Perseus Mining Limited · ASX:PRU

Perseus Mining — Africa Downunder 2012

26 slides from Perseus Mining's conference presentation, Aug 29, 2012

  1. Slide 1: Targeting +400,000oz Gold Production From 2014

    For personal use only Targeting +400,000oz Gold Production From 2014 August 2012 Mark Calderwood CEO

  2. Slide 2: Competent Person's Statement and Forward-Looking Statements

    Competent Person’s Statement Information in this presentation that relates to exploration results, mineral resources or ore reserves is based on information compiled by Mr Mark Calderwood, who is a Chartered Professional Member of The Australasian Institute of Mining and Metallurgy. Mr Calderwood is

  3. Slide 3: Perseus the Company

    Perseus the Company Track Record; = / = / ¢ Exploration - 16 Years in West Africa discovered 9Moz > * Development — Edikan Gold Mine built on time & on budget ) * Production - Evolved into a miner and producer in past 18 | months i Large, low risk (open pit and free milling) high-margin projects 2nd

  4. Slide 4: Targeting low total cost and high IRR projects

    Targeting low Total Cost* (S900) and high /RR (+30%) projects to maximise return Continuous optimisation of existing projects Reduce risk - Experienced team, focus, steady growth, low gearing Corporate responsibility, building a long term presence in West Africa Total Cost* defined as exploration-ac

  5. Slide 5: Capital Structure

    TY A Aut = JAN) Capital Structure Shares on Issue Unlisted Options (avg. AS2.96) June 30 2012 Financials FY2012 Profit (after tax) Cash (30 June ‘12) +Bullion (30 June ‘12) Total Borrowings As at June 30 2012, hedging 190koz over 3 years at avg. $1,256/oz, represents 5% of reserves 90-day share turn

  6. Slide 6: 7.0Moz in M&I Resources

    7.0Moz (87% in Ghana) in M&I Resources (197Mt at 1.1g/t) Including 4.0Moz (84% in Ghana) in Reserves (104Mt at 1.2g/t) Additional 2.2Moz (88% in Ghana) in Inferred Resources (74Mt at 0.9g/t) Updates Céte d’lvoire — Q2, 2012 Ghana — Q2, 2013 Rounding applied, see pages 23,24 for details

  7. Slide 7: For personal use only

    For personal use only

  8. Slide 8: Ashanti Belt

    Ashanti Belt (— > 650 sq km total holding in rich Ashanti gold belt Edikan Gold Mine, Grumesa Meas. & Ind. 6.1Moz -182Mt Inf. 2.0Moz - 67Mt Significant exploration upside - years of drilling ahead |

  9. Slide 9: Edikan deposits and resources map

    ESUAJAH SOUTH ABNABNA FOBINSO | BOKITSI Mill sit? 77 2: y Resources © Current Production Pits

  10. Slide 10: For personal use only

    For personal use only

  11. Slide 11: Edikan Gold Mine

    Edikan Gold Mi Large deposits - 80m wide ore bodies bulk mineable Open pit operations (W:O 3.4:1 ) Large mill, ramping up to 8mtpa Low cost, low consumer of power, cyanide, grinding, media Favourable recovery at coarse grind, currently 85%- 90%, increasing to 92% as oxides reduce Resources, M&I 5.6M

  12. Slide 12: EGM - June Quarter Operating Highlights

    EGM - June Quarter Operating Highlights » Mining = 3.7Mbcm of ore and waste mined 2.1Mt of ore at 1.2g/t Au (down 6%) « Ore stockpile increased to 3.6Mt at 0.8g/t containing 90Koz of gold Mining cost average USS2.70/t of material Processing » 1,15Mt treated (up 12 %) 52,6700z produced (up 36%) » Rec

  13. Slide 13: Edikan Gold Mine - Guidance

    OF Dersam= Edikan Gold Mine - Guidance laseecuniza) [pei] uanstunz) Throughput (dry Mt) 1,450,000 1,700,000 3,600,000 Head grade 1.39g/t 1.43g/t 1.24g/t Gold recovered (02) 55,000-60,000 65,000 - 70,000 125,000 - 135,000 Adjusted C1 cash cost $575 $575 $625 (USS/o0z) Overheads Approximate unit costs

  14. Slide 14: Edikan Gold Mine Simplified Flow Sheet

    Edikan Gold Mine Simplified Flow Sheet 1,200tph capacity Fresh Rock Coarse 1,000tph capacity 400tph capacity 212 micron Flotation Tails FLOTATION 14MW SAG mill, Currently using 12MW. Current milling 750-900tph Flotati trate 35g/t-120g/t r lotation concentrate 35¢/t-120g Ramping up to 1,100tph curren

  15. Slide 15: Environment, OH&S, Host Communities

    Environment OH&S Host Communities Employee training & benefits ‘Australia-Africa Mining Industry Group AAMIG @¥)

  16. Slide 16: Perseus the Explorer

    Meas. Perseus the Explorer »~ Ma&l Resource Growth ~5.8Moz in 4 years : : P&P Reserve Growth ~4.2Moz in 3 years* *Updates Céte d’lvoire — Q4, 2012 Inferred &Ind. Reserves Tengrela | | | Ghana || | |ooad a 2005 2006 2007 2008 2009 2010 2011

  17. Slide 17: Perseus Licences - Cote d'Ivoire

    Perseus Licences - Cote d'Ivoire ~3000 sq km Under explored Sissingué Resource: 0.93Moz M&l; 0.26Moz Inf. Reserve: 0.66Moz Tengrela TENGRELA PROJECT Significant intercepts on multiple prospects Mbengue, Napié Preparing to drill Underexplored Excellent upside potential

  18. Slide 18: Sissingué Gold Project Status

    Sissingué Gold Project Status Permitting Completed * Environmental and Social Impact Assessment approved by Ivorian National Environmental Agency (ANDE) * Exploitation Permit granted August 2012 Detailed design/tenders * Detailed design approximately 90% complete * All key equipment selected and pri

  19. Slide 19: Sissingue Processing Plant

    Sissingue Processing Plant Capital budget US$115M (Nov 2010 estimate) * Tendered equipment prices in line with expectations * Optional additional US$33M for HV power line to connect the mine to national power grid. * Project expenditure to date totals USS9.2 million * Preparation underway for early

  20. Slide 20: Sissingué Feasibility

    Sissingué Feasibility Reserve Target Cash Cost* (C1) 657koz 340koz US$421/0z at USS$950 gold price in first 2 years in first two years 3.5Mt at 3.5¢/t Au L | r 1 First 6 months Next 12 months Next 30 months 700kt at 2.0g/t 1,760kt at 4.52¢/t Au 2.0g/t commissioning Additional reserves over the next

  21. Slide 21: Perseus The Future

    Perseus The Future Ramp up Edikan Gold Mine - increase throughput beyond name plate and continue to grow reserves Develop and grow Sissingué - bring mine into production in 2013, currently stepping up exploration and resource/reserve drilling on Sissingué and satellite prospects Exploration experien

  22. Slide 22: Mineral Resources

    Mineral Resources Mineral Resources (Gold) Including Reserves Edikan Gold Mine 49.5 1.5 2,378 38.2 1.3 1,813 24.9 1.4 1,111 >0.8g/t Edikan Gold Mine 34.2 0.7 718 34.5 0.6 706 25.7 0.7 602 0.4g/t - 0.8g/t Grumesa 25.1 0.6 471 16.4 0.5 247 >0.4 Tengrela 0.9 3.2 90 9.1 2.5 706 3.3 1.7 171 >1.0g/t Tengr

  23. Slide 23: Mineral Reserves

    Mineral Reserves_ Mineral Reserves (Gold) Edikan >0.4g/t 64.6 1.2 2,417 29.2 1.0 961 93.8 11 3,378 Tengrela >0.55g/t 9.7 2.1 657 9.7 2.1 657 Total 64.6 1.2 2,417 38.9 1.3 1,618 103.5 1.2 4,035 Notes *As at December 2010; +Edikan >0.4g/t Au cut-off for Abnabna-Fobinso, >0.5g/t Au cut-off for all othe

  24. Slide 24: EGM Section - High-grade & Low-grade zones

    EGM Section - High-grade & Low-grade zones Esuajah South pee seat Section 6,300N a Fetish {) Granite vA Section 5,240N 24

  25. Slide 25: Sissingue Section

    Sissingue Section 33m incl, Tim i 3.6g/t 8.3git 32m 48m @ 0.9g/t 1.3git 4m @ 1.7g/t 8m @ 1.6g/t 47m @ 34g) 3m @ 1.3g/t 45m @ 2.3git' 10m @ 2.7g/ 110m @ 4.0g/t incl. 16m @ 11.3g/t 8m @ 1.0g/t 6m @ 475g/t 320mRL. 10m @ 4.5g/t om @ 1.89) gents 2m @ 25.0g/t 9m @ 0.6g/t (0m @ 1.6g/t — 240mRL 40m — Sissin

  26. Slide 26: Cluster Target Analysis - Eastern Group, Edikan

    Cluster Target Analysis - Eastern Group, Edikan GRADIENT IP/Resistivity - Cluster Analysis Legend Very Low Resistivity and Chargeability; Graphitic or carbonaceous. 6 > metasediments. The high-pass filtered Resistivity is generally high, possibly indicating the presence of resistive axes at depth (i