Slide 1: Developing the Next Tier 1 Gold & Silver Mine
Developing the Next Tier 1 Gold & Silver Mine Corporate Presentation March 2026 TSX: SKE | NYSE: SKE www.skeenagoldsilver.com
Slide 2: Forward Looking Statements
Certain statements and information contained or incorporated by reference in this news release constitute “forward-looking information” and “forward-looking statements” within the meaning of Forward applicable Canadian and United States securities legislation (collectively, “forward-looking statemen
Slide 3: Eskay Creek is a Cashflow Focused Gold & Silver Mine
Eskay Creek is a Cashflow Focused Gold & Silver Mine Large -Scale Gold & High Low Operating Robust Cashflow & Major Construction Silver Production Gold Grade Costs Profitability Underway 450,000 gold equivalent 5.5 gpt gold equivalent in US$538 per oz AISC Projected annual after -tax free On schedul
Slide 4: Rigorous Permitting Process Completed
R igorous Permitting “A collaborative effort drawing on leadership from Tahltan Nation, community comments, regulators and Skeena’s expert team.” Process Completed Nalaine Morin SVP, Environment & Social Affairs EA 180 Day Revised 180 Day IBA Vote S ection 7 EA Major Certificate Review Application R
Slide 5: Our Track Record of Delivering on Commitments in our Journey to Production
Our Track Record of Delivering on Commitments in our Journey to 2026 -2027 Production 2023 -2025 2019 -2022 2016 -2018 Received all permits for construction Improved Definitive Feasibility Study Full scale construction Secured project financing Publish updated NI 43-101 to Upgraded resource commitme
Slide 6: The Golden Triangle in BC: World Leading Mining Jurisdiction
Projects The Golden Triangle TAHLTAN TERRITORY Operations Dease Lake in BC: World Leading Mining Jurisdiction Telegraph Creek SADDLE Newmont RED CHRIS Newmont Fully Permitted IBA Completed with SCHAFT CREEK Environmental Assessment Certificate Tahltan Nation Teck & Major Mines Permit received follow
Slide 7: Existing Infrastructure Provides Substantial Cost Savings
Existing Infrastructure FORREST BOB QUINN AIRSTRIP B Provides Substantial MCLYMONT KERR A VOLCANO Cost Savings CREEK CREEK SNIP C ESKAY Access & transport CREEK 37 D + Connected via Highway 37 for all -weather access + 60 km from Highway, accessible via service road + 253 km from Port of Stewart Pow
Slide 8: Exceptional Economics Drive Cashflow & Fast Payback
Exceptional Economics Payback (Years) Drive Cashflow & 1.2 < 8 months < 7 months Fast Payback $14,000 NPV(5%) $C IRR 138% 140% Annual Financial Metrics (Years 1 -5) at $12,000 114 % Spot Prices ($CAD) 120% $10,000 100% $8,000 $ 3. 1 Billion $ 2.9 Billion 80% (2) Annual EBITDA (2) $6,000 Annual reven
Slide 9: Front Loaded Production Profile Driven by Grade
Front Loaded Production Profile 800 Opportunities to backfill Driven by Grade 700 6.2 gpt 6.0 gpt production profile with satellite deposits in the area 5.5 gpt 600 5.1 gpt 4.6 gpt 4.2 gpt 4.0 gpt 450,000oz 5.5 gpt gold 500 Elevated annual gold Elevated gold 2.4 gpt 2.6 gpt equivalent production equ
Slide 10: Flexible Funding Approach to Support Project Timeline
Flexible Funding Approach to Support Project Timeline GOLD STREAM: FULLY DRAWN EQUITY INVESTMENT: BRIDGE CAPITAL SENIOR SECURED LOAN COST CONTINGENCY US$200M C $143.8M US$350M US$100M Fully Drawn in 2025: Equity Bridge Capital was raised in + Receipt of the Major Mines Act + Optional cost over -run
Slide 11: World Class Gold Grade & Scale
World Class Gold Top global open -pit gold mines by grade ( gpt ) (3) Grade & Scale Kekura (Highland Gold) Eskay Creek (Y1-5) Salares Norte (Gold Fields) 5.4 5.5 7.0 Meliadine (Agnico Eagle) 5.3 Kyzyl (Solidcore) 5.1 Eskay Creek 3.6 Veduga (Solidcore) 3.4 PROVEN & PROBABLE GOLD RESERVES Loulo (Barri
Slide 12: Eskay Creek is Canada's Largest Silver Mine
Eskay Creek is Top global primary silver production (2) Canada’s Largest Saucito (Fresnillo) Cannington (South32) San Julian (Fresnillo) 11.8 12.7 14.5 Silver Mine Pirquitas (SSR Mining) Uchucchacua (Buenaventura) Juanicipio (Fresnillo's 56% stake) 10.5 10.5 10.4 Fresnillo (Fresnillo) 10.2 Eskay Cre
Slide 13: Bulk Earthworks & Mining
Bulk Earthworks & Mining Majority of mining is performed with in -house expertise Mining the North Pit MRSA Water Collection Pond 13
Slide 14: Haul Road & Komatsu Fleet
Haul Road & Komatsu Fleet 14
Slide 15: Process Plant Progress
Process Plant Progress September 2025 December 2025 15
Slide 16: Process Plant - Interiors
Process Plant - Interiors SAG mill pedestals Rebar for slab adjacent to mills 16
Slide 17: Waste & Water Management
Waste & Water Management February 2026 17
Slide 18: Volcano Creek Substation
Volcano Creek Substation Concrete pedestals for ringbus complete Backfill complete 18
Slide 19: New Employee Camp Location
New Employee Camp Location February 2026 19
Slide 20: Significant Re-rate Ahead as Eskay Creek Achieves Production
Significant Re -rate Lundin Gold (1) Ahead as Eskay Creek Artemis Gold (1) 2026E production: 508k oz Au 2026E FCF: C $1.9 billion 2026E production: 290k oz Au Achieves Production 2026E OCF: C $ 726 million Market cap of C$ 9 .5B P/NAV = 0.7x Market cap of C$ 29 B P/NAV = 2.2 x (2,3) Skeena Gold & Si
Slide 21: Strong Shareholder Support
Strong Shareholder Support Research Coverage Shareholders Agentis Michael Gray Helikon Investments Ltd. 13.1% Retail/Public Insiders BMO Andrew Mikitchook Deutsche Balaton AG 9.0% 33% 2% CIBC Luke Bertozzi TD Wayne Lam Van Eck 4.0% Canaccord Jeremy Hoy Tidal Investments (SILJ) 2.6% Desjardins Alliso
Slide 22: Connect with Investor Relations for More Insights
CONNECT WITH INVESTOR RELATIONS FOR MORE INSIGHTS info@skeenagold.com March 2026 skeenagoldsilver.com Follow us on social:
Slide 23: A BC Leadership Team
A BC Leadership Team Walter Coles Randy Reichert Andrew Nalaine Morin Justin Deep development expertise Executive Chairman Chief Executive Officer SVP, Environment & with the correct management MacRitchie Himmelright Chief Financial Officer Social Affairs SVP, External Affairs team in place Kanako G
Slide 24: Mineral Reserves & Mineral Resource Estimates
Mineral Reserves & Mineral Resource Estimates Eskay Creek Resources & Reserves – Pit -constrained (as of December 31, 2023) Tonnes Au Ag AuEq Au oz Ag oz AuEq Oz (Mt) (gpt) (gpt) (gpt ) (Moz) (Moz) (Moz) Mineral Reserves Proven 28.0 3.0 80.9 4.1 2.7 72.7 3.7 Probable 11.9 1.8 40.1 2.3 0.7 15.3 0.9 T
Slide 25: Mineral Resource Estimate
Mineral Resource Estimate Eskay Creek Resources – Underground (as of December 31, 2023) Tonnes Au Ag AuEq Au oz Ag oz AuEq Oz (000) (gpt) (gpt) (gpt ) (Koz) (Koz) (Koz) Mineral Resources Measured 834 5.3 142.6 7.3 142 3,830 196 Indicated 988 4.1 55.7 4.9 131 1,768 156 Total Measured + Indicated Reso
Slide 26: Non-IFRS Measures
Non -IFRS Measures Non -IFRS Measures This presentation refers to various non -IFRS measures, such as “AISC", “total cash costs per ounce sold”, “average realized pric e per ounce sold” and “free cash flow”. These measures do not have a standardized meaning prescribed by IFRS as an indicator of perf