure that the project is funded through to full production. • Strategies submitted and approved perio

  3. Slide 3: Clean Ownership Structure

    CLEAN OWNERSHIP STRUCTURE STRATEGIC OVERVIEW – JULY 2012 3

  4. Slide 4: Vision and Purpose

    VISION AND PURPOSE VISION To become a significant multi-commodity company, focusing on strategic metals with sound derived demand fundamentals PURPOSE To create shareholder value in an environmentally responsible and sustainable manner based on long-term relationships with government and local commu

  5. Slide 5: Key Strategic Objectives

    KEY STRATEGIC OBJECTIVES • To ensure that the Bakubung Platinum Mine is delivered within budget and on schedule. • To explore synergies with industry peers on consolidation opportunities in the vicinity of the Bakubung Platinum Mine • To achieve 26% BEE ownership by 2014 ƒ Various options being cons

  6. Slide 6: Wesizwe Share Price Performance

    WESIZWE SHARE PRICE PERFORMANCE STRATEGIC OVERVIEW – JULY 2012 6

  7. Slide 7: The Journey Has Started

    THE JOURNEY HAS STARTED STRATEGIC OVERVIEW – JULY 2012 7

  8. Slide 8: Perfectly Located Quality Resource

    PERFECTLY LOCATED QUALITY RESOURCE Western Limb provides 67% of the world’s platinum High quality resource…at the centre of platinum gravity of the Western Bushveld, which is a fully explored, quality new mining area Flat lying, thick reef • Easier, more efficient mining • Amenability to mechanisati

  9. Slide 9: Key Asset Differentiators

    KEY ASSET DIFFERENTIATORS • Shallow in relation to other producers: mean mining depth of 850mbc • High mining extraction – 74% • Thick reef widths - 1.4m to 1.7m - higher operating efficiency and yields • Favourable prill split – good Pt yield from Merensky reef, improved basket value • Head grades

  10. Slide 10: Highly Favourable Prill Split

    HIGHLY FAVOURABLE PRILL SPLIT Merensky prill split, UG2 prill split without Ruthenium (Bakubung) (Bakubung) Au g/t, Rh g/t, Au g/t, 3.8% 4.6% Rh g/t, 0.4% 10.6% Pd g/t, 26.9% Pd g/t, 29.2% Pt g/t, Pt g/t, 64.7% 59.7% MERENSKY ƒ Pt to Pd Ratio: 2,42 ƒ Ratio is one of the highest in the industry STRAT

  11. Slide 11: Site View – March 2012

    SITE VIEW – MARCH 2012 STRATEGIC OVERVIEW – JULY 2012 11

  12. Slide 12: Delivery on Mine Development Milestones

    DELIVERY ON MINE DEVELOPMENT MILESTONES • Apr 2011: First blast for box cut and winder house foundation • Jul 2011 : TWP appointed EPCM contractor to June 2012 • Sep 2011: Award full scope civil earthworks and concrete for mine area, winder-house and winder foundations, and shafts collaring • Nov 20

  13. Slide 13: Site Progress – March 2012

    SITE PROGRESS – MARCH 2012 STRATEGIC OVERVIEW – JULY 2012 13

  14. Slide 14: Significant Activity on Site

    SIGNIFICANT ACTIVITY ON SITE • Vent shaft collar and backfill completed, main shaft collar making good progress • All critical winders refurbished - installation and commissioning underway • Eskom sub-station near completion, supply installation on track • Shaft sinker given access to portion of the

  15. Slide 15: Site Progress – May 2012

    SITE PROGRESS – MAY 2012 STRATEGIC OVERVIEW – JULY 2012 15

  16. Slide 16: Focused on Mine Development Milestones

    FOCUSED ON MINE DEVELOPMENT MILESTONES • Jun 2012: Ventilation # pre-sink start • Sept 2012: Eskom Phase 1 commissioned • Aug 2012: Shaft civils complete • Oct 2012: Main # pre-sink start • Jan 2013: Ventilation # main sink start • Jun2013: Main # main sink start • Apr 2018: Main # commission • Jun

  17. Slide 17: Capex Summary

    CAPEX SUMMARY STRATEGIC OVERVIEW – JULY 2012 17

  18. Slide 18: Escalation per Commodity

    ESCALATION PER COMMODITY STRATEGIC OVERVIEW – JULY 2012 18

  19. Slide 19: Possible Synergy Opportunities

    POSSIBLE SYNERGY OPPORTUNITIES • Infrastructure/bulk services: water and power supply • Feasibility studies being completed on concentrator plant synergy (PTM / Maseve) • Sharing concepts for employee housing programme • Proposing joint training and skills development centre in the area • Community

  20. Slide 20: Investor Relations Strategy

    Investor Relations Strategy • The new Investor Relations Strategy has been developed to respond to – Wesizwe’s need to positively reposition the company, its brand and its leadership in the marketplace – and to engage all key stakeholders proactively in the realisation of its vision, mission and bus

  21. Slide 21: Investor Relations Strategy: Business Challenges

    Investor Relations Strategy Business Challenges to be addressed • Reputational impact on the company share price • Community based challenges. • Low brand visibility in the immediate competitor environment and in the market sector as a whole • Reputational management in the face of the above challen

  22. Slide 22: Human Resources

    HUMAN RESOURCES • At full production, the Bakubung Platinum Mine will employ 3200 employees • Current average employment (six months): 42 employees and 460 contract workers • YTD average of 27% local employment vs. 20% commitment in the social and labour plan • Large contractors are fully committed

  23. Slide 23: Skills Development

    SKILLS DEVELOPMENT • Investment in skills development a key component of human resources development • As at May 2012, our HR development expenditure was 3% of payroll - well on-track to meet 4% Mining Charter target • Wesizwe has 23 bursars in 2012: – 12 apprenticeships (four-year artisan programs)

  24. Slide 24: Social and Labour Plan (SLP)

    SOCIAL AND LABOUR PLAN (SLP) • Over R25 million has been spent on SLP to date • Projects have included: • Agricultural project • Education support (Schools infrastructure program, ABET, portable skills training) • Water tanks and permanent water supply solution for Ledig community • New SLP is being

  25. Slide 25: Formal Stakeholder Engagement Processes Are in Place

    FORMAL STAKEHOLDER ENGAGEMENT PROCESSES ARE IN PLACE Community • Perception survey conducted to inform ongoing engagement strategy • Stakeholder Engagement Forum set-up • Traditional leadership challenges in the community Government • Programme in place for communication with all tiers of government

  26. Slide 26: Conclusion

    CONCLUSION • Tremendous management focus and good progress on delivering the Bakubung Platinum Mine • Strategy Approved • Continuous evaluation of Project Synergies. • Relationship with Communities and Government • Progress on becoming a multi-commodity company. • Share value & Market capitalization

  27. Slide 27: Thank You

    THANK YOU STRATEGIC OVERVIEW – JULY 2012 27

Wesizwe Platinum — Shareholder Meeting (July 2012) on 6ix