Monument Mining Limited · TSXV:MMY

Monument Mining — Investor Presentation (June 2022)

24 slides from Monument Mining's investor presentation, June 2022

  1. Slide 1: Corporate Presentation: Executing Value Creation

    Corporate Presentation Executing Value Creation June 2022 TSX–V MMY

  2. Slide 2: Forward Looking Statements

    Forward Looking Statements This presentation includes statements containing forward-looking statements or forward-looking information under applicable Canadian securities laws (hereinafter collectively referred to as “forward- looking statements”) about Monument, its business and future plans. Forwa

  3. Slide 3: Corporate Summary

    Corporate Summary Undervalued Gold Producer and Explorer ▪ Producing Asset: Malaysia – 330.7 koz produced since 2010, 1mtpa plant, 6-yr LOM extension underway ▪ Exploration Portfolio: Western Australia – existing resources, 260 ktpa gold plant on C&M ▪ Resource Base (NI 43-101 compliant): 880 koz1 S

  4. Slide 4: Board of Directors & Founder

    Board of Directors & Founder Robert Baldock Graham Dickson Cathy Zhai FOUNDER Chairman of the Board Director, President & CEO Zaidi Harun Michael Kitney Dato’ Sia Hok Kiang Jean-Edgar de Trentinian Director, VP Business Director Director Director Development TSX–V MMY 4

  5. Slide 5: Core Operations

    Core Operations Producing Asset - Malaysia Exploration/Development - Australia 330.7Koz Au PRODUCED Selinsing Gold Portfolio 150km2 880 koz Murchison Gold Portfolio 230km2 381 koz TSX–V MMY 5

  6. Slide 6: Investment Highlights

    Investment Highlights Undervalued Gold Producer and Explorer Selinsing Gold Mine (Malaysia) ▪ 11 years in production; 330,658 oz of gold produced as of March 31, 2022 PROVEN GOLD PRODUCER ▪ Mineral Resources of 880 koz, including Mineral Reserves of 267 koz Au at 1.45 g/t Murchison Gold Portfolio (W

  7. Slide 7: Implementing Long-Term Growth Strategy

    Implementing Long-Term Growth Strategy Value Creation Through Expansion, Exploration and Acquisitions Targeted Acquisition ▪ Proceed with a disciplined acquisition to increase the Company’s gold production profile M&A Establish Murchison As Cornerstone Asset ▪ Aggressive two-year exploration program

  8. Slide 8: Implementation Timeline & Milestones

    Implementation Timeline & Milestones Strong News Flow Ahead Malaysia • Gold concentrate production • Flotation plant construction commences-October 2022, ramp completion -September 2022 up period till December 2022 June 2022 September 2022 December 2022 March 2023 June 2023 • Completed Phase 2 wrap

  9. Slide 9: Corporate Social Responsibility

    Corporate Social Responsibility Monument takes CSR very seriously and has organised and funded a number of programs within its local communities over the years. Top Left: Financial support for disability programs at the Selinsing Gold Mine Top Right: Sponsorship of a student excellence program at Su

  10. Slide 10: Selinsing Gold Mine Malaysia

    SELINSING GOLD MINE MALAYSIA TSX–V M MMMYY

  11. Slide 11: Selinsing Gold Portfolio

    Selinsing Gold Portfolio Monument’s Selinsing Gold Portfolio is in the Central Gold Belt of Western Malaysia ▪ 158km north of Kuala Lumpur ▪ Total tenement area of 150km2 ▪ Consists of the Selinsing, Buffalo Reef, Felda Land, Peranggih and Famehub properties ▪ 1 million tonne per annum (TPA) gold pr

  12. Slide 12: Selinsing Gold Mine: Low-Cost Producer with Growth Potential

    Selinsing Gold Mine Low-Cost Producer with Growth Potential Historic Production Figures Selinsing Sulphide Expansion Feasibility Study Start of Production IRR 2010 49% Cash Costs Upfront Capex US$563 Per Ounce US$53M Mill Capacity LoM Production 1 Million Tpa 223 koz Gold Produced Cash Costs 330.7 k

  13. Slide 13: Selinsing-Flotation Plant Construction

    Selinsing-Flotation Plant Construction Transition to Sulphide Gold Treatment with flotation plant construction and mine development currently underway ▪ Estimated construction costs of up to $20 million, production of flotation concentrate is expected to commence in early October 2022 ▪ Construction

  14. Slide 14: Selinsing – Processing Plant Expansion

    Selinsing – Processing Plant Expansion Phased Expansion Strategy with Phase 1 Initial Capital of US$20 Million CONCENTRATE FLOTATION PLANT Initial Flotation ▪ Low capex first stage production Concentrates ▪ Targeting production of flotation concentrate in October 2022 ▪ Production of gold concentrat

  15. Slide 15: Selinsing Resources and Reserves

    Selinsing Resources and Reserves *Proven Reserve is entirely stockpile material **Probable Oxide Reserve is a combination of in situ oxide material occurring in Selinsing and Buffalo Reef/Felda deposits plus Selinsing Old Tailings material; Probable Transition and Sulphide Reserve comprises in situ

  16. Slide 16: Selinsing – Resource Replacement Strategy

    Selinsing – Resource Replacement Strategy Significant Exploration Potential for Long Term Resource Growth Near-Mine Potential ▪ Existing sulphide resources at Selinsing / Buffalo Reef open at depth ▪ Additional near-surface oxide material around Peranggih open pits Regional Exploration Potential ▪ N

  17. Slide 17: Murchison Portfolio Western Australia

    MURCHISON PORTFOLIO WESTERN AUSTRALIA TSX–V M MMMYY

  18. Slide 18: Murchison Portfolio

    Murchison Portfolio Developing A Potential Cornerstone Asset Monument has a highly prospective gold portfolio in WA ▪ Burnakura, Gabanintha and 20% Tuckanarra free carried JV interest, historic resources of 644koz with 381koz confirmed, multiple historical producing pits 500koz delivered ▪ Well main

  19. Slide 19: Murchison Portfolio - Burnakura

    Murchison Portfolio - Burnakura Existing Plant & Infrastructure = Cash Generative Restart Option Burnakura Development ▪ Option for plant expansion of up to 750ktpa production Infrastructure ▪ Existing 260,000 tpa CIL processing plant well maintained with a fully commissioned operational camp ready

  20. Slide 20: Murchison Portfolio - Gabanintha

    Murchison Portfolio - Gabanintha Gabanintha Development ▪ Planning to complete a full review of historical maps and reports for Gabanintha project ▪ Additional pit mapping and structural interpretation of the main Gabanintha pit area will be completed to assist in drill hole targeting underneath the

  21. Slide 21: Murchison Resources

    Murchison Resources (1) Small discrepancies may occur due to rounding. (2) All Mineral Resources have been reported on a dry tonnage basis. (3) SRK is unaware of any issues that materially affect the Mineral Resources in a detrimental sense. (4) Mineral Resources that are not Mineral Reserves do not

  22. Slide 22: Murchison Portfolio Development Strategy

    Murchison Portfolio Development Strategy Developing A Potential Cornerstone Asset Three Prospective Tenements: ▪ Burnakura 123.1km², 381 koz (NI 43-101), 260kpta CIL plant ▪ Gabanintha 43.4km², 153 koz (JORC Historic) ▪ Tuckanarra (20% MMY) 63.7km², 81 koz (JORC Historic) Exploration ▪ AUD10m commit

  23. Slide 23: Murchison 2-year Exploration Program

    Murchison 2-year Exploration Program Program aims to discover significant additional resources to establish Murchison as a cornerstone project for the Company ▪ COMPLETED-Phase 1 RC and AC drill program comprised 3,465m in 46 RC holes and 10,484m in 349 AC holes, designed to test new targets away fr

  24. Slide 24: Investor Relations Contact

    Investor Relations Contact: Richard Cushing Monument Mining Ltd. T: +1-604-638-1661 x102 rcushing@monumentmining.com TSX–V MMY