Galan Lithium Limited · ASX:GLN

Galan Lithium — Investor Presentation (July 2023)

15 slides from Galan Lithium's investor presentation, Jul 5, 2023

  1. Slide 1: Accelerated Production for Galan's High-Grade Lithium Brine Projects in Argentina

    For personal use only ACCELERATED PRODUCTION FOR GALAN’S HIGH-GRADE LITHIUM BRINE PROJECTS IN ARGENTINA July 2023 ASX:GLN | FSX:9CH galanlithium.com.au 1

  2. Slide 2: Disclaimers & Important Information

    Disclaimers & Important Information This presentation has been prepared by Galan Lithium Limited. Competent Persons The information contained herein that relates to exploration results and geology is based on information compiled or reviewed by Dr Luke Milan, who has consulted to the Company. Dr Mil

  3. Slide 3: The Premier Lithium Developer

    The Premier Lithium Developer For personal use only Production target of 60ptpa World-class location LCE by 2030 Low risk and rapid project Strong local community and delivery government support Work commenced from initial Highly experienced team permits granted Investor presentation 3

  4. Slide 4: Corporate Snapshot

    Corporate Snapshot Strong cash liquidity, tight share register Market Capitalisation Share Price (4 July ‘23) Major Shareholders For personal use only A$318m A$0.95 A$/share Shares on Issue 2.5 2.3 336.9m 2.1 1.9 Cash/Investments 1.7 1.5 A$44m 1.3 1.1 Directors & Top 20 Unquoted Securities 0.9 Manag

  5. Slide 5: World-Class Location

    World-Class Location Highly strategic positioning 25+ year history of production within salar For personal use only Significant regional infrastructure and investment with excellent government and community support Hombre Muerto West (HMW) and Candelas projects – highest grade, lowest impurity lithi

  6. Slide 6: Low Risk – Staged, Flexible Production Plan

    Low Risk – Staged, Flexible Production Plan Fast track route to Li production Targeting first-phase HMW Li concentrate production in H1 CY25 For personal use only Phase 1 – >5ktpa LCE Phase 2 – 20ktpa LCE Phase 3 – 40ktpa LCE Phase 4 – 60ktpa LCE DFS and development initial DFS and permits expected

  7. Slide 7: Phase 1 DFS Delivered and Initial Permits Granted

    Low Risk - Staged, Flexible Production Plan Phase 1 DFS Delivered and Initial Permits Granted DFS announced 3 July 2023; compelling economics for 5.37ktpa LCE production For personal use only Targeting a high end, 6% concentrated lithium chloride product (equivalent to 12.9% Li2O or 31.9% LCE) in H1

  8. Slide 8: Initial Permits Granted – Works Commenced

    Initial Permits Granted – Works Commenced Initial Phase 1 HMW development permits granted Friday 23 June 2023 * For personal use only Top-soil removal for pond construction commenced Permit includes all earthworks required for ground pond testing and camp extension Full construction permits and comm

  9. Slide 9: Compelling Phase 1 DFS Economic Outcomes

    Low Risk – Staged, Flexible Production Plan Compelling Phase 1 DFS Economic Outcomes Flagship HMW Project 100% ownership Definitive Feasibility Study - July 2023 (1) UoM Result For personal use only Proven processing route Project life Years 40 Production of 5.37ktpa Li2CO3 Steady state lithium carb

  10. Slide 10: Highly Experienced Team

    Highly Experienced Team With a proven track record For personal use only Richard Homsany JP Vargas de la Vega Daniel Jimenez Terry Gardiner Claudia Pohl Non-Executive Chairman Founder & Managing Director Non-Executive Director Non-Executive Director Non-Executive Director • Experienced corporate law

  11. Slide 11: Highly Experienced Team

    Highly Experienced Team A strong and talented group of professionals with world class knowledge and extensive local experience For personal use only Juan Carlos Barerra Boris Caro Alvaro Henriquez Francisco Lopez Pablo Sanz Project & Board Consultant Project Advisor/Director Group Geology Manager Ex

  12. Slide 12: The Premier Lithium Developer

    The Premier Lithium Developer For personal use only Strong local community and Strong local team, including ex The best Lithium project in Argentina government support, evidenced SQM team, experienced in (high grade, low impurities) – and the by recent grant of initial permits Lithium project execut

  13. Slide 13: Contact

    Contact ACN 149 349 646 ASX : GLN | FSX : 9CH Juan Pablo (“JP”) Vargas de la Vega For personal use only Managing Director Email: jp@galanlithium.com.au Tel: +61 8 9214 2150 Terry Gardiner Non-Executive Director Email: TGardiner@galanlithium.com.au Tel: + 61 400 900 377 Jane Morgan Investor and Media

  14. Slide 14: Appendix 1: Mineral Resource Estimate

    Appendix 1: Mineral Resource Estimate Mineral Resource Statement for Candelas1 Mineral Resource Statement for Hombre Muerto West2 In situ Li Avg. Li LCE Avg. K In situ K KCl In situ Li Avg. Li LCE Avg. K In situ K KCl For personal use only Category (kt) (mg/l) (kt) (mg/l) (kt) Equiv. Category (kt) (

  15. Slide 15: Appendix 2: Ore Reserve Statement

    Appendix 2: Ore Reserve Statement Ore Reserve Statement for Hombre Muerto West (effective date 3 July 2023) Production Period Pumped Brine Vol. Recovered Li Metal Reserve Category Avg. Li Grade (mg/l) LCE (Kt) For personal use only (years) (Mm3) (Kt) Proven 1-10 19.7 17.8 901.6 53.7 Probable 11-40 5

Galan Lithium — Investor Presentation (July 2023) on 6ix