Aurelia Metals Limited · ASX:AMI

Aurelia Metals — Corporate Update (February 2025)

23 slides from Aurelia Metals's corporate update, Feb 18, 2025

  1. Slide 1: CCC Presentation Hera-Federation Complex Project Update

    CCC Presentation Hera-Federation Complex Project Update 18 February 2025 ASX Code: AMI

  2. Slide 2: Acknowledgement of Country

    Acknowledgement of Country • Aurelia Metals Ltd respectfully acknowledges the Ngiyampaa Nation as the Traditional Custodians of this land – both past and present. • We know this land has history, custodians and stories, spanning tens of thousands of years, that endure to this day. • We pay our respe

  3. Slide 3: Federation Hera Complex Progress

    3 Federation Hera Complex Progress ì ō₉ Ĵ ǻȘ  �´  Ϊ �L ẅ ť �Ŷ�¤Șẅ ō ť ẅ� • Ore transport between Federation and Peak Commenced on the 20th November 2024. Trucking is occurring under temporary permit from TfNSW. • No haulage has secured since mid January, and it is scheduled to recommence aro

  4. Slide 4: Federation Hera Complex Progress

    4 Federation Hera Complex Progress New magazine commissioned January 2025

  5. Slide 5: Federation Hera Complex Progress

    5 Federation Hera Complex Progress New aerial Imagery acquired for Hera Federation :

  6. Slide 6: Federation Hera Complex Progress

    6 Federation Hera Complex Progress Ø Φ� ōǻ�¤Ś   ōΪ �₉ ŏ ǻō ₎ �Ŷō�¡  ō�s  ₎  ōẅǻŶȘ ��Φẅ ō�Ś Ș   Ś  Ș ẅ�₎ Ś �

  7. Slide 7: Federation Hera Complex Progress

    7 Federation Hera Complex Progress Ø Φ� ōǻ�¤Ś   ōΪ �₉ ŏ ǻō ₎ �Ŷō�ØΪ Ś    ��

  8. Slide 8: Federation Mine Development

    8 Federation Mine Development Federation development 25 November 2024

  9. Slide 9: Federation Mine Development

    9 Federation Mine Development Federation development 1 February 2025

  10. Slide 10: Environment and Community

    Environment and Community 18 February 2025 ASX Code: AMI

  11. Slide 11: Environment and Community: Project Approval Modification

    11 Environment and Community Project Approval Modification Modification 2: • As reported at the last CCC meeting the company is seeking approval to modify the project approval • to increase the project's of ore trucked to the Peak, • increase trucking numbers and increase trucking hours from 7pm to 10

  12. Slide 12: Environmental Priorities, Improvement Initiatives and Complaints

    12 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Priorities and improvement initiatives • To minimise dust in the camp and exploration core yard, plans are in pace to bitumen the road past camp and trial long term road stabilising products in other areas

  13. Slide 13: Groundwater Monitoring

    13 Groundwater Monitoring Groundwater monitoring completed in December. Quarterly SWL for Hera Bores. Quarterly SWL and water quality for Federation bores

  14. Slide 14: Air Quality Monitoring network

    14 Air Quality Monitoring network

  15. Slide 15: Air Quality – HVAS PM 10

    — Air Quality - HVAS PM,, 60.0 50.0 40.0 g = 30.0 = Qq 20.0 “|| Il | | | | AM | oo ull ll l.. lt ll b & b b be b db be bd b am oh oh a cm ch a com ah ah om oh oh ah oi cs oss rs a % 0h As BP a ss pF cs ov DOT gy OE BP ADP ah Th I gah ah gph PB gah WP” gh wh” gal” apt mmm PM-10 (g/m?) ——PM10 limit au

  16. Slide 16: Air Quality – HVAS TSP

    16 — Air Quality - HVAS TSP 140 120 40 Mull HH, lu II a> Oo TSP (ug/m*) Db » bak oh ob oo ‘ey oo ery os Riss ste oe ” re ay mTSP (ug/m*) aurelia

  17. Slide 17: Air quality - EBAM

    17 Air quality - EBAM EBAM average daily concentrations of PM10. Comparison to NEPM criteria

  18. Slide 18: Air Quality – E-Sampler

    18 Air Quality – E-Sampler 1 E-Sampler 1 has had intermittent issues resulting in poor data capture. The sampler was replaced on 31st January 2025

  19. Slide 19: Air Quality – E-Sampler

    19 == — Air Quality - E-Sampler 2 70 60 50 40 30 PM1 (ug/m) 20 aurelig*.

  20. Slide 20: Trucking to Peak

    20 Trucking to Peak Trucking to Peak commenced in November 2024. Transport of ore was undertaken 21st November to 19th December. Trucking is planned to recommence 24th February 2025. Note – Return trip from Federation to The Peak is counted as two movements. Average Total quantity Month No. movement

  21. Slide 21: Blasting

    21 Blasting Blast monitoring recommenced in November 2024. Number of blasts each month were: November – 66 December – 69 January – 63 No exceedances were recorded.

  22. Slide 22: Exploration

    Exploration 18 February 2025 ASX Code: AMI

  23. Slide 23: Exploration

    23 Exploration • “Nymagee Mine” is the current focus for exploration in Nymagee area. • For the calendar year 2024 - 4634.67m drilled • 3000m meters planned for the rest of the 25 FY