  1. Slide 1: Grand Canal Industrial Estates Inc. (GCIE) Berbice Deep Water Port

    Grand Canal Industrial Estates Inc. (GCIE) Berbice Deep Water Port October 2020

  2. Slide 2: GCIE: Wholly Owned Subsidiary of CGX Energy Inc.

    GCIE: Wholly Owned Subsidiary of CGX Energy Inc. CGX Energy Inc. (Ontario) 100% 100% 100% 62% CGX Energy CGX Resources GCIE Holdings Management ON Energy Inc. Inc. Ltd. Corp. (Guyana) (Bahamas) (Barbados) (Delaware) CGX Resources Inc. Grand Canal (Guyana Industrial Estates 100% Registered 100% Inc.

  3. Slide 3: GCIE – Company Details

    GCIE – Company Details • Grand Canal Industrial Estates Inc. incorporated in Guyana on 30th June 2010 • Registered office at 234 Lance Gibbs and Irving Streets, Georgetown. Principal activity is to build and operate the Berbice Deep Water Port on the Berbice River in Guyana • GCIE acquired a Governm

  4. Slide 4: GCIE Vision

    GCIE Vision • Berbice Deep Water Port servicing: • Oil and Gas Exploration • Oil and Gas Production • Phase 1 (Target: Oct 2020 to Dec 2021): • Agricultural export • 91m x 30m wharf platform built out into the channel and accessed via a 49m long, 12m wide trestle. • Containerized • Facility targets

  5. Slide 5: Factors Motivating Berbice Deep Water Port in Guyana

    Factors Motivating Berbice Deep Water Port in Guyana • Currently, there are two functional Oil and Gas Ports in Guyana • Located South of the Georgetown Harbour. The Demerara River has a depth of 5.5 – 5.9m at low water. Georgetown Harbour is congested with little room for expansion • Stabroek Block

  6. Slide 6: Near Term Phase Objectives: Targeted October 2020 – December 2021

    GCIE Near Term – Phase 1 Objectives: Targeted October 2020 – December 2021 Build and operationalize initial phase of the Berbice Deep Water Port to service the highly active offshore oil and gas exploration industry in the Guyana-Suriname Basin • 91m x 30m wharf platform and 49m x 12m approach trest

  7. Slide 7: Berbice Deep Water Port Targeted Expansion: December 2021 - December 2025

    Berbice Deep Water Port Targeted Expansion: December 2021 - December 2025 This targeted expansion will support: • Oil and Gas operations and production support • Agricultural export • Containerized import/export • Cruise ship docking • Regional shipping www.cgxenergy.com 7

  8. Slide 8: GCIE Site Advantages

    GCIE Site Advantages • GCIE selected this site for its shore-base and port facility based on the following: • Berbice River is one of three major rivers in Guyana – 600 kilometres long, and 2.3 kilometres wide at the project location • Berbice River channel is currently dredged and maintained at a d

  9. Slide 9: GCIE Site Advantages

    GCIE Site Advantages • In 2010, Guyana Lands and Surveys Commission in its land use planning map for Region 6 list the area for the development of a deep sea port, new airport runway of 1.2km and an industrial park • The GCIE location can also service import/export of agricultural and other goods wh

  10. Slide 10: Thank You

    Corporate Office Houston Office Guyana Office 333 Bay Street, Suite 1100 810 Highway 6 South, Suite 240 234 Lance Gibbs and Irving Toronto, ON, Canada M5H 2R2 Houston, TX, USA 77079 Streets, Queenstown, +1 (416) 364-5569 +1 (832) 300-3200 Georgetown, Guyana +011 (592) 225-5038 www.cgxenergy.com Than